Project ID | 625 |
Agency Name | Brazoria County |
Project Title | Pearland Parkway extension |
Facility/Street/Highway | Pearland Parkway |
Limits | from Dixie Farm to FM 2351 |
Description | Extend Pearland Parkway from Dixie Farm Road to FM 2351 (as a four-lane, median divided roadway) to improve mobility within Brazoria County and provide an additional north/south route parallel to SH 35 to reduce congestion. |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $35,000,000.00 |
High Growth Area Needs Questionnaire | View Questionnaire |
Operational Improvements and Congestion Management Questionnaire | View Questionnaire |
Resiliency and State of Good Repair Questionnaire | View Questionnaire |
Project ID | 626 |
Agency Name | Brazoria County |
Project Title | CR 100 extension |
Facility/Street/Highway | County Road 100 |
Limits | from CR 113 to SH 35 |
Description | Construct 2-lane roadway and 2-lane grade separation crossing at existing railroad. |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $16,600,000.00 |
High Growth Area Needs Questionnaire | View Questionnaire |
Operational Improvements and Congestion Management Questionnaire | View Questionnaire |
Resiliency and State of Good Repair Questionnaire | View Questionnaire |
Project ID | 627 |
Agency Name | Brazoria County |
Project Title | CR 64 widening (both east and west – but east is mostly City) - Medium Term |
Facility/Street/Highway | County Road 64 |
Limits | from SH 288 to CR 65 |
Description | Construct 10-foot shoulders along CR 64 from SH 288 to CR 65 to offset fixed objects from the travel way. |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $2,976,000.00 |
Project ID | 628 |
Agency Name | Brazoria County |
Project Title | CR 64 widening (both east and west – but east is mostly City) - Short Term |
Facility/Street/Highway | County Road 64 |
Limits | from SH 288 to CR 65 |
Description | Construct 10-foot shoulders along CR 64 from SH 288 to CR 65 to offset fixed objects from the travel way. |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $4,000,000.00 |
Project ID | 629 |
Agency Name | Brazoria County |
Project Title | CR 44 improvements |
Facility/Street/Highway | County Road 44 |
Limits | FM 521 to SH 288 |
Description | Install signage to warn drivers of roadway conditions and rumble strips to improve safety along CR 44 from FM 521 to W Wilkins Street. Construct 10-foot shoulders along CR 44 from SH 288 to FM 521 to offset fixed objects from the travel way and improve sight distance at intersections and driveways. |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $6,500,000.00 |
High Growth Area Needs Questionnaire | View Questionnaire |
Operational Improvements and Congestion Management Questionnaire | View Questionnaire |
Resiliency and State of Good Repair Questionnaire | View Questionnaire |
Project ID | 630 |
Agency Name | Brazoria County |
Project Title | CR 44 improvements - Short Term |
Facility/Street/Highway | County Road 44 |
Limits | FM 521 to SH 288 |
Description | Install signage to warn drivers of roadway conditions and rumble strips to improve safety along CR 44 from FM 521 to W Wilkins Street. Construct 10-foot shoulders along CR 44 from SH 288 to FM 521 to offset fixed objects from the travel way and improve sight distance at intersections and driveways. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $35,000.00 |
Project ID | 631 |
Agency Name | Brazoria County |
Project Title | CR 44 improvements |
Facility/Street/Highway | County Road 44 |
Limits | SH 288 to Loop 274 |
Description | Install signage to warn drivers of roadway conditions and rumble strips to improve safety along CR 44 from SH 288 to Loop 274. Construct 10-foot shoulders along CR 44 from SH 288 to Loop 274 to offset fixed objects from the travel way and improve sight distance at intersections and driveways. |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $5,500,000.00 |
High Growth Area Needs Questionnaire | View Questionnaire |
Operational Improvements and Congestion Management Questionnaire | View Questionnaire |
Resiliency and State of Good Repair Questionnaire | View Questionnaire |
Project ID | 632 |
Agency Name | Brazoria County |
Project Title | CR 44 improvements - Short Term |
Facility/Street/Highway | County Road 44 |
Limits | SH 288 to Loop 274 |
Description | Install signage to warn drivers of roadway conditions and rumble strips to improve safety along CR 44 from SH 288 to Loop 274. Construct 10-foot shoulders along CR 44 from SH 288 to Loop 274 to offset fixed objects from the travel way and improve sight distance at intersections and driveways. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $28,900.00 |
Project ID | 633 |
Agency Name | Brazoria County |
Project Title | CR 353/359 improvements - Medium Term |
Facility/Street/Highway | County Road 353 and County Road 359 |
Limits | FM 522 to CR 348FM 524 to FM 1459 |
Description | Install signage to warn drivers of roadway conditions, install rumble strips, and clear vegetation along CR 353 from FM 522 to CR 348 to improve safety. Construct 10-foot shoulders and widen travel lanes to be 12 feet wide along CR 353 from FM 522 to CR 348 and along CR 359 from FM 1459 to FM 524 |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $2,283,300.00 |
Project ID | 634 |
Agency Name | Brazoria County |
Project Title | CR 353/359 improvements - Short Term |
Facility/Street/Highway | County Road 353 and County Road 359 |
Limits | FM 522 to CR 348FM 524 to FM 1459 |
Description | Install signage to warn drivers of roadway conditions, install rumble strips, and clear vegetation along CR 353 from FM 522 to CR 348 to improve safety. Construct 10-foot shoulders and widen travel lanes to be 12 feet wide along CR 353 from FM 522 to CR 348 and along CR 359 from FM 1459 to FM 524 |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $404,000.00 |
Project ID | 635 |
Agency Name | Brazoria County |
Project Title | CR 59 widening - Medium Term |
Facility/Street/Highway | County Road 59 |
Limits | West of CR 48 |
Description | Construct 10-foot shoulders from the Fort Bend County Line to CR 48 and from Kirby Drive to SH 288 to offset fixed objects from the travel way. Construct turn bays to allow for safe deceleration at CR 564. |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $4,331,000.00 |
Project ID | 636 |
Agency Name | Brazoria County |
Project Title | CR 59 widening - Short Term |
Facility/Street/Highway | County Road 59 |
Limits | West of CR 48 |
Description | Construct 10-foot shoulders from the Fort Bend County Line to CR 48 and from Kirby Drive to SH 288 to offset fixed objects from the travel way. Construct turn bays to allow for safe deceleration at CR 564. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $95,000.00 |
Project ID | 637 |
Agency Name | Chambers County |
Project Title | Chambers Parkway |
Facility/Street/Highway | Chambers Parkway |
Limits | Approx. 0.5 mi. south of I10 from S.H. 146 to F.M. 3180 |
Description | Reconstruction of existing 2 lane roadway. Along with construction of a new 4 lane roadway. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $30,000,000.00 |
Regional Goods Movement Questionnaire | View Questionnaire |
Project ID | 638 |
Agency Name | Chambers County |
Project Title | Kilgore Parkway Widening |
Facility/Street/Highway | Kilgore Parkway |
Limits | From SH 99 East to FM 3180 |
Description | Widen from 2 to 4 lanes with center turn lane |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $4,000,000.00 |
Project ID | 639 |
Agency Name | Chambers County |
Project Title | NEEDLEPOINT RD |
Facility/Street/Highway | Needlepoint Rd |
Limits | From IH-10 south to FM 565 |
Description | Reconstruction widen from 2 to 4 lanes |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $8,000,000.00 |
Regional Goods Movement Questionnaire | View Questionnaire |
Project ID | 640 |
Agency Name | Chambers County |
Project Title | Jonnie G Jennings Dr |
Facility/Street/Highway | Jonnie G Jennings Dr |
Limits | From FM 1405 East to FM 2354 |
Description | Construct 2 lane concrete freight roadway |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $10,000,000.00 |
Regional Goods Movement Questionnaire | View Questionnaire |
Project ID | 641 |
Agency Name | Chambers County |
Project Title | Belton Lane Extinsion Widen |
Facility/Street/Highway | Belton Lane Extension |
Limits | From FM 563 to FM 562 |
Description | Widen roadway to include turn lanes and sidewalks in front of new school |
Timeframe | |
Estimated Cost | $6,000,000.00 |
Project ID | 642 |
Agency Name | Chambers County |
Project Title | Hatcherville RD |
Facility/Street/Highway | Hatcherville RD |
Limits | From Liberty County to FM 1942 |
Description | Full depth repairs and replace asphalt pavement to concrete |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $2,750,000.00 |
Project ID | 643 |
Agency Name | Chambers County |
Project Title | Bayer Road |
Facility/Street/Highway | Bayer Road |
Limits | From FM 1405 to 6,185 ft North |
Description | Reconstruction of asphalt road to industrial standards |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $4,100,000.00 |
Project ID | 644 |
Agency Name | Chambers County |
Project Title | West Bay Road |
Facility/Street/Highway | West Bay Road |
Limits | From SH 99 to Bayer Road |
Description | Reconstruction of asphalt road to industrial standards |
Timeframe | Long Term (More than 10 Years) |
Estimated Cost | $3,600,000.00 |
Project ID | 645 |
Agency Name | Chambers County |
Project Title | Rhonda Rosa |
Facility/Street/Highway | Rhonda Rosa |
Limits | At Turtle Bayou |
Description | Replace Bridge Class Culvert |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $500,000.00 |
Project ID | 646 |
Agency Name | City of Angleton |
Project Title | Henderson Road Improvement Project |
Facility/Street/Highway | Henderson Road |
Limits | From SH 288B to SH 35 |
Description | This project will improve the modlity and safety for bike, pedestrian, and vechicular movements in a cooridor with an existing school and significant amount of new development. The City has perform a cooridor study and identifed that the two lane roadway is insufficent and does is required to be converted into a boulavard section with sidewalks/shared paths and several signalized intersection. Associated drainage improvements will be required to install this boulevard cross-section and improve the drainage in the area. |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $51,600,000.00 |
High Growth Area Needs Questionnaire | View Questionnaire |
Operational Improvements and Congestion Management Questionnaire | View Questionnaire |
Project ID | 647 |
Agency Name | City of Angleton |
Project Title | Western Avenue Improvement Project |
Facility/Street/Highway | Western Ave |
Limits | From West Mullberry Street to West Mulbery Street |
Description | This project will improve the paving condition, safety, and drainage in the area |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $3,240,000.00 |
Project ID | 648 |
Agency Name | City of Baytown |
Project Title | Garth Rd Widening Segment D |
Facility/Street/Highway | Garth Rd |
Limits | Archer Rd to SH 146 |
Description | Reconstruction and Widening from 4 to 6 11 ft. lanes with 16 ft. non continuous mediansfor access management and right turns in some locations; 6.5 ft sidewalk on east side and 10 ft shared use path on west side |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $105,000,000.00 |
Major Projects Questionnaire | View Questionnaire |
Project ID | 649 |
Agency Name | City of Baytown |
Project Title | Garth Rd Widening Segment E |
Facility/Street/Highway | Garth Rd |
Limits | N. of Riceland Rd to S. of Baker Rd |
Description | Reconstruction and Widening from 4 to 6 11 ft. lanes with 16 ft. non continuous mediansfor access management and right turns in some locations; 6.5 ft sidewalk on east side and 10 ft shared use path on west side |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $34,600,000.00 |
Project ID | 650 |
Agency Name | City of Baytown |
Project Title | Garth Rd Widening Segment F |
Facility/Street/Highway | Garth Rd |
Limits | N. of Riceland Rd to S. of Baker Rd |
Description | Reconstruction and Widening from 4 to 6 11 ft. lanes with 16 ft. non continuous mediansfor access management and right turns in some locations; 6.5 ft sidewalk on east side and 10 ft shared use path on west side |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $44,700,000.00 |
Project ID | 651 |
Agency Name | City of Baytown |
Project Title | Cedar Bayou Crossing (formerly Hunt Rd) |
Facility/Street/Highway | Cedar Bayou Crossing (formerly Hunt Rd) |
Limits | N. Main St to SH-146 |
Description | Construct new 4 lane roadway connection across Cedar Bayou; with bridge and elevated crossing across railroads to provide alternate evacuation route. |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $230,000,000.00 |
Project ID | 652 |
Agency Name | City of Baytown |
Project Title | W Baker Rd Reconstruction |
Facility/Street/Highway | W Baker Rd |
Limits | Garth Rd to Decker Dr |
Description | Reconstruct pavement section, including drainge improvments. Reduce median width to improve sight distance and safety. |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $78,500,000.00 |
Project ID | 653 |
Agency Name | City of Baytown |
Project Title | Lee Drive Revitalization |
Facility/Street/Highway | Lee Dr |
Limits | Market St to SH-99 |
Description | Reconfigure cross section to include reconstruction of 2 lane roadwy with a 12-ft shared-use path separated by a vegetative buffer, pedestrian signals and improvements to signalized intersections. |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $51,800,000.00 |
Project ID | 654 |
Agency Name | City of Bellaire |
Project Title | Traffic Management System |
Facility/Street/Highway | Multiple (Bellaire Blvd, Bissonnet St, South Rice Ave, Newcastle St, Chimney Rock Rd, Fournace Pl) |
Limits | From Limit: CHIMNEY ROCK TO NEWCASTLE; CHIMNEY ROCK TO NEWCASTLE To Limit : FOURNACE PLACE TO BEECHNUT; BISSONNET TO BEECHNUT |
Description | INSTALLATION FIBER OPTIC CABLE AND WIRELESS COMMUNICATION TO SUPPORT CLOSED-CIRCUIT (CCTV) CAMERAS, DYNAMIC MESSAGE SIGNS AND LOOP DETECTOR SENSORS AT 14 EXISTING TRAFFIC SIGNALS MAINTAINED BY THE CITY OF BELLAIRE. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $1,117,925.00 |
Project ID | 655 |
Agency Name | City of Bellaire |
Project Title | Traffic Signal Timing Optimization Program |
Facility/Street/Highway | Multiple (Bellaire Blvd, Bissonnet St, South Rice Ave, Newcastle St, Chimney Rock Rd, Fournace Pl) |
Limits | From Limit: VA To Limit : VA |
Description | TRAFFIC SIGNAL TIMING OPTIMIZATION PROGRAM FOR THE CITY OF BELLAIRE |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $1,002,246.00 |
Project ID | 656 |
Agency Name | City of Bellaire |
Project Title | Pavement Conditions Analysis |
Facility/Street/Highway | All roadways maintained by Bellaire |
Limits | All roadways maintained by Bellaire |
Description | STUDY TO DETERMINE CONDITIONS OF BELLAIRE ROADWAYS TO ASSIST IN REPAIR/REPLACEMENT PLANNING |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $75,000.00 |
Project ID | 657 |
Agency Name | City of Bellaire |
Project Title | Speed Study |
Facility/Street/Highway | All roadways maintained by Bellaire |
Limits | All roadways maintained by Bellaire |
Description | ANALYSIS OF TRAFFIC FLOW TO DETERMINE IF SPEED LIMITS NEED TO BE UPDATED. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $50,000.00 |
Project ID | 658 |
Agency Name | City of Conroe |
Project Title | Airport Road Widening |
Facility/Street/Highway | Airport Road |
Limits | FM 1314 / Porter Rd to FM 3083 |
Description | Widen existing two-lane road (no sidewalks) to four lane with sidewalks. Scope includes stormwater, water, and wastewater. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $22,000,000.00 |
High Growth Area Needs Questionnaire | View Questionnaire |
Operational Improvements and Congestion Management Questionnaire | View Questionnaire |
Regional Goods Movement Questionnaire | View Questionnaire |
Resiliency and State of Good Repair Questionnaire | View Questionnaire |
Project ID | 659 |
Agency Name | City of Conroe |
Project Title | Foster Drive Widening |
Facility/Street/Highway | Foster Drive |
Limits | S. Frazier St / N. Porter Rd. |
Description | Widen existing two-lane road (no sidewalks) to four lane with sidewalks. Scope includes stormwater, water, and wastewater. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $30,000,000.00 |
High Growth Area Needs Questionnaire | View Questionnaire |
Operational Improvements and Congestion Management Questionnaire | View Questionnaire |
Resiliency and State of Good Repair Questionnaire | View Questionnaire |
Project ID | 660 |
Agency Name | City of Conroe |
Project Title | Commuter Bus Purchase |
Facility/Street/Highway | N/A |
Limits | N/A |
Description | Purchase four (4) commuter bus vehicles. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $4,500,000.00 |
Project ID | 661 |
Agency Name | City of Conroe |
Project Title | Old Conroe Road |
Facility/Street/Highway | Old Conroe Road |
Limits | FM 1488 to S LP 336 |
Description | Widening of Old Conroe Road to four (4) lanes and extending the roadway to include a bridge over the west fork of the San Jacinto River. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $125,000,000.00 |
Project ID | 662 |
Agency Name | City of Dickinson |
Project Title | Dickinson Ave./FM 1266 Safety Improvements |
Facility/Street/Highway | Dickinson Avenue / FM 1266 |
Limits | FM 646 to FM 517 |
Description | The improvement will be a full reconstruction of the roadway including the addition of street lighting, sidewalk facilities, and upgrades to signalized intersection at Deats Road. To accommodate the addition of sidewalks, the existing open ditches will be replaced with culverts. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $15,000,000.00 |
High Growth Area Needs Questionnaire | View Questionnaire |
Operational Improvements and Congestion Management Questionnaire | View Questionnaire |
Regional Goods Movement Questionnaire | View Questionnaire |
Resiliency and State of Good Repair Questionnaire | View Questionnaire |
Project ID | 663 |
Agency Name | City of Dickinson |
Project Title | Dickinson High School Pedestrian Enhancements |
Facility/Street/Highway | FM 517 |
Limits | Baker Drive to Owens Drive |
Description | The improvements will include upgrades to the signalized intersection at Owens Drive such as wider sidewalks, updated pedestrian ramps, pedestrian signalization, and enhanced crosswalks. Wider sidewalks will be constucted along FM 517 and improvements will be made to existing midblock crossing at Meadow Glen Drive. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $1,500,000.00 |
Project ID | 664 |
Agency Name | East Aldine Management District |
Project Title | Bikeways on Aldine Mail Route |
Facility/Street/Highway | Aldine Mail Route Road |
Limits | US 59 and Hardy Toll Road |
Description | The proposed improvements include the addition of a 10' sidepath on both side of the corridor. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $9,000,000.00 |
Project ID | 665 |
Agency Name | East Aldine Management District |
Project Title | Greens Bayou Greenway Trail |
Facility/Street/Highway | Greens Bayou |
Limits | Hardy Toll Road to BW 8 to US 59/Homestead |
Description | Construct off street trail along Greens Bayou requiring on crossing at signalized intersection and construction of 1 bridge facility. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $11,000,000.00 |
Project ID | 666 |
Agency Name | East Aldine Management District |
Project Title | Enhance Halls Bayou Trail |
Facility/Street/Highway | Halls Bayou |
Limits | Hardy Toll Road to Keith Wiess Park (southern edge) |
Description | Construct off street trail along Halls Bayou including construction of 1 bridge facility. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $4,000,000.00 |
Project ID | 667 |
Agency Name | East Aldine Management District |
Project Title | Hopper Road Complete Street |
Facility/Street/Highway | Hopper Road |
Limits | US 59 to Aldine Westfield Road |
Description | Retrofit Hopper Road within existing ROW to have one travel lane in each direction with bicycle and pedestrian facilities on both sides. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $6,000,000.00 |
Project ID | 668 |
Agency Name | East Aldine Management District |
Project Title | Bayou Community Trail |
Facility/Street/Highway | off-street |
Limits | Greens Bayou to Aldine Town Center |
Description | Construct off street trail along drainage facility between Greens Bayou and the Aldine Town Center. |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $4,000,000.00 |
Project ID | 669 |
Agency Name | Friendswood |
Project Title | Friendswood Parkway / Pearland Parkway |
Facility/Street/Highway | Funding will cover street construction, storm sewer and detention if needed |
Limits | FM 528 to FM 2351 |
Description | Funding will cover street construction, storm sewer and detention if needed |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $14,312,700.00 |
Project ID | 670 |
Agency Name | Friendswood |
Project Title | FM518 at FM 528 Intersection (Phase I) |
Facility/Street/Highway | S. Friendswood Drive/FM 528 at E. Parkwood Drive/FM 528. |
Limits | FM 518 at FM 528 |
Description | Phase 1 includes dual left-turn lanes along FM 518 and optimization of traffic signal timing. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $396,000.00 |
Project ID | 671 |
Agency Name | Friendswood |
Project Title | FM 528 at Sunset Intersection (Phase 1) |
Facility/Street/Highway | W. Parkwood Drive/FM 528 at Sunset Drive |
Limits | FM 528 at Sunset |
Description | Restripe southbound Sunset Drive approach to have a dedicated left-turn lane and a shared left/through lane. Optimize traffic signal timings. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $55,000.00 |
Project ID | 672 |
Agency Name | Friendswood |
Project Title | FM 518 at FM 2351 Intersection (Phase 1) |
Facility/Street/Highway | N. Friendswood Dr/FM 518 at E. Edgewood Dr/FM 2351 |
Limits | FM 518 at FM 2351 |
Description | Left-turns extension on all approaches Southbound right-turn lane |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $374,000.00 |
Project ID | 673 |
Agency Name | Friendswood |
Project Title | FM 528 at Bay Area Blvd Intersection (Phase 1) |
Facility/Street/Highway | FM 528 at Bay Area Blvd (Blackhawk Blvd Extension) |
Limits | FM 528 at Bay Area Blvd |
Description | Add a through that extends 500 feet north and south of the intersection. Dual eastbound and westbound left-turn lanes. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $1,067,000.00 |
Project ID | 674 |
Agency Name | Friendswood |
Project Title | E. Parkwood Drive/FM 528 at Winding Way Intersection (Phase 1) |
Facility/Street/Highway | E. Parkwood Dr/FM 528 at Winding Way Dr |
Limits | E. Parkwood Drive/FM 528 at Winding Way |
Description | Optimize traffic signal timings |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $8,250.00 |
Project ID | 675 |
Agency Name | Friendswood |
Project Title | Blackhawk Boulevard Phase IIC |
Facility/Street/Highway | FM 2351 to Geneva Drive, Thursa Lane to FM 528 |
Limits | FM 2351 to Geneva Drive, Thursa Lane to FM 528 |
Description | Funding will cover street construction and Utilities |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $7,535,402.00 |
Project ID | 676 |
Agency Name | Friendswood |
Project Title | Friendswood Parkway / Pearland Parkway |
Facility/Street/Highway | Funding will cover street construction, storm sewer and detention if needed |
Limits | FM 2351 to Pearland Parkway |
Description | Funding will cover street construction, storm sewer and detention if needed |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $12,043,485.00 |
Project ID | 677 |
Agency Name | Friendswood |
Project Title | FM518 at FM 528 Intersection (Phase 2) |
Facility/Street/Highway | S. Friendswood Drive/FM 528 at E. Parkwood Drive/FM 528. |
Limits | FM 518 at FM 528 |
Description | Phase 2 includes dual left-turn lanes to match length of existing left-turn lanes on the eastbound and westbound FM 528 approaches and optimization of traffic signal timings |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $385,000.00 |
Project ID | 678 |
Agency Name | Friendswood |
Project Title | FM 528 at Sunset Intersection (Phase 2) |
Facility/Street/Highway | W. Parkwood Drive/FM 528 at Sunset Drive |
Limits | FM 528 at Sunset |
Description | Widening of Sunset Drive approach to include dual left-turn lanes on southbound Sunset Drive approach. Proposed lane configuration would consist of exclusive left-turn lane, a shared left-turn/through lane, and an exclusive right-turn lane. Optimization fo signal timings. |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $209,000.00 |
Project ID | 679 |
Agency Name | Friendswood |
Project Title | FM 518 at FM 2351 Intersection (Phase 2) |
Facility/Street/Highway | N. Friendswood Dr/FM 518 at E. Edgewood Dr/FM 2352 |
Limits | FM 518 at FM 2351 |
Description | Westbound right-turn lane |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $187,000.00 |
Project ID | 680 |
Agency Name | Friendswood |
Project Title | FM 528 at Bay Area Blvd Intersection (Phase 2) |
Facility/Street/Highway | FM 528 at Bay Area Blvd (Blackhawk Blvd Extension) |
Limits | FM 528 at Bay Area Blvd |
Description | Blackhawk Blvd extension from FM 528 to Bay Area Blvd |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $5,214,000.00 |
Project ID | 681 |
Agency Name | Friendswood |
Project Title | E. Parkwood Drive/FM 528 at Winding Way Intersection (Phase 2) |
Facility/Street/Highway | E. Parkwood Dr/FM 528 at Winding Way Dr |
Limits | E. Parkwood Drive/FM 528 at Winding Way |
Description | Right turn lane with 100 ft of storage and a 100-foot taper on the northbounds Winding Way Drive approach. Optimize traffic signal timings. |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $187,000.00 |
Project ID | 682 |
Agency Name | Friendswood |
Project Title | FM 2351 at Beamer Rd |
Facility/Street/Highway | FM 2351 at Beamer Rd |
Limits | FM 2351 at Beamer Rd |
Description | Northbound and Southbound right-turn lanes |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $343,200.00 |
Project ID | 683 |
Agency Name | Friendswood |
Project Title | FM518 at FM 528 Intersection (Phase 3) |
Facility/Street/Highway | S. Friendswood Drive/FM 528 at E. Parkwood Drive/FM 528. |
Limits | FM 518 at FM 528 |
Description | Phase 3 includes extending left-turn lanes, 100 feet storage and a 100-ft taper at all approaches, except for the southbound FM 518 approach. Proposed dedicated right-turn lanes on eastbound and wetbound FM 528 approaches with 200-ft storage and 150-ft storage with 100-ft taper, respectively. Extend teh northbound FM 518 right-turn lane, 100 ft storage and 100ft taper. Optimize traffic signal timing. |
Timeframe | Long Term (More than 10 Years) |
Estimated Cost | $1,067,000.00 |
Project ID | 684 |
Agency Name | Friendswood |
Project Title | FM 528 at Sunset Intersection (Phase 3) |
Facility/Street/Highway | W. Parkwood Drive/FM 528 at Sunset Drive |
Limits | FM 528 at Sunset |
Description | Exclusive southbound Sunset Drive right-turn lane with 150 ft storage and 25 ft taper and an easbound FM 528 right-turn lane with 180 ft of storage and a 25-ft taper. Optimization of traffic signal timings. |
Timeframe | Long Term (More than 10 Years) |
Estimated Cost | $214,500.00 |
Project ID | 685 |
Agency Name | Friendswood |
Project Title | FM 528 at Bay Area Blvd Intersection (Phase 3) |
Facility/Street/Highway | FM 528 at Bay Area Blvd (Blackhawk Blvd Extension) |
Limits | FM 528 at Bay Area Blvd |
Description | Southbound right-turn lane |
Timeframe | Long Term (More than 10 Years) |
Estimated Cost | $313,500.00 |
Project ID | 686 |
Agency Name | Friendswood |
Project Title | E. Parkwood Drive/FM 528 at Winding Way Intersection (Phase 3) |
Facility/Street/Highway | E. Parkwood Dr/FM 528 at Winding Way Dr |
Limits | E. Parkwood Drive/FM 528 at Winding Way |
Description | Construct a dedicated westbound FM 528 right-turn lane with 300 feet of storage and a 100-ft taper. Optimize traffic signal timings |
Timeframe | Long Term (More than 10 Years) |
Estimated Cost | $275,000.00 |
Project ID | 687 |
Agency Name | Friendswood |
Project Title | FM 528 Connection to SH 99 |
Facility/Street/Highway | FM 528 Connection to SH 99 |
Limits | FM 528 Connection to SH 99 |
Description | Roadway connection between FM528 and SH99 |
Timeframe | Long Term (More than 10 Years) |
Estimated Cost | $3,014,000.00 |
Project ID | 688 |
Agency Name | City of Galveston |
Project Title | Stewart Road - 61st to 75th Streets: Corridor Improvements |
Facility/Street/Highway | Stewart Road |
Limits | 61st Street to 75th Street |
Description | Full reconstruction of Stewart Road from 61st to 75th Streets to include a two-way left turn lane, pedestrian improvements (e.g. sidewalks, ADA ramps), traffic signal upgrades (i.e. 65th, 68th, 69th and Colony Park Drive), replacement of water and sanitary sewer infrastructure, storm sewer system improvements, and ROW acquisition (if necessary). |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $46,058,000.00 |
Operational Improvements and Congestion Management Questionnaire | View Questionnaire |
Resiliency and State of Good Repair Questionnaire | View Questionnaire |
Transit Questionnaire | View Questionnaire |
Project ID | 689 |
Agency Name | City of Galveston |
Project Title | Avenues O & P: 53rd to Seawall Corridor Safety Improvements |
Facility/Street/Highway | Avenue O & Avenue P |
Limits | 53rd Street to Seawall Blvd |
Description | Install curb extensions, sidewalks and/or a multi-use trail, install ADA ramps, perform traffic signal upgrades, construct storm sewer improvements to accommodate drainage modifications due to improvements made, improve roadway signage and striping for enhanced visibility and safety. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $31,545,000.00 |
Operational Improvements and Congestion Management Questionnaire | View Questionnaire |
Resiliency and State of Good Repair Questionnaire | View Questionnaire |
Transit Questionnaire | View Questionnaire |
Project ID | 690 |
Agency Name | City of Galveston |
Project Title | Intersection Improvements: 33rd Street & Seawall Blvd |
Facility/Street/Highway | Seawall Blvd |
Limits | 33rd Street |
Description | Construct a new Traffic Signal |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $525,000.00 |
Resiliency and State of Good Repair Questionnaire | View Questionnaire |
Project ID | 691 |
Agency Name | City of Galveston |
Project Title | Bicycle Infrastructure Improvements |
Facility/Street/Highway | Citywide |
Limits | |
Description | Implement new bicycle lanes along various roadway corridors within the City including signage and striping. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $355,583.00 |
Resiliency and State of Good Repair Questionnaire | View Questionnaire |
Project ID | 692 |
Agency Name | City of Galveston |
Project Title | Seawall Blvd Traffic: Signal Installation |
Facility/Street/Highway | Seawall Blvd |
Limits | 75th Street & 89th Street |
Description | This proposed project will add: 1) a new traffic signal at the intersection of 75th Street & Seawall Blvd., and 2) a new traffic signal at the intersection of 89th Street & Seawall Blvd. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $957,375.00 |
Resiliency and State of Good Repair Questionnaire | View Questionnaire |
Project ID | 693 |
Agency Name | City of Galveston |
Project Title | Traffic Signal / Safety Improvements |
Facility/Street/Highway | Citywide |
Limits | |
Description | Replace old traffic signal heads, cabinets and controllers; Install new guard rails and battery back ups for traffic signals. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $1,431,111.00 |
Resiliency and State of Good Repair Questionnaire | View Questionnaire |
Project ID | 694 |
Agency Name | City of Galveston |
Project Title | Seawall Blvd: Pedestrian Safety & Traffic Calming Measures (12th to 61st Streets) |
Facility/Street/Highway | Seawall Blvd |
Limits | 12th to 61st Streets |
Description | This proposed project will add: 1) a new low linear barrier along the north side of Seawall Blvd. between 12th & 61st Streets to separate the at grade sidewalk from the adjacent on-street vehicle parking; 2) new traffic calming measures incorporating medians, curb bump outs and high visibility crosswalks at four (4) unsignalized intersections along Seawall Blvd. to reduce speeds along the corridor and enhance pedestrian safety and a new HAWK Pedestrian Crossing in the 5400 Block of Seawall Blvd. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $2,021,277.00 |
Resiliency and State of Good Repair Questionnaire | View Questionnaire |
Project ID | 695 |
Agency Name | City of Galveston |
Project Title | Seawall Blvd: Pedestrian Safety & Traffic Calming Measures (61st to 103rd Streets) |
Facility/Street/Highway | Seawall Blvd |
Limits | 61st to 103rd Streets |
Description | This proposed project will add: 1) a new low linear barrier along the north side of Seawall Blvd. between 61st & 103rd Streets to separate the at grade sidewalk from the adjacent on-street vehicle parking, and 2) new traffic calming measures incorporating medians, curb bump outs and high visibility crosswalks at give (5) intersections along Seawall Blvd. to reduce speeds along the corridor and enhance pedestrian safety. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $1,984,900.00 |
Resiliency and State of Good Repair Questionnaire | View Questionnaire |
Project ID | 696 |
Agency Name | City of Galveston |
Project Title | Downtown Streetscape Improvements |
Facility/Street/Highway | |
Limits | |
Description | Phase 1 includes streetscape improvements to the downtown area of 23rd Street between Harborside and Church. Phase 2 (FY2025) includes streetscape improvements to the downtown area of 22nd Street |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $4,788,113.00 |
Resiliency and State of Good Repair Questionnaire | View Questionnaire |
Transit Questionnaire | View Questionnaire |
Project ID | 697 |
Agency Name | City of Galveston |
Project Title | Traffic Signal at 28th St/SH-275 |
Facility/Street/Highway | SH-275 |
Limits | 28th Street |
Description | Installation of a Traffic Signal at 28th Street and Harborside Drive |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $500,000.00 |
Project ID | 698 |
Agency Name | City of Galveston |
Project Title | Traffic Signal at 33rd St/SH-275 |
Facility/Street/Highway | SH-275 |
Limits | 33rd Street |
Description | Installation of a Traffic Signal at 33rd Street and Harborside Drive |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $500,000.00 |
Project ID | 699 |
Agency Name | City of Galveston |
Project Title | Traffic Signal at 16th St/SH-275 |
Facility/Street/Highway | SH-275 |
Limits | 16th Street |
Description | Installation of a Traffic Signal at 16th Street and Harborside Drive |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $500,000.00 |
Project ID | 700 |
Agency Name | City of Hedwig Village |
Project Title | Hedwig Village Commercial Promenade |
Facility/Street/Highway | Gaylord Drive |
Limits | Campbell Road to Brogden Road and Bunker Hill Drive to Echo Lane |
Description | The project will include the addition of a 12' shared-use path on the north side of Gaylord Drive; a landscaped buffer zone of an additional 12' will also be constructed. The existing sidewalk on the south side of Gaylord will be upgraded to a 6' wide facility. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $3,000,000.00 |
Project ID | 701 |
Agency Name | City of Hedwig Village |
Project Title | Hedwig Village Residential Neighborhood Sidewalk Upgrades |
Facility/Street/Highway | multiple - Denise Drive, Magdelene Street, Taylorcrest Road, Echo Lane, Piney Point Road, Beinhorn Road, Gaylord Drive, Corbindale Road, Hedwig Road, and Brogden Road |
Limits | within City limits |
Description | The project will replace and upgrade existing sidewalks to be 6' wide, upgrade crosswalks, and replace pedestrian ramps. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $8,000,000.00 |
Project ID | 702 |
Agency Name | City of Iowa Colony |
Project Title | Iowa Colony Blvd Expansion and Improvements (North) |
Facility/Street/Highway | Iowa Colony Blvd |
Limits | SH 6 to Meridiana Pkwy |
Description | Improve and expand Iowa Colony Blvd from 2-lane, deteriorated asphalt road to 4-lane concrete boulevard, as identified in the Brazoria County and Iowa Colony Major Thoroughfare Plans. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $33,000,000.00 |
Project ID | 703 |
Agency Name | City of Iowa Colony |
Project Title | Cedar Rapids Pkwy Expansion and Improvements |
Facility/Street/Highway | Cedar Rapids Pkwy (CR57) |
Limits | FM 521 to SH 288 |
Description | Improve and expand Cedar Rapids Pkwy (CR57) to 4-lane concrete boulevard, as identified in the Brazoria County and Iowa Colony Major Thoroughfare Plans. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $11,000,000.00 |
Project ID | 704 |
Agency Name | City of Iowa Colony |
Project Title | Davenport Pkwy Expansion and Improvements (East) |
Facility/Street/Highway | Davenport Pkwy (CR64) |
Limits | SH 288 to Iowa Colony Blvd |
Description | Improve and expand Davenport Pkwy (CR64) to 4-lane boulevard, as identified in the Iowa Colony and Brazoria County Major Thoroughfare Plans. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $6,000,000.00 |
Project ID | 705 |
Agency Name | City of Iowa Colony |
Project Title | Davenport Pkwy Expansion and Improvements (West) |
Facility/Street/Highway | Davenport Pkwy (CR64) |
Limits | Ames Blvd to SH 288 |
Description | Improve and expand Davenport Pkwy (CR64) to 4-lane boulevard, as identified in the Iowa Colony and Brazoria County Major Thoroughfare Plans. |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $11,000,000.00 |
Project ID | 706 |
Agency Name | City of Iowa Colony |
Project Title | Iowa Colony Blvd Expansion and Improvements (South) |
Facility/Street/Highway | Iowa Colony Blvd |
Limits | Davenport Pkwy (Freedom Field) to Dubuque Pkwy (Municipal Government Complex) |
Description | Improve and expand Iowa Colony Blvd from 2-lane, deteriorated asphalt road to 4-lane concrete boulevard, as identified in the Brazoria County and Iowa Colony Major Thoroughfare Plans. |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $13,000,000.00 |
Project ID | 707 |
Agency Name | City of Iowa Colony |
Project Title | Dubuque Parkway Expansion and Improvements |
Facility/Street/Highway | Dubuque Parkway (CR63) |
Limits | From SH288 to Iowa Colony Blvd. |
Description | Improve and expand Dubuque Pkwy (CR 63) to 4-lane concrete boulevard, as identified in the Brazoria County and Iowa Colony Major Thoroughfare Plans. |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $11,000,000.00 |
Project ID | 708 |
Agency Name | City of Iowa Colony |
Project Title | Ames Bvld Expansion and Improvements |
Facility/Street/Highway | Dubuque Parkway (CR63) |
Limits | From Cedar Rapids Pkwy south approximaltey 3000' |
Description | Improve and expand Ames Blvd. (CR 48) from 0 to 4-lane concrete boulevard, as identified in the Brazoria County and Iowa Colony Major Thoroughfare Plans. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $6,000,000.00 |
Project ID | 709 |
Agency Name | City of League City |
Project Title | SH 96 Widening Project, Phase 1: West of Hobbs Rd. intersection to Benson Bayou |
Facility/Street/Highway | Highway |
Limits | Hobbs Rd. to Benson Bayou |
Description | This project would widen SH 96 from the existing 4-lane divided roadway to a 6-lane divided roadway between Hobbs Road and Benson Bayou. ROW will expand from 120' to 140' in width; estimate approximately 11 acres of land along the SH 96 frontage will need to be acquired for expansion and detention/mitigation needs. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $46,670,500.00 |
Project ID | 710 |
Agency Name | City of League City |
Project Title | FM 270 Widening Project, Phase 1: Main Street to south of the SH 96 Intersection |
Facility/Street/Highway | Highway |
Limits | Main Street to SH 96 |
Description | This project would widen FM 270 between Main Street and SH 96 from an existing 2/3 lane roadway to a 4-lane roadway, with sidewalk and/or bike paths. Anticpated that some land acquisition may be needed for detention, right turn lanes, and corner clips. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $58,745,400.00 |
Project ID | 711 |
Agency Name | City of League City |
Project Title | Texas Ave. Improvements, Phase 1: FM 518 to south of the Walker Street Intersection |
Facility/Street/Highway | Street |
Limits | FM 518 to Walker |
Description | Improvements along Texas Avenue between FM 518 and Walker Street to provide safe pedestrian access and drainage improvements. Project will also add dedicated left turn lane at the FM 518 intersection. Texas Ave is currently a 2-lane asphalt open-ditch roadway. Proposed improvements could include (a) a 2-lane concrete curb and gutter roadway with 12' lanes, approximately 1,500' of new 24" diam stormsewer and 5' wide sidewalk along the eastern ROW, or (b) a hybrid design with a concrete roadway and mixture of stormsewer and open ditches with a 5' sidewalk on along the eastern ROW. Either option will require some utility adjustments. ROW would need to expand in certain areas for this project. ROW needs are not anticipated to exceed 1 acre in total. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $2,760,100.00 |
Project ID | 712 |
Agency Name | City of League City |
Project Title | Texas Ave. Improvements, Phase 2: Walker thru Webster St. intersection |
Facility/Street/Highway | Street |
Limits | Walker to Webster |
Description | Improvements along Texas Avenue between Walker Street and Webster Street to provide safe pedestrian access and drainage improvements. Texas Ave is currently a 2-lane asphalt open-ditch roadway. The proposed improvements could include (a) a 2-lane concrete curb and gutter roadway with 12' wide lanes, with approximately 2,000' in total of new 24", 30" and 42" diam stormsewer installed along with a 5' wide sidewalk adjusting as needed along the eastern ROW or (b) a hybrid design with a concrete roadway and mixture of storm sewer and open ditches with a 5' sidewalk on along the eastern ROW. Either option will require some utility adjustments. ROW would need to expand in certain areas for this project. ROW needs are not anticipated to exceed 1 acre in total. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $3,763,700.00 |
Project ID | 713 |
Agency Name | City of League City |
Project Title | FM 2094 Shared Use Path Improvements |
Facility/Street/Highway | Highway |
Limits | Twin Oaks Blvd to Lawrence Road |
Description | Construct 5-foot wide Pedestrian Path and a 10-foot wide Shared Use Path with intersection improvements and pedestrian crossings between Twin Oaks Blvd and Lawrence Road |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $2,300,000.00 |
Project ID | 714 |
Agency Name | City of League City |
Project Title | Hobbs Road Extension to FM 517 |
Facility/Street/Highway | City Collector |
Limits | Patagonia Street to FM 517 |
Description | Extend 2-Lanes of Hobbs Road from Patagonia Street to FM 517 |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $8,941,250.00 |
Project ID | 715 |
Agency Name | City of League City |
Project Title | Webster Street Sidewalk Improvements |
Facility/Street/Highway | City Collector |
Limits | Texas Ave to Louisiana Ave (Go Forth Elementary School) |
Description | Construct 5-foot wide Pedestrian Path intersection improvements and pedestrian crossings between Texas Ave and Louisiana Ave. There are no current pedestian pathways along this cooridor that has Goforth Elementary and League City Intermediate School located on Webster Street. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $2,012,500.00 |
Project ID | 716 |
Agency Name | City of League City |
Project Title | Main Street/E. FM 518 Improvement Project. |
Facility/Street/Highway | Highway |
Limits | Magnolia Ave to thru Iowa Ave intersection |
Description | The project includes major renovations proposed for Main Street (E. FM 518) between Magnolia Ave and Iowa Ave. Improvements would include: Landscaping and streetscaping enhancements along Main St including pedestrian improvements, off street parking locations, transferring overhead utilities to underground, and a visible entrance way into the Downtown (sign to be located along FM 518 near Magnolia Ave intersection). |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $13,225,000.00 |
Project ID | 717 |
Agency Name | City of League City |
Project Title | Main Street/E. FM 518 Intersection Improvement Project. |
Facility/Street/Highway | Highway |
Limits | Intersection |
Description | This project will add 230 LF to the existing Left Turn Lane southbound on SH3 at intersection and convert an existing Thru Lane southbound SH3 into a second Left Turn Lane, and a new Right Turn Lane to southbound SH3. An additional 170 LF will be added to an existing Right Thru Lane on southbound SH3 south of the intersection and 400 LF to an existing Left Turn Lane on northbound SH3. A Conversion of an existing Thru Lane on Northbound SH3 at the intersection into a second Left Turn Lane and a new Right Turn Lane to northbound SH3 will be included. Additional 180 LF will be added to the existing Left Turn Lane on eastbound FM518 at intersection with a raised curb median and a new Right Turn Lane eastbound on FM518 at the intersection. A Right Turn/Thru Lane will be converted to a 460 LF Right Turn Lane on westbound FM518 and an additional 110 LF will be added to the Left Turn Lane on westbound FM518. Traffic access management measures will be Implemented with raised curbs. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $2,425,900.00 |
Project ID | 718 |
Agency Name | City of League City |
Project Title | Smith Lane Sidewalk Improvement |
Facility/Street/Highway | City Collector |
Limits | Bern Street to Webster Street |
Description | Construct 5-foot wide Pedestrian Path with intersection improvements and pedestrian crossings between Bern Street and Webster Street. There are no current pedestian pathways along this cooridor that connects several residential developments to Webster Street near both Goforth Elementary and League City Intermediate School. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $1,150,000.00 |
Project ID | 719 |
Agency Name | City of League City |
Project Title | SH 96 Widening Project, Phase 2: Benson Bayou to East of Hometown Heroes Dr. Intersection |
Facility/Street/Highway | Highway |
Limits | Benson Bayou to Hometown Heroes Dr. |
Description | This project would widen SH 96 from the existing 4-lane divided roadway to a 6-lane divided roadway; extend and widen existing fly-over to include SH 3; create access roads as needed to accomodate the extended SH 3 fly-over. ROW will expand from 120' to 140' in width; estimate approximately 3.1 acres of land along the SH 96 frontage will need to be acquired for expansion and detention/mitigation needs. |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $54,245,270.00 |
Project ID | 720 |
Agency Name | City of League City |
Project Title | FM 270 Widening Project Phase 2: SH 96 to FM 646 |
Facility/Street/Highway | Highway |
Limits | SH 96 to FM 646 |
Description | This project would widen FM 270 between SH 96 to FM 646 from an existing 2/3 lane roadway to a 4-lane roadway, with sidewalk and/or bike paths. Anticpated that some land acquisition may be needed for detention, right turn lanes, and corner clips. |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $25,142,400.00 |
Project ID | 721 |
Agency Name | City of League City |
Project Title | Hobbs Road Expansion to 4-Lanes |
Facility/Street/Highway | City Collector |
Limits | Ervin Street to FM 517 |
Description | Expand 2-lane Hobbs Road to 4-lanes from Ervin Street to FM 517 |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $5,635,000.00 |
Project ID | 722 |
Agency Name | City of Missouri City |
Project Title | US 90A Railroad Crossing Safety Initiative |
Facility/Street/Highway | US 90A at Cravens Rd |
Limits | Identified Intersection |
Description | Implement improvements to reduce railroad collisions at intersection and at-grade crossing. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $2,400,000.00 |
Project ID | 723 |
Agency Name | City of Missouri City |
Project Title | US 90A Railroad Crossing Safety Buildout |
Facility/Street/Highway | US 90A at Cravens Rd |
Limits | Identified Intersection |
Description | Implement long-term solutions to reduce railroad collisions at intersection and at-grade crossing. |
Timeframe | Long Term (More than 10 Years) |
Estimated Cost | $20,000,000.00 |
Project ID | 724 |
Agency Name | City of Missouri City |
Project Title | ITS Communications Upgrade |
Facility/Street/Highway | Citywide |
Limits | City limts & ETJ |
Description | The project includes the development of Plans, Specifications & Estimates (PS&E) and subsequent construction for upgrading the aging Intelligent Transportation Systems (ITS) wireless communications network architecture, antennae, radios, routers, switchers, and other associated network equipment. Project includes communications equipment upgrades (radio and Ethernet switches) at four existing radio towers, select intersections and CCTV gap locations along select corridors. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $720,000.00 |
Project ID | 725 |
Agency Name | City of Missouri City |
Project Title | Traffic Management Center Ugprade |
Facility/Street/Highway | Citywide |
Limits | City limts & ETJ |
Description | The Traffic Management Center (TMC) project will upgrade the existing TMC including reconfiguring the video wall, replacing the video control system, enhancing operator capabilities. Performing an architectural assessment and proposing architectural upgrades is included. TMC website with traffic conditions and traveler information will also be assessed. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $480,000.00 |
Project ID | 726 |
Agency Name | City of Missouri City |
Project Title | Hunters Glen Multimodal Improvements |
Facility/Street/Highway | Independence Blvd. |
Limits | 1340 Independence Blvd. |
Description | Improve 3510 feet of decomposed granite footpaths to 8-fot wide concrete multiuse activity corridor. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $270,000.00 |
Project ID | 727 |
Agency Name | City of Missouri City |
Project Title | Pedestrian Bridge |
Facility/Street/Highway | 1) Middle Oyster Creek 2) Channel A |
Limits | 1) Middle Oyster Creek; connecting proposed trail from Glenn Lakes Lane to Lake Olympia Middle School, and 2) Channel A; connecting proposed trail from Independence Park to American Legion Park, near Bay Shore Boulevard and Waterford Village Boulevard. |
Description | The City and residents would benefit greatly from increasing the access to desired locations and further connecting the existing parks and trails. Park, near Bay Shore Boulevard and Waterford Village Boulevard. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $720,000.00 |
Project ID | 728 |
Agency Name | City of Missouri City Parks and Recreation |
Project Title | Hunters Glen Trail |
Facility/Street/Highway | Off-Street Trail Independence Blvd |
Limits | |
Description | This trail will address the need for safe travel by for pedestrians and bicylclists by connecting Hunters Glen Park, Progressive High School, and the surrounding neighborhoods. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $260,000.00 |
Project ID | 729 |
Agency Name | City of Missouri City, TxDOT |
Project Title | FM 1092 Widening |
Facility/Street/Highway | FM 1092 |
Limits | Missouri City Limits to SH 6 |
Description | Widening existing 4-lane roadway to a 6-lane roadway with medians and\or turn lane improvements. Install sidewalks, improve signals, and evaluate additional operational improvements to provide better through movement along roadway corridor. |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $20,000,000.00 |
Project ID | 730 |
Agency Name | City of Missouri City, TxDOT |
Project Title | SH 6 Traffic Control Improvements |
Facility/Street/Highway | SH 6 |
Limits | Dulles Avenue to N. Creekmont Dr. |
Description | Implement traffic signal improvements, and evaluate widen roadway from 6 lanes to 8 lanes with turn lane improvements along critical intersections. |
Timeframe | Long Term (More than 10 Years) |
Estimated Cost | $30,000,000.00 |
Project ID | 731 |
Agency Name | City of Missouri City, TxDOT |
Project Title | Texas Parkway Shared Use Path |
Facility/Street/Highway | Texas Parkway/FM2234 |
Limits | US 90 to Turtle Creek Drive (End of City Limits) |
Description | The Shared Use Path project will design and install shared use paths along priority corridors. The project includes the development of Plans, Specifications & Estimates (PS&E), and subsequent construction of proposed shared use path |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $2,280,000.00 |
Project ID | 732 |
Agency Name | City of Missouri City, TxDOT |
Project Title | Intersection Improvements |
Facility/Street/Highway | 1) FM 1092 at Cartwright Road 2) SL 8 at Gessner Road 3) FM 1092 at Lexington Boulevard, 4) FM 1092 at SH 6, and 5) SH 6 at Sienna Parkway |
Limits | Identified Intersections |
Description | The Intersection Improvements project will expand study on safety and mobility enhancements for priority intersections which have been identified to experience congestion and have a high crash incidence within the City. Studies within this project will analyze the safety and efficiency of the identified intersections, and culminate in actionable geometric and/or operational improvements. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $3,720,000.00 |
Project ID | 733 |
Agency Name | City of Mont Belvieu |
Project Title | Public Works & Engineering Director |
Facility/Street/Highway | Eagle Dr. |
Limits | From Fm 565 to SH 146 |
Description | Reconstruction of 2-lane open ditch to 4-lane Blvd with curb and gutter with sidewalks and bikeway. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $36,000,000.00 |
High Growth Area Needs Questionnaire | View Questionnaire |
Operational Improvements and Congestion Management Questionnaire | View Questionnaire |
Regional Goods Movement Questionnaire | View Questionnaire |
Resiliency and State of Good Repair Questionnaire | View Questionnaire |
Transit Questionnaire | View Questionnaire |
Project ID | 734 |
Agency Name | City of Mont Belvieu |
Project Title | Public Works & Engineering Director |
Facility/Street/Highway | FM 565 |
Limits | From SH 99 to Canal St. |
Description | Reconstruction of 2-lane open ditch to 4-lane Blvd with curb and gutter with sidewalks and bikeway. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $24,000,000.00 |
High Growth Area Needs Questionnaire | View Questionnaire |
Operational Improvements and Congestion Management Questionnaire | View Questionnaire |
Regional Goods Movement Questionnaire | View Questionnaire |
Resiliency and State of Good Repair Questionnaire | View Questionnaire |
Transit Questionnaire | View Questionnaire |
Project ID | 735 |
Agency Name | City of Mont Belvieu |
Project Title | Public Works & Engineering Director |
Facility/Street/Highway | Traffic Management Center |
Limits | City Wide |
Description | Construction of a traffic management center for the City of Mont Belvieu |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $3,000,000.00 |
High Growth Area Needs Questionnaire | View Questionnaire |
Operational Improvements and Congestion Management Questionnaire | View Questionnaire |
Regional Goods Movement Questionnaire | View Questionnaire |
Transit Questionnaire | View Questionnaire |
Project ID | 736 |
Agency Name | City of Pearland |
Project Title | Reid Boulevard Extension (Max Road) |
Facility/Street/Highway | Reid Boulevard (Max Road) |
Limits | Hughes Ranch Road to McHard |
Description | Reid Boulevard from Hughes Ranch Road to Mchard Road. Approximately 3,500 LF extension will extend and match the 4-lane boulevard cross-section of Reid Blvd (HRR to FM 518)previously constructed through the TIP program. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $17,571,000.00 |
Project ID | 737 |
Agency Name | City of Pearland |
Project Title | O'Day Road |
Facility/Street/Highway | O'Day Road |
Limits | McHard to Broadway |
Description | The project consists of 7,800 LF reconstruction of O’Day Road from two lane asphalt to four lanes divided with curb and gutter, underground drainage and a single ten-foot sidewalk along one side. The project will require approximately 9.25 acres of ROW and 15 acres for detention. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $42,541,000.00 |
Project ID | 738 |
Agency Name | City of Pearland |
Project Title | Reid Boulevard Extension (Max Road) |
Facility/Street/Highway | Reid Boulevard (Max Road) |
Limits | McHard to Beltway 8 |
Description | Extend Reid Boulevard from McHard Road to BW8. Approximately 7,500 LF extension will match the 4-lane boulevard cross-section of Reid Blvd (McHard to FM 518) to provide connectivity to Beltway 8. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $63,386,000.00 |
Project ID | 739 |
Agency Name | City of Pearland |
Project Title | Kingsley Drive |
Facility/Street/Highway | Kingsley Drive |
Limits | Clear Creek to Beltway 8 |
Description | Expand 4,800 feet of Kingsley drive from Clear Creek to Beltway 8. The project will replace a 2-lane road with a 4-lane road connecting HWY 6 to Beltway 8 |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $20,758,000.00 |
Project ID | 740 |
Agency Name | City of Pearland |
Project Title | Harkey Road Expansion |
Facility/Street/Highway | Harkey Road |
Limits | Broadway to Bailey Road |
Description | The project will widen 7,900 LF of the existing 2 lane roadway to a 4-lane undivided concrete curb and gutter cross-section with a 10’ shared use path from Broadway to Bailey Road. |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $45,736,000.00 |
Project ID | 741 |
Agency Name | City of Pearland |
Project Title | Miller Ranch Road Expansion |
Facility/Street/Highway | Miller Ranch Road |
Limits | Broadway to Hughes Ranch Rd |
Description | The project will widen 5,300 LF of the existing 2 lane roadway to a 4-lane undivided concrete curb and gutter cross-section with a 10’ shared use path from Hughes Ranch Road to FM 518. |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $15,936,000.00 |
Project ID | 742 |
Agency Name | City of Pearland |
Project Title | Veterans Drive Expansion |
Facility/Street/Highway | Veterans Drive |
Limits | Walnut to Bailey Road |
Description | This project will consist of the reconstruction of 10,600 feet of Veterans from Walnut to Bailey Road. The street will be constructed as four-lane divided with curb and gutter cross section, underground drainage, detention pond, and a ten-foot-wide sidewalk. |
Timeframe | Long Term (More than 10 Years) |
Estimated Cost | $52,500,000.00 |
Project ID | 743 |
Agency Name | City of Pearland |
Project Title | Cullen Parkway Expansion |
Facility/Street/Highway | Cullen Parkway |
Limits | Magnolia Parkway (Southfork) to Bailey Road |
Description | This project will consist of the reconstruction of 4,300 feet of Cullen Parkway from Magnolia Pkwy to Bailey Road. Street will be constructed as 4 lanes divided with curb and gutter cross section, underground drainage, detention pond, one ten-foot-wide sidewalk and add one additional two lane bridge over Mary’s Creek approximately 150 feet in length. |
Timeframe | Long Term (More than 10 Years) |
Estimated Cost | $59,230,000.00 |
Project ID | 744 |
Agency Name | City of Pearland |
Project Title | Dixie Farm Road Extension |
Facility/Street/Highway | Dixie Farm Road |
Limits | SH 35 to Veterans (Pearland Sites) |
Description | A 4,800 LF extension of Dixie Farm Road from SH 35 to Pearland Sites (Dixie Farm Rd to existing McKeever Rd). The project would also widen the existing cross-section of McKeever to a 4-lane boulevard and include an above grade crossing over the Railroad. THe project will provide vehicular mobility from HWY35 to FM1128. |
Timeframe | Long Term (More than 10 Years) |
Estimated Cost | $50,740,000.00 |
Project ID | 745 |
Agency Name | City of Pearland |
Project Title | Clear Creek Trail |
Facility/Street/Highway | Clear Creek Trail |
Limits | Province Village to Dixie Farm |
Description | Project will consist of the installation of approximately 19,900 LF of 10 foot wide concrete multi-path use, benches, waste receptacles, and appurtenances along Clear Creek (Country Club Dr. to Dixie Farm). |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $10,694,000.00 |
Project ID | 746 |
Agency Name | City of Pearland |
Project Title | Clear Creek Trail |
Facility/Street/Highway | Clear Creek Trail |
Limits | SH 288 to Cullen Parkway |
Description | Project will consist of the installation of approximately 12,950 LF of 10 foot wide concrete multi-path use, benches, waste receptacles, and appurtenances along Clear Creek (SH 288 to Cullen Blvd). |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $7,110,000.00 |
Project ID | 747 |
Agency Name | City of Sugar Land |
Project Title | Soldiers Field Extension/ Roundabout @ First Colony Blvd & Brooks St Improvements (CST1901) |
Facility/Street/Highway | Soldiers Field Blvd/First Colony Blvd/Brooks Street |
Limits | From Fluor Daniel Drive to SH6 |
Description | Extend the existing Soldiers Field roadway to SH 6 and install roundabout at the intersection of Soldiers Field and First Colony Boulevard. Project will include sidepaths, buffered bike lanes, and shared lanes. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $3,400,000.00 |
Project ID | 748 |
Agency Name | City of Sugar Land |
Project Title | Sugar Land Trail Phase 2 (Ditch H Trail) (PK1702) |
Facility/Street/Highway | Ditch H/ Bullhead Bayou/ CenterPoint Corridor |
Limits | From Imperial Park to Lexington Blvd near Smart Financial Centre |
Description | Approx. 4 mile, 10-ft wide concrete trail with below-grade crossings at state highway intersections and three pedestrian bridges |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $8,000,000.00 |
Project ID | 749 |
Agency Name | City of Sugar Land |
Project Title | University Blvd Widening & Intersection Improvements (CST2102/CST2203) |
Facility/Street/Highway | University Blvd |
Limits | From New Territory Blvd to Wentworth Ave |
Description | Widen existing roadway from 4 lanes to six lanes and intersection improvements at Wescott & Branford Place. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $4,000,000.00 |
Project ID | 750 |
Agency Name | City of Sugar Land |
Project Title | Brazos River Turnaround Alt/UHSL Roadway (CST2103) |
Facility/Street/Highway | UHSL Roadway/ US 59 Frontage Road |
Limits | From Wallingford Ave to Grand Pkwy/SH99 |
Description | Design new roadway as low-speed facility using traffic calming, such as raised crosswalks or narrow lanes. Intersection improvements at University Blvd @ US 59 and replace existing substandard bike lane with sidepath in each direction. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $25,000,000.00 |
Project ID | 751 |
Agency Name | City of Sugar Land |
Project Title | ITS Railroad Monitoring, Notification, & Communication (CTR2203) |
Facility/Street/Highway | Cravens Road |
Limits | Pitts Road |
Description | Install railroad notification DMS prior to RR crossings to reroute traffic; Add Lidar or other technology to the Rail Monitor System to detect trains on dual tracks. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $2,100,000.00 |
Regional Goods Movement Questionnaire | View Questionnaire |
Project ID | 752 |
Agency Name | City of Sugar Land |
Project Title | Dulles Avenue Pedestrian Improvements |
Facility/Street/Highway | Dulles Avenue |
Limits | From Avenue E to 3 Rivers Drive |
Description | Install 10-ft wide sidepath on one side of street and pedestrian bridge over American Canal near Riverbend Country Club. Pedestrian midblock crossing and connection at Oyster Creek Trail. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $2,000,000.00 |
Project ID | 753 |
Agency Name | City of Sugar Land |
Project Title | Gannoway Lake Trail |
Facility/Street/Highway | Gannoway Lake Park |
Limits | From Voss Rd to Cullinan Park |
Description | Approx. 2 mile, 10-ft wide concrete trail with below-grade crossings and two pedestrian bridges |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $2,100,000.00 |
Project ID | 754 |
Agency Name | City of Sugar Land |
Project Title | New Territory Trail |
Facility/Street/Highway | CenterPoint Corridor |
Limits | From Wescott Avd to New Terriroty Blvd |
Description | Approx. 1.5-mile, 10-ft wide concrete trail within CNP easement |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $1,900,000.00 |
Project ID | 755 |
Agency Name | City of Sugar Land |
Project Title | Traffic Signal Detection Update |
Facility/Street/Highway | Various |
Limits | Various |
Description | The City has identified the need to update detection to as it reaches end-of-life. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $600,000.00 |
Project ID | 756 |
Agency Name | City of Sugar Land |
Project Title | Adaptive Signal Timing Update |
Facility/Street/Highway | Various |
Limits | Various |
Description | Update adaptive signal timing for top 3 corridors. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $540,000.00 |
Project ID | 757 |
Agency Name | City of Sugar Land |
Project Title | ITS Upgrades |
Facility/Street/Highway | Citywide ITS |
Limits | City Limits |
Description | In order for ITS to continue support mobility goals, hardware and software need to be upgraded after reaching end of life . Major componenets currently need to be replaced due to end of life and some will need to be replaced within 5 years to continue to support future ITS initiatiatives like connected vehicles and others. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $3,750,000.00 |
Project ID | 758 |
Agency Name | City of Sugar Land |
Project Title | Sweetwater Blvd Reconstruction |
Facility/Street/Highway | Sweetwater Blvd |
Limits | From Austin Pkwy to Town Center Blvd |
Description | Replace Approx. 2 miles of boulevard sectioned roadway and water main, traffic signal upgrades, and pedestrian/bicyclist capacity and enhanced access. |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $24,000,000.00 |
High Growth Area Needs Questionnaire | View Questionnaire |
Resiliency and State of Good Repair Questionnaire | View Questionnaire |
Project ID | 759 |
Agency Name | City of Sugar Land |
Project Title | Williams Trace Blvd Reconstruction |
Facility/Street/Highway | Williams Trace Blvd |
Limits | From Lexington Blvd to SH6 |
Description | Reconstruct 4 lane divided roadway including curb and gutter, left turn lanes, inlets and manholes; Construct a triple left from SB Quarry Hill to SB SH6 |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $14,900,000.00 |
High Growth Area Needs Questionnaire | View Questionnaire |
Resiliency and State of Good Repair Questionnaire | View Questionnaire |
Project ID | 760 |
Agency Name | City of Sugar Land |
Project Title | Williams Trace Blvd Widening |
Facility/Street/Highway | Williams Trace Blvd |
Limits | From US59 to Oyster Creek |
Description | Widen from 4 - 6 lanes; Improvements to intersection at 59 & William Trace - Potential Triple Left; Intersection Improvements to Parkway Blvd & Williams Trace, Roadway Improvements to SB Williams Trace- potentially adding an additional right turn lane |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $22,400,000.00 |
High Growth Area Needs Questionnaire | View Questionnaire |
Project ID | 761 |
Agency Name | City of Sugar Land |
Project Title | West Airport Blvd |
Facility/Street/Highway | West Airport Blvd |
Limits | From SH6 to Dairy Ashford Rd |
Description | Replace Approx. 3 miles of roadway |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $20,000,000.00 |
Project ID | 762 |
Agency Name | City of Sugar Land |
Project Title | Grand Parkway Direct Connectors |
Facility/Street/Highway | Grand Parkway - Segment C |
Limits | US 59 |
Description | Construction four director connectors (TOLL) for traffic flow improvements. |
Timeframe | Long Term (More than 10 Years) |
Estimated Cost | $104,000,000.00 |
Project ID | 763 |
Agency Name | City of Sugar Land |
Project Title | Brazos River Multimodal Bridge & Connections |
Facility/Street/Highway | Brazos River Corridor |
Limits | From Greatwood Community to Brazos River Park |
Description | Multimodal bridge over the Brazos River connecting from Greatwood to Brazos River Park. |
Timeframe | Long Term (More than 10 Years) |
Estimated Cost | $25,000,000.00 |
Project ID | 764 |
Agency Name | City of Sugar Land |
Project Title | Bullhead Bayou Trail |
Facility/Street/Highway | University Blvd |
Limits | University Blvd to Easton Ave |
Description | Approx. 1.25 mile trail along Bullhead Bayou within Telfair. |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $7,000,000.00 |
Project ID | 765 |
Agency Name | City of Sugar Land |
Project Title | East Utility Corridor Greenway |
Facility/Street/Highway | Utility Corridor |
Limits | SH 6 to Austin Parkway |
Description | Approx. 1.25 mile trail along utility corridor between Chimneystone and Lakefield neighborhoods and pedestrian bridge connection to Oyster Creek Park over SH6. |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $11,000,000.00 |
Project ID | 766 |
Agency Name | City of Sugar Land |
Project Title | John Sharp (Owens Rd) Trail |
Facility/Street/Highway | John Sharp Road |
Limits | US 90A to Cullinan Park |
Description | Approx. 1.5 mile trail west of the Sugar Land Regional Airport connecting from US 90A along John Sharp Rd to the existing trail system within Cullinan Park. Includes pedestrian & bicycle improvements at the US 90A and John Sharp Rd intersection. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $5,000,000.00 |
Project ID | 767 |
Agency Name | City of Sugar Land |
Project Title | Sugar Land Business Park Trail |
Facility/Street/Highway | Drainage Corridor |
Limits | Eldridge Road to West Airport Blvd |
Description | Approx. 1 mile trail within the Sugar Land Business Park. |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $5,000,000.00 |
Project ID | 768 |
Agency Name | City of Tomball |
Project Title | Alley Improvement Project |
Facility/Street/Highway | Street |
Limits | 200, 300 & 400 blocks of Commerce and Market |
Description | To improve the connectivity and walkability of the downtown area while providing revitalization of the Main Street area. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $5,000,000.00 |
Project ID | 769 |
Agency Name | City of Tomball |
Project Title | South Persimmon Street Widening |
Facility/Street/Highway | Street |
Limits | South Persimmon from FM 2920 to Medical Complex |
Description | Widening of a north to south corridor widely used for industrial and commercial purposes due to the businesses located in the area. |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $4,000,000.00 |
Project ID | 770 |
Agency Name | City of Tomball |
Project Title | Rudolph Road Widening |
Facility/Street/Highway | Street |
Limits | Rudolph Road from Zion Road to Hufsmith Road |
Description | Widening of a currently undersized road due to safety. The road is experiencing development and the City's wastewater treatment plant is located on this road and does have large deliveries. |
Timeframe | Long Term (More than 10 Years) |
Estimated Cost | $2,500,000.00 |
Project ID | 771 |
Agency Name | City of Waller |
Project Title | Schultz Middle School and Waller High School Safe Routes Project |
Facility/Street/Highway | Field Store Road |
Limits | Waller Spring Creek Road to Daugherty Street (the project includes other small gap filling connections on Brazeal St., Farr St., Daughterty St., and Waller St.) |
Description | Construct 6-FT wide sidewalk to connect new Schultz Middle School and new Waller High School to community. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $2,600,000.00 |
Project ID | 772 |
Agency Name | City of West Columbia, TX |
Project Title | West Columbia Roadway State of Good Repair |
Facility/Street/Highway | Various locally owned and maintained roads within the City limits, a supplemental list can be provided outside of this spreadsheet. |
Limits | Various limits. |
Description | Design and reconstruction of approximately 8.61 lane miles of roads within the City. The scope of work is limited to roadway reconstruction, pavement markings, hydromulch, and incidental reconstruction/replacement of driveways and drainage within existing rights-of-way. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $5,261,200.00 |
High Growth Area Needs Questionnaire | View Questionnaire |
Resiliency and State of Good Repair Questionnaire | View Questionnaire |
Project ID | 773 |
Agency Name | Energy Corridor District |
Project Title | Memorial Drive Reconstruction |
Facility/Street/Highway | Memorial Drive |
Limits | SH-6 to N. Eldridge Pkwy |
Description | A redesign and reconstruction of Memorial Drive into a bikable, walkable, and more resilient street. A planning study is underway to determine bicycle, pedestrian, transit, drainage, and safety improvements for this detoriating 2-mile stretch of Memorial Drive. Currently, the road has demonstrated poor pavement conditions, lacks multi-modal features, and contains significant open drainage. |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $52,403,656.00 |
Project ID | 774 |
Agency Name | Energy Corridor District |
Project Title | Eldridge Pkwy Reconstruction |
Facility/Street/Highway | Eldridge Parkway |
Limits | Addicks Reservoir to Briar Forest |
Description | A complete reconstruction of Eldridge Parkway from the Addicks Reservoir to Briar Forest to address a detoriating and structurally damaged roadway while adding shared use paths and improving pedestrian safety. Eldridge Parkway flooded during Hurrican Harvey and has not received improvements to address flood damage. |
Timeframe | Long Term (More Than 10 years) |
Estimated Cost | $98,120,272.00 |
Project ID | 775 |
Agency Name | Energy Corridor District |
Project Title | N. Dairy Ashford Shared Use Paths |
Facility/Street/Highway | N. Dairy Ashford |
Limits | N. Eldridge Pkwy to IH-10 |
Description | The proposed project will convert existing 6-foot wide sidewalks into 10-foot wide shared use paths for approximately .85 miles along N. Dairy Ashford Rd from I-10 to N. Eldridge Parkway. The shared use paths will close an existing gap in trail connectivity and improve the pedestrian and bicycle infrastructure that connects a 1.3 million sf mixed-use development to office buildings with more than 5,000 employees daily. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $888,657.00 |
Project ID | 776 |
Agency Name | Energy Corridor District |
Project Title | Park Row Bicycle and Pedestrian Improvements |
Facility/Street/Highway | Park Row |
Limits | SH-6 to N. Eldridge Pkwy |
Description | The proposed project will construct 1.65 miles of a 10'-12' foot wide shared use path and 6' wide sidewalks along Park Row in the city of Houston, from N. Eldridge Parkway to SH-6. The shared use path and sidewalks will add bicycle and pedestrian infrastructure along a major thoroughfare, connecting office buildings, Terry Hershey Trail and Park, medical facilities, and housing. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $1,458,435.00 |
Project ID | 777 |
Agency Name | Energy Corridor District |
Project Title | Grisby Square/Addicks Village Infrastructure Enhancements |
Facility/Street/Highway | Grisby Rd, Fortsmith, Addicks Howell Rd, Grasshopper |
Limits | Grisby Rd from SH-6 to Addicks Howell Rd; Fortsmith from SH-6 to Addicks Howell Rd; Stafford St from IH-10 FR to Grisby Rd; Jackson Ave from IH-10 FR to Grisby Rd; |
Description | A property line to property line reconstruction of several small blocks in the GrisbySquare/Addicks Village area. Improvements include one travel lane in each direction, sidewalks, and bicycle facilities (potential shared use path along Addicks Howell Rd); and upgrades to stormwater and subsurface utilities. |
Timeframe | Long Term (More Than 10 years) |
Estimated Cost | $14,217,750.00 |
Project ID | 778 |
Agency Name | Energy Corridor District |
Project Title | N. Eldridge Pkwy-N. Dairy Ashford/Park Row Intersection Safety Enhancements |
Facility/Street/Highway | N. Eldridge Parkway-N. Dairy Ashford Intersection |
Limits | Intersection of N. Eldridge Parkway and N.Dairy Ashford/Park Row |
Description | A redesign of the intersection to improve vehicular, pedestrian, and bicylcist safety through curb extensions, new mast arms, turning lane removal, median extensions, and a shared use path |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $714,007.00 |
Project ID | 779 |
Agency Name | Energy Corridor District |
Project Title | SH-6 and Grisby Rd. Traffic Signal |
Facility/Street/Highway | SH-6 and Grisby Rd Intersection |
Limits | Intersection of SH-6 and Grisby Rd |
Description | A redesign of the intersection to feature a new traffic signal, curb extensions, updated markings, and universal accesibility upgrades |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $671,563.00 |
Project ID | 780 |
Agency Name | Energy Corridor District |
Project Title | SH-6 and Park Row Intersection Enhancements |
Facility/Street/Highway | SH-6 and Park Row Intersection |
Limits | Intersection of SH-6 and Park Row |
Description | A redesign of the intersection to add curb extensions, a Texas U-turn, better signal timing, and leading pedestrian intervals |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $492,279.00 |
Project ID | 781 |
Agency Name | Fort Bend County |
Project Title | SH 99 Frontage Rd (20303a) |
Facility/Street/Highway | SH 99 |
Limits | NB Cinco Ranch Blvd to Bay Hill |
Description | Construction of a two lane concrete curb and gutter frontage road. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $13,600,000.00 |
High Growth Area Needs Questionnaire | View Questionnaire |
Operational Improvements and Congestion Management Questionnaire | View Questionnaire |
Project ID | 782 |
Agency Name | Fort Bend County |
Project Title | SH 99 Frontage Rd (20303b) |
Facility/Street/Highway | SH 99 |
Limits | NB Westheimer Pkwy to Cinco Ranch Blvd |
Description | Construction of a two lane concrete curb and gutter frontage road. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $12,000,000.00 |
High Growth Area Needs Questionnaire | View Questionnaire |
Operational Improvements and Congestion Management Questionnaire | View Questionnaire |
Project ID | 783 |
Agency Name | Fort Bend County |
Project Title | SH 99 Frontage Rd (20307) |
Facility/Street/Highway | SH 99 |
Limits | SB Fry Rd to Westheimer Pkwy |
Description | Construction of a two lane concrete curb and gutter frontage road. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $20,500,000.00 |
High Growth Area Needs Questionnaire | View Questionnaire |
Operational Improvements and Congestion Management Questionnaire | View Questionnaire |
Project ID | 784 |
Agency Name | Fort Bend County |
Project Title | SH 99 Frontage Rd (203xx) |
Facility/Street/Highway | SH 99 |
Limits | NB Fry Rd to Westheimer Pkwy |
Description | Construction of a two lane concrete curb and gutter frontage road. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $25,000,000.00 |
High Growth Area Needs Questionnaire | View Questionnaire |
Operational Improvements and Congestion Management Questionnaire | View Questionnaire |
Project ID | 785 |
Agency Name | Fort Bend County |
Project Title | FM 762 Extension to 10th St (Grade separation over Railroad) |
Facility/Street/Highway | FM 762 (10th St) |
Limits | Morton to Preston St. |
Description | Engineering and construction of a bridge over the railroad crossing between Morton St. and Preston St. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $7,500,000.00 |
Operational Improvements and Congestion Management Questionnaire | View Questionnaire |
Project ID | 786 |
Agency Name | Fort Bend County |
Project Title | FM 1093 and FM 1489 |
Facility/Street/Highway | Intersection Improvement |
Limits | Intersection of FM 1093 and FM 1489 |
Description | Align the intersection in downtown Simonton. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $6,400,000.00 |
Project ID | 787 |
Agency Name | Fort Bend County |
Project Title | FM 1093 |
Facility/Street/Highway | FM 1093 |
Limits | Fulshear to west of Simonton |
Description | Construction of four lane roadway. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $70,000,000.00 |
Project ID | 788 |
Agency Name | Fort Bend County |
Project Title | FM 1489 |
Facility/Street/Highway | FM 1489 |
Limits | SH 36 to I-10 |
Description | Construction of four lane roadway. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $225,000,000.00 |
Project ID | 789 |
Agency Name | Fort Bend County |
Project Title | Fort Bend Parkway |
Facility/Street/Highway | Fort Bend Pkwy |
Limits | FM 762 to Sienna Ranch Rd |
Description | Construction of four lane highway. (including 2 bridge structures) |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $180,000,000.00 |
Major Projects Questionnaire | View Questionnaire |
Project ID | 790 |
Agency Name | Fort Bend County |
Project Title | FM 2759 |
Facility/Street/Highway | FM 2759 |
Limits | FM 762 to Thompsons (8.25 miles) |
Description | Construction of a four lane concrete curb and gutter road. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $100,000,000.00 |
Project ID | 791 |
Agency Name | Fort Bend County |
Project Title | FM 521 |
Facility/Street/Highway | SH 6 |
Limits | SH 6 to Brazoria County Line (4.85 miles) |
Description | Construction of a four lane concrete curb and gutter road. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $85,000,000.00 |
Project ID | 792 |
Agency Name | Fort Bend County |
Project Title | Humphrey Way |
Facility/Street/Highway | Humphrey Way |
Limits | Braxton Road to Emmanuel King Road |
Description | Concrete roadway, 4-12 ft lanes undivided w/ 4 ft shoulders. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $7,000,000.00 |
Operational Improvements and Congestion Management Questionnaire | View Questionnaire |
Project ID | 793 |
Agency Name | Fort Bend County |
Project Title | FM 2977 |
Facility/Street/Highway | FM 2977 |
Limits | FM 361 to FM 762 |
Description | Partner with Rosenberg for Engineering and Contruction - over all improvements |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $80,000,000.00 |
Project ID | 794 |
Agency Name | Fort Bend County |
Project Title | Austin St |
Facility/Street/Highway | Austin St |
Limits | 7th St to 90A |
Description | Sidewalks |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $400,000.00 |
Project ID | 795 |
Agency Name | Fort Bend County |
Project Title | FM 762 (10th St) |
Facility/Street/Highway | FM 762 (10th St) |
Limits | Clay Street to over the Brazos to meet McCrary/Peek |
Description | FM 762/10th - over the Brazos to get to Peek and McCrary |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $120,000,000.00 |
Project ID | 796 |
Agency Name | Fort Bend County |
Project Title | FM 762 |
Facility/Street/Highway | FM 762 |
Limits | Brazos Center Blvd to FM 2759 (2.55 miles) |
Description | Construction of a four lane concrete curb and gutter road. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $30,000,000.00 |
High Growth Area Needs Questionnaire | View Questionnaire |
Operational Improvements and Congestion Management Questionnaire | View Questionnaire |
Project ID | 797 |
Agency Name | Fort Bend County |
Project Title | FM 762 BNSF Rail Underpass |
Facility/Street/Highway | FM 2759 & FM 762 |
Limits | FM 762 at BNSF Railroad/FM 2759 Intersection |
Description | Construction of underpass beneath BNSF Railroad at FM 762 |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $50,000,000.00 |
High Growth Area Needs Questionnaire | View Questionnaire |
Operational Improvements and Congestion Management Questionnaire | View Questionnaire |
Project ID | 798 |
Agency Name | Fort Bend County Public Transportation |
Project Title | Bus Support Equipment |
Facility/Street/Highway | 3737 Bamore Rd Rosenberg, TX |
Limits | |
Description | Bus support equipment and facilities, transit software, hardware and bus wraps FY2020. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $1,281,000.00 |
Project ID | 799 |
Agency Name | Fort Bend County Public Transportation |
Project Title | Rolling Stock - Replacement |
Facility/Street/Highway | 3737 Bamore Rd Rosenberg, TX |
Limits | |
Description | Replace 11 transit vehicles FY2024 |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $3,809,848.00 |
Project ID | 800 |
Agency Name | Fort Bend County Public Transportation |
Project Title | Bus Support Equipment |
Facility/Street/Highway | 3737 Bamore Rd Rosenberg, TX |
Limits | |
Description | Bus support equipment and facilities, transit software, hardware and bus wraps FY2021. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $580,000.00 |
Project ID | 801 |
Agency Name | Fort Bend County Public Transportation |
Project Title | Rolling Stock - Replacement |
Facility/Street/Highway | 3737 Bamore Rd Rosenberg, TX |
Limits | |
Description | Replace seven (7) transit vehicles FY2023 |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $1,942,939.00 |
Project ID | 802 |
Agency Name | Fort Bend County Public Transportation |
Project Title | Bus Support Equipment |
Facility/Street/Highway | 3737 Bamore Rd Rosenberg, TX |
Limits | |
Description | Bus support equipment and facilities, transit software, hardware and bus wraps FY2023 |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $650,000.00 |
Project ID | 803 |
Agency Name | Fort Bend County |
Project Title | Rolling Stock - Replacement |
Facility/Street/Highway | 3737 Bamore Rd Rosenberg, TX |
Limits | |
Description | Replace nine (9) transit vehicles FY2022 |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $2,495,493.00 |
Project ID | 804 |
Agency Name | Fort Bend County Public Transportation |
Project Title | ITS Equipment - Fare Collection System |
Facility/Street/Highway | 3737 Bamore Rd Rosenberg, TX |
Limits | |
Description | Contactless fare collection system to allow customers to pay transit fare using a mobile device. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $500,000.00 |
Project ID | 805 |
Agency Name | Fort Bend County Public Transportation |
Project Title | Signage and Wayfinding |
Facility/Street/Highway | 3737 Bamore Rd Rosenberg, TX |
Limits | |
Description | New signs for all FBCT facilities along roadways surrounding facilities. Implement wayfinding improvements to coordinate with the transit, sidewalk and bikeway networks. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $300,000.00 |
Project ID | 806 |
Agency Name | Fort Bend County Public Transportation |
Project Title | Rolling Stock - Expansion |
Facility/Street/Highway | 19820 FM 1093 Rd, Richmond, TX |
Limits | |
Description | Acquire six (6) large transit vehicles for expansion service from Westpark Park & Ride. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $1,758,392.00 |
Project ID | 807 |
Agency Name | Fort Bend County Public Transportation |
Project Title | ITS - Scheduling & Dispatch System |
Facility/Street/Highway | 3737 Bamore Rd Rosenberg, TX |
Limits | |
Description | Upgrade scheduling and dispatch system |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $1,750,000.00 |
Project ID | 808 |
Agency Name | Fort Bend County Public Transportation |
Project Title | Rolling Stock - Low Emission Pilot Program |
Facility/Street/Highway | 3737 Bamore Rd Rosenberg, TX |
Limits | |
Description | Pilot nine (9) low emission vehicles for Phase II of new downtown service. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $3,505,526.00 |
Project ID | 809 |
Agency Name | Fort Bend County Public Transportation |
Project Title | Bus Facility -Parking Garage |
Facility/Street/Highway | Thomas Taylor Parkway & Texas Parkway Missouri City, TX |
Limits | |
Description | Construct structured TOD parking garage of 400 spaces in downtown Missouri City with bus and passenger accommodations for a permanent park and ride including dedicated bus bays with passenger platforms, passenger waiting shelters and transit information systems. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $10,000,000.00 |
Operational Improvements and Congestion Management Questionnaire | View Questionnaire |
Transit Questionnaire | View Questionnaire |
Project ID | 810 |
Agency Name | Fort Bend County Public Transportation |
Project Title | Rolling Stock - Expansion |
Facility/Street/Highway | 19820 FM 1093 Rd, Richmond, TX |
Limits | |
Description | Acquire six (6) additional large transit vehicles for express services from Westpark Park & Ride. |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $2,000,714.00 |
Project ID | 811 |
Agency Name | Fort Bend County Public Transportation |
Project Title | Rolling stock - Expansion |
Facility/Street/Highway | 3737 Bamore Rd Rosenberg, TX |
Limits | |
Description | Acquire six (10) additional large transit vehicles and bus support equipment for express services from Westpark Park & Ride. |
Timeframe | Long Term (More than 10 Years) |
Estimated Cost | $6,856,000.00 |
Project ID | 812 |
Agency Name | Fort Bend County Public Transportation |
Project Title | Bus Facility - Expand Parking Lot |
Facility/Street/Highway | 19820 FM 1093 Rd, Richmond, TX |
Limits | |
Description | Construct additional 500 spaces of park and ride to service express bus and vanpool services to the Energy Corridor, Greenway-Galleria, Downtown and other employment centers. Ultimate lot size to include 1,000 spaces. |
Timeframe | Long Term (More than 10 Years) |
Estimated Cost | $3,210,000.00 |
Project ID | 813 |
Agency Name | Fort Bend County Public Transportation |
Project Title | Operations & Maintenance Facility |
Facility/Street/Highway | North area of Fort Bend County |
Limits | |
Description | Construct a second Fort Bend Transit operations and maintenance facility to support expanded transit services. |
Timeframe | Long Term (More than 10 Years) |
Estimated Cost | $4,500,000.00 |
Project ID | 814 |
Agency Name | Fort Bend County Public Transportation |
Project Title | Bus Facility -Parking Garage |
Facility/Street/Highway | 14000 University Boulevard Sugar Land, TX |
Limits | |
Description | Construct structured parking garage of 2,500 spaces with bus and passenger accommodations for a permanent park and ride including dedicated bus bays with passenger platforms, passenger waiting shelters and transit information systems. |
Timeframe | Long Term (More than 10 Years) |
Estimated Cost | $73,083,000.00 |
Project ID | 815 |
Agency Name | Fort Bend County Public Transportation |
Project Title | Construction - HOV Lane |
Facility/Street/Highway | Westpark Toll Road |
Limits | SH 99 to IH69 |
Description | Construct bi-directional HOV lane on the Westpark toll road. |
Timeframe | Long Term (More than 10 Years) |
Estimated Cost | $0.00 |
Project ID | 822 |
Agency Name | Gulf Coast Transit District |
Project Title | GCTD Universal Accessibility Program |
Facility/Street/Highway | Various - Galveston & Brazoria County |
Limits | District Wide |
Description | The system consists of a total of 1019 unique Bus Stops. Based on field works, ridership, stakeholder input, and other data three hundred and thirty-one (331) bus stops will receive accessibly improvements in the way of signage, shelters, pads, trash cans and benches. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $4,300,000.00 |
Project ID | 823 |
Agency Name | Gulf Coast Transit District |
Project Title | Texas City Maintenance Facility |
Facility/Street/Highway | 1415 33rd St. North, Texas City, Texas |
Limits | None |
Description | The facilities will include a four-bay maintenance facility (9,000 square feet), a wash building with bus wash bay as well as an undercarriage wash bay with detailed cleaning space (4,564 square feet), an office building with 17 offices (4,800 square feet), a storage building (2,500 square feet), and a storage shed (1,100 square feet). |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $6,000,000.00 |
Project ID | 824 |
Agency Name | Gulf Coast Transit District |
Project Title | GCTD Training Facility and Transit Oriented Development Space |
Facility/Street/Highway | 1415 33rd St. North, Texas City, Texas |
Limits | None |
Description | GCTD has seeking funding to build a GCTD training facility (which can be flexed as community space) and transit oriented development space. The project will optimize the commercial value of the proposed development to generate maximum revenue by making the best use of the available piece of property under GCTD control, as well as to meet the needs of the surrounding community. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $10,000,000.00 |
Project ID | 825 |
Agency Name | Gulf Coast Transit District |
Project Title | Fleet Replacement |
Facility/Street/Highway | 1415 33rd St. North, Texas City, Texas |
Limits | None |
Description | Replacement of rolling stock (10 buses) that have reached the end of their useful life. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $1,500,000.00 |
Project ID | 826 |
Agency Name | Gulf Coast Transit District |
Project Title | Brazoria County Park & Ride Facility |
Facility/Street/Highway | 1415 33rd St. North, Texas City, Texas |
Limits | City of Pearland |
Description | Planning funds for Engineering, land lease/purchase pursual and other planning activities for a central hub for the Brazoria County Park and ride located in Pearland area to allow for full intergration of this and Metro busses for all Brazoria County residents and Metro UZA residents. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $1,250,000.00 |
Project ID | 827 |
Agency Name | Gulf Coast Transit District |
Project Title | Demand Response Coverage Area Increase |
Facility/Street/Highway | 1415 33rd St. North, Texas City, Texas |
Limits | Bacliff / San Leon / North Galveston County / City of Pearland and areas in North Brazoria County |
Description | Providing funds for new vehicles and operating costs for expansion of DR into Pearland (taking over for Harris county rides) and providing full services for the area, as well as Webster and Baycliff. This will be an expansion of the DR to the Houston UZA for areas not being serviced at a full level due to lack of resources. This expansion will focus on the Houston UZA areas in Galveston and Brazoria county. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $1,250,000.00 |
Project ID | 828 |
Agency Name | Harris County |
Project Title | Barker Cypress Road Capacity and Safety Improvements |
Facility/Street/Highway | Barker Cypress Road - HGAN |
Limits | From: Queenston Blvd/To: North of US 290 |
Description | The proposed project, which is primarily in existing right of way, widens Barker Cypress Road from four to six lanes, converting it from a four-lane asphalt section with open ditch drainage to a six-lane concrete urban section with curb-and-gutter including added sidewalks; the project includes reconstruction of the bridge over the railroad and intersection improvements along Barker Cypress Road at Queenston Boulevard, US 290 eastbound and westbound frontage roads. The improvements will reduce congestion, increase safety in the area, improve pedestrian accommodations, improve drainage due to modernizing the roadway to include curbs and gutters, reduce vehicular emissions attributable to severe traffic congestion, and decrease the travel delays for the Barker Cypress Corridor. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $60,000,000.00 |
Project ID | 829 |
Agency Name | Harris County Engineering |
Project Title | Safety Improvement Projects on Vision Zero High Injury Network |
Facility/Street/Highway | Various locations: Garth Road Stuebner Airline Road Jones Road Atascocita Road Grant Road Louetta Road W Lake Houston Parkway Spring Cypress Road Greenhouse Road (North) Greenhouse Road (South) |
Limits | Garth Road at Barbers Hill Rd intersection Stuebner Airline Road from N. of Spring Cypress Rd to FM1960 Jones Road from Grant Road to Ranchstone Drive Atascocita Road from Kings Parkway to FM1960 Grant Road from Perry Road to SH249 Louetta Road from SH249 to Cannaberry Way W Lake Houston Pkwy from Pine Cup Dr to Atascocita Middle School South Boundary Spring Cypress Rd from Memorial Springs Dr to W. of Valka Rd. Greenhouse Road (North) from Clay Road to Golden Wave Drive Greenhouse Road (South) from IH10 to Misty Cove Drive |
Description | Safety projects at various locations to mitigate serious injuries and fatalities on Vision Zero High Injury Network corridors. Signal modifications (leading pedestrian interval, crosswalks, ramps), pedestrian refuge, bike lane improvements, and street lighting. Total: $11,943,671 Garth Road $650,000 Stuebner Airline Road (Streetlights) $506,226 Jones Road $1,158,289 Atascocita Road $2,400,000 Grant Road $87,616 Louetta Road $759,338 W Lake Houston Pkwy $1,500,000 Spring Cypress Road $194,702 Greenhouse Road (North) $1,746,428 Greenhouse Road (South) $2,941,072 |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $11,943,671.00 |
Project ID | 830 |
Agency Name | Harris County Engineering |
Project Title | White Oak Bayou Bicycle Pedestrian Bridge Project |
Facility/Street/Highway | De Soto St. |
Limits | White Oak Bayou at De Soto St. |
Description | Pedestrian Bridge , approximately 220' feet span with a 14-ft clear width , and Trail to that will connect the Acres Homes neighborhood to the existing Trail on west-side of White Oak Bayou. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $4,300,000.00 |
Project ID | 831 |
Agency Name | Harris County Engineering |
Project Title | Mason Creek Trail Extension |
Facility/Street/Highway | Mason Rd./I-10, Colonial Pkwy./ Merchants Way/ 99, Mason Creek. |
Limits | Mason Rd. and Mason Access Rd. to I-10 and Highway 99. |
Description | Build Concrete/Asphalt 10' wide trail to connect TXDOT car/vanpool lot under I-10 and provide safe access to Asia Town, HCC, UofH Katy Campus, and Metro Grand Parkway Park and Ride. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $5,000,000.00 |
Project ID | 832 |
Agency Name | Harris County Engineering |
Project Title | Old Hwy 146 Reconstruction Project |
Facility/Street/Highway | Old Hwy 146 |
Limits | Port Rd to New Hwy 146 |
Description | Project includes a full road reconstruction to a concrete 4 lane road |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $6,000,000.00 |
Project ID | 833 |
Agency Name | Harris County Engineering |
Project Title | Rankin Road Access Management Project |
Facility/Street/Highway | Rankin Road |
Limits | IH 45 NBFR to Ranch View Trail |
Description | Add center two-way left turn lane, signal modifications (leading pedestrian intervals, crosswalks, ADA ramps), and sidewalk improvements to mitigate serious injuries and fatalities on 1.5 mile Vision Zero High Injury Network corridor. |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $12,200,000.00 |
Regional Goods Movement Questionnaire | View Questionnaire |
Project ID | 834 |
Agency Name | Harris County Engineering |
Project Title | ITS - CCTV Implementation |
Facility/Street/Highway | County Wide |
Limits | Unincorporated Harris County |
Description | Addition of 400 CCTV at various county-wide unincorporated locations to observe and monitor medium to high flood risk road segments. This includes implementation on existing traffic signal devices, new pole-mounted devices and a wireless 5yr contract and server upgrade/software transition costs as part of the estimate. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $6,700,000.00 |
Project ID | 835 |
Agency Name | Harris County Engineering |
Project Title | Fry Road/Cypress Rose Hill Road ITS Infrastructure Project |
Facility/Street/Highway | Fry Road |
Limits | Clay Road to Louetta Road/Huffmeister Road |
Description | Installation of ITS infrastructure along the Fry Road/Cypress Rose Hill Road Corridor, From Clay Road to Louetta Road/Huffmeister Road in Harris County |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $8,000,000.00 |
Project ID | 836 |
Agency Name | Harris County Engineering |
Project Title | W Montgomery Road Access Management Project |
Facility/Street/Highway | W Montgomery Road |
Limits | Tomball Pkwy to Wavell St |
Description | Add center two-way left turn lane, signal modifications (leading pedestrian interval, crosswalks, ramps), and sidwalk improvements to mitigate serious injuries and fatalities on 2 mile Vision Zero High Injury Network corridor. |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $8,700,000.00 |
Project ID | 837 |
Agency Name | Harris County Engineering |
Project Title | Navigation Blvd Access Management Project |
Facility/Street/Highway | Navigation Blvd |
Limits | Lockwood to S Sgt Macario Garcia |
Description | Project includes a median reconstruction to add a shared use path, landscaping and sidewalks. |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $10,000,000.00 |
Project ID | 838 |
Agency Name | Harris County Engineering |
Project Title | Allen Genoa Access Management Project |
Facility/Street/Highway | Allen Genoa |
Limits | Queens Road to Genoa Red Bluff |
Description | Project includes a safety study, design, access management, and implementation of recommended improvements. |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $10,000,000.00 |
Project ID | 839 |
Agency Name | Harris County Engineering |
Project Title | Aldine Mail Road Access Management Project |
Facility/Street/Highway | Aldine Mail Road |
Limits | Airline Dr to Easthampton Dr |
Description | Raised median improvements, driveway consolidation, signal modifications (leading pedestrian interval, crosswalks, ramps), pedestrian refuge, sidewalk, and street lighting improvements to mitigate serious injuries and fatalities on Vision Zero High Injury Network corridor. |
Timeframe | Medium Term (3-5 Years) |
Estimated Cost | $11,500,000.00 |
Project ID | 840 |
Agency Name | Harris County Engineering |
Project Title | Stuebner Airline Drive Access Management Project |
Facility/Street/Highway | Stuebner Airline Drive |
Limits | Lyons School Rd to Naremore Dr |
Description | Raised median improvements, driveway consolidation, signal modifications (leading pedestrian interval, crosswalks, ramps), and sidewalk improvements to mitigate serious injuries and fatalities on 4.5 mile Vision Zero High Injury Network corridor. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $11,800,000.00 |
Project ID | 841 |
Agency Name | Harris County Engineering |
Project Title | Wallisville Rd Reconstruction Project |
Facility/Street/Highway | Wallisville Road - HGAN |
Limits | Maxey to 1,000 East of Uvalde Rd |
Description | curb and gutter drainage, access management, shared use path, sidewalks and landscaping, Signal modifications (leading pedestrian interval, crosswalks, ramps) and signal timing improvements to mitigate serious injuries and fatalities on Vision Zero High Injury Network corridor. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $50,000,000.00 |
High Growth Area Needs Questionnaire | View Questionnaire |
Operational Improvements and Congestion Management Questionnaire | View Questionnaire |
Resiliency and State of Good Repair Questionnaire | View Questionnaire |
Project ID | 842 |
Agency Name | Harris County Engineering |
Project Title | E Mount Houston Reconstruction Project |
Facility/Street/Highway | E Mount Houston |
Limits | Keith Weiss to Hirsch Rd. |
Description | Project includes a full road reconstruction, drainage, sidewalks and landscaping |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $15,000,000.00 |
Project ID | 843 |
Agency Name | Harris County Engineering |
Project Title | Fairmont Parkway Accesss Management and Safety Improvement Project |
Facility/Street/Highway | Fairmont Parkway |
Limits | Allen Genoa to Broadway St |
Description | Project includes a safety study design, and implementation of recommended access management and safety improvements. |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $60,000,000.00 |
Operational Improvements and Congestion Management Questionnaire | View Questionnaire |
Project ID | 844 |
Agency Name | Harris County Engineering |
Project Title | CE King Parkway Project |
Facility/Street/Highway | CE King Parkway |
Limits | Tidwell to BW 8 |
Description | Expansion from 2 to 4 lanes and addition of bicycle pedestrian trail |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $27,000,000.00 |
High Growth Area Needs Questionnaire | View Questionnaire |
Operational Improvements and Congestion Management Questionnaire | View Questionnaire |
Resiliency and State of Good Repair Questionnaire | View Questionnaire |
Project ID | 845 |
Agency Name | Harris County Engineering |
Project Title | Veterans Memorial Drive Access Management Project |
Facility/Street/Highway | Veterans Memorial Drive |
Limits | FM 1960 to SH 249 |
Description | Raised median improvements, driveway consolidation, signal modifications (leading pedestrian interval, crosswalks, ramps), pedestrian refuge, sidewalk, and street lighting improvements to mitigate serious injuries and fatalities on 7.5 mile Vision Zero High Injury Network corridor. |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $34,100,000.00 |
Project ID | 846 |
Agency Name | Harris County Engineering |
Project Title | Spencer Hwy. Access Management Project |
Facility/Street/Highway | Spencer Hwy. |
Limits | I-45 to TX-146 |
Description | Raised median improvements, driveway consolidation, signal modifications (leading pedestrian interval, crosswalks, ramps), sidewalk, and bike lane improvements to mitigate serious injuries and fatalities on Vision Zero High Injury Network corridor. |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $28,200,000.00 |
Project ID | 847 |
Agency Name | Harris County Engineering |
Project Title | Gulf Bank Road Reconstruction Project |
Facility/Street/Highway | Gulf Bank Road |
Limits | IH-45 to Hardy Toll Road |
Description | The proposed improvements consist of reconstructing Gulf Bank Road as a 4-lane divided boulevard with 8-foot to 10-foot multi-use paths, pedestrian ramps, landscaping, modernized traffic signals at Sweetwater Lane and Airline Drive, a closed drainage system, detention ponds, and appropriate signage and striping |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $30,000,000.00 |
Project ID | 848 |
Agency Name | Harris County Engineering |
Project Title | Red Bluff Road Reconstruction Project |
Facility/Street/Highway | Red Bluff Rd. |
Limits | Spencer Hwy to Kirby road. |
Description | Project includes a full road reconstruction, shared use path and landscaping |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $31,500,000.00 |
Project ID | 849 |
Agency Name | Harris County Engineering |
Project Title | FM 2920 Intersection Improvements |
Facility/Street/Highway | FM 2920 |
Limits | US 290 to Telge Road |
Description | Construct full boulevard segment 1,000' north and south on major thoroughfares that intersect FM 2920. Should include drainage, ROW, signals, pedestrian accomodations, etc. |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $36,000,000.00 |
Project ID | 850 |
Agency Name | Harris County Engineering |
Project Title | Expanding ITS Infrastructure - Traffic Control signals |
Facility/Street/Highway | County Wide |
Limits | Unincorporated Harris County |
Description | Study, design, and construct traffic control signals upto 83 intersections that based on land use analysis, showcase an activity of 10k average daily trips, providing critical congestion, safety and access management improvements. |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $40,000,000.00 |
Project ID | 851 |
Agency Name | Harris County Engineering |
Project Title | Sheldon Road (North) Improvement Project |
Facility/Street/Highway | Sheldon Road |
Limits | US90 to Sheldon Ridge |
Description | Reconstruct and widen, existing 2 lane concrete overlaid with asphalt to 4 lanes of reinforced 12" concrete roadway. Includes bridge section, 2 major throughfare intersections and multiple industrial/ commercial business entrances. drainage, sidewalks and landscaping and safety. Considering existing railroad at-grade crossing to be a separate line item. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $22,800,000.00 |
Regional Goods Movement Questionnaire | View Questionnaire |
Project ID | 852 |
Agency Name | Harris County Engineering |
Project Title | ITS - Upgrading of Aging Infrastructure - Traffic Control signals |
Facility/Street/Highway | County Wide |
Limits | County Wide |
Description | Replacement of 450 aging traffic signal intersections (over 20 years) operated by Harris County Engineering. This includes new hardware, and a wireless 5yr contract and server upgrade/software transition costs as part of the estimate. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $55,000,000.00 |
Project ID | 853 |
Agency Name | Harris County Engineering |
Project Title | Market Street - Channelview Reconstruction Project |
Facility/Street/Highway | Market Street - Channelview |
Limits | IH-10 to Monmoth |
Description | Project includes a full road reconstruction, drainage, shared use path, sidewalks and landscaping |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $56,000,000.00 |
Project ID | 854 |
Agency Name | Harris County Engineering |
Project Title | Bourgeois Rd Street Improvements |
Facility/Street/Highway | Bourgeois Rd |
Limits | Cutten Rd to West Richey Rd |
Description | Sidewalks, Intersection and roadway improvements to address multimodal accessibility and traffic circulation. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $12,000,000.00 |
Project ID | 855 |
Agency Name | Harris County Engineering |
Project Title | Hillcroft Street Trail |
Facility/Street/Highway | Hillcroft Street |
Limits | Willow Bend to UPRR |
Description | Multimodal and safety improvements along Hillcroft Corridor |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $7,000,000.00 |
Project ID | 856 |
Agency Name | Harris County Engineering |
Project Title | Jacintoport Blvd Rehabililtation |
Facility/Street/Highway | Jacintoport Blvd |
Limits | Sheldon to Penn City Rd |
Description | Rehabiliataion of Jacintoport Blvd and extension to connect to Penn City Rd |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $10,000,000.00 |
Project ID | 857 |
Agency Name | Harris County Redevelopment Authority |
Project Title | Kirby Drive Extension |
Facility/Street/Highway | Street |
Limits | Holmes Rd. to Sam Houston Tollway South |
Description | Proposed Kirby Dr. is a multimodal thoroughfare consisiting of 3 segments: Segment 1 - construct a 4-lane from Holmes Rd. to Airport Blvd. with grade separation at Almeda Rd., Segment 2 - construct a bridge crossing Sims Bayou connecting to W. Orem Dr., Segment 3 - construct a 4-lane from Nichol Woods Dr. to Sam Houston Tollway South. Kirby Dr. is designated as a transit corridor from Fannin terminus at Feldman St. (west of Almeda Rd) to Airport Blvd. |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $110,000,000.00 |
Major Projects Questionnaire | View Questionnaire |
Project ID | 858 |
Agency Name | Harris County Redevelopment Authority |
Project Title | Almeda Road, IH 610, SH 288 Connectors |
Facility/Street/Highway | Street/Highway |
Limits | North bound SH 288 to west bound IH 610 frontage to Almeda Rd.; south bound Almeda Rd. near Holly Hall St. to east bound IH 610 to south bound SH 288; SH 288 south bound frontage road crossing Holmes Rd. |
Description | Proposed project consists of 3 segments: Segment 1 - Construct a single-lane from SH 288/IH610 off ramp to IH 610 westbound frontage; Segment 2 - Construct a single-lane elevated ramp connecting Almeda Rd. southbound to IH 610 eastbound; Segment 3 - construct a grade separation crossing Holmes Rd to have continuous SH 288 frontage southbound. |
Timeframe | Long Term (More than 10 Years) |
Estimated Cost | $150,000,000.00 |
Project ID | 859 |
Agency Name | METRO |
Project Title | 3 Additional Curb to Curb Services |
Facility/Street/Highway | VA |
Limits | Within defined zone |
Description | Shuttle service within selected communities that lack convenient access to transit $12 million/annually ($4 million/annually each) |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $60,000,000.00 |
Project ID | 860 |
Agency Name | METRO |
Project Title | 54 Scott BOOST Corridor |
Facility/Street/Highway | VA |
Limits | Downtown TC to MLK Health Center (Swingle Rd) |
Description | Optimize bus operations using a toolbox of improvements - traffic sign al prioritization, real-time travel information, shelters, level boarding, etc. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $25,000,000.00 |
Project ID | 861 |
Agency Name | METRO |
Project Title | 56 Airline/Montrose BOOST |
Facility/Street/Highway | VA |
Limits | TMC/Rice TC to Greenspoint TC |
Description | Optimize bus operations using a toolbox of improvements - traffic sign al prioritization, real-time travel information, shelters, level boarding, etc. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $30,000,000.00 |
Project ID | 862 |
Agency Name | METRO |
Project Title | 82 Westheimer BOOST |
Facility/Street/Highway | VA |
Limits | Milam @ SP 527 to SH 6 (West Oaks Mall) |
Description | Optimize bus operations using a toolbox of improvements - traffic sign al prioritization, real-time travel information, shelters, level boarding, etc. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $42,546,000.00 |
High Growth Area Needs Questionnaire | View Questionnaire |
Operational Improvements and Congestion Management Questionnaire | View Questionnaire |
Resiliency and State of Good Repair Questionnaire | View Questionnaire |
Project ID | 863 |
Agency Name | METRO |
Project Title | Bus Fleet Conversion to Zero Emissions Vehicles |
Facility/Street/Highway | VA - within METRO service area |
Limits | |
Description | Replace diesel buses with zero emissions buses $26 million/annually |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $130,000,000.00 |
Project ID | 864 |
Agency Name | METRO |
Project Title | Bus Shelter Program |
Facility/Street/Highway | VA - within METRO service area |
Limits | |
Description | Service area wide program to replace aging shelters |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $25,000,000.00 |
Project ID | 865 |
Agency Name | METRO |
Project Title | Denver Harbor Transit Center |
Facility/Street/Highway | Lockwood @ Temper |
Limits | |
Description | Relocate, Expand and Replace Existing Facility |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $34,500,000.00 |
Project ID | 866 |
Agency Name | METRO |
Project Title | Emergency & Community Services Bldg. |
Facility/Street/Highway | Main Street |
Limits | @ Downtown TC (Main St. and St. Joseph St.) |
Description | Construction of new METRO PD emergency services & transit customer services building |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $57,000,000.00 |
High Growth Area Needs Questionnaire | View Questionnaire |
Operational Improvements and Congestion Management Questionnaire | View Questionnaire |
Resiliency and State of Good Repair Questionnaire | View Questionnaire |
Transit Questionnaire | View Questionnaire |
Project ID | 867 |
Agency Name | METRO |
Project Title | Gulfton BRT |
Facility/Street/Highway | Gulfton St. |
Limits | Uptwon TC to Gulfton/Chimnery Rock Rd |
Description | Southern extension of Silver Line from Uptown TC to Gulfton |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $250,000,000.00 |
Project ID | 868 |
Agency Name | METRO |
Project Title | Hiram Clarke curb2curb service |
Facility/Street/Highway | VA |
Limits | Within defined zone |
Description | Shuttle service within selected communities that lack convenient access to transit $4 million/annually |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $20,000,000.00 |
Project ID | 869 |
Agency Name | METRO |
Project Title | I 69 2-way HOV - Phase 1 |
Facility/Street/Highway | I 69 S |
Limits | Milam @ SP 527 to IH 610 W |
Description | Convert 1-way to 2-way HOV |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $85,000,000.00 |
Project ID | 870 |
Agency Name | METRO |
Project Title | Inner Katy Busway |
Facility/Street/Highway | Northwest TC |
Limits | Downtown HOV connector ramp |
Description | Dedicated busway |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $665,000,000.00 |
Project ID | 871 |
Agency Name | METRO |
Project Title | Missouri City Park & Ride Capitalized Lease |
Facility/Street/Highway | SH 6 |
Limits | @ Vicksburg |
Description | Private partner to develop parking garage to service site; METRO to enter into extended lease for use of garage for P&R service |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $52,000,000.00 |
High Growth Area Needs Questionnaire | View Questionnaire |
Operational Improvements and Congestion Management Questionnaire | View Questionnaire |
Transit Questionnaire | View Questionnaire |
Project ID | 872 |
Agency Name | METRO |
Project Title | New Bus Operating Facility in Western Service Area |
Facility/Street/Highway | VA - within METRO service area |
Limits | |
Description | Construct new BOF to accommodate low-to no emmission infrastructure to support existing needs as well as new BRT lines. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $300,000,000.00 |
Project ID | 873 |
Agency Name | METRO |
Project Title | Northline TC |
Facility/Street/Highway | Fulton St. |
Limits | @ Julia St. |
Description | Construct new multi-level TC on new location to replace existing Northline TC |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $42,000,000.00 |
High Growth Area Needs Questionnaire | View Questionnaire |
Operational Improvements and Congestion Management Questionnaire | View Questionnaire |
Resiliency and State of Good Repair Questionnaire | View Questionnaire |
Transit Questionnaire | View Questionnaire |
Project ID | 874 |
Agency Name | METRO |
Project Title | Other BOOST Corridors (3) |
Facility/Street/Highway | VA |
Limits | VA |
Description | Optimize bus operations using a toolbox of improvements - traffic sign al prioritization, real-time travel information, shelters, level boarding, etc. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $75,000,000.00 |
Project ID | 875 |
Agency Name | METRO |
Project Title | Regional Transit Fare System Implementation - Fare Box Replacement |
Facility/Street/Highway | VA |
Limits | |
Description | Replace current multiagency fare boxes with new universal fareboxes that offer cash payment |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $100,000,000.00 |
Project ID | 876 |
Agency Name | METRO |
Project Title | TMC Transit Center State of Good Repair |
Facility/Street/Highway | Replace TMC transit center elevators, escalators |
Limits | Fannin @ Pressler |
Description | Replace elevators, escalators at TMC Red Line Transit Center |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $40,000,000.00 |
Project ID | 877 |
Agency Name | METRO |
Project Title | Sunnyside curb2curb service |
Facility/Street/Highway | VA |
Limits | Within defined zone |
Description | Shuttle service within selected communities that lack convenient access to transit $4 million/annually |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $20,000,000.00 |
Project ID | 878 |
Agency Name | METRO |
Project Title | Universal Accessibility (UA) - Phase 2 |
Facility/Street/Highway | VA - within METRO service area |
Limits | |
Description | Implement UA standards that exceed federal ADA requirements; improved bus shelters and pads, level boarding, assessible ramps, sidewalk improvements, and other stop improvements designed to improve accessibility |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $30,000,000.00 |
Project ID | 879 |
Agency Name | METRO |
Project Title | West Bellfort Park and Ride |
Facility/Street/Highway | West Bellfort Ave. |
Limits | @ Roark Road |
Description | Reconstruct existing park and ride to add capacity and improve service |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $80,000,000.00 |
Project ID | 880 |
Agency Name | METRO |
Project Title | Wheeler Intermodal Terminal |
Facility/Street/Highway | @ Main St. |
Limits | |
Description | Replace existing TC with expanded intermodal terminal to connect light rail and University BRT |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $60,000,000.00 |
Project ID | 881 |
Agency Name | METRO |
Project Title | Zero Emissionsn Infrastructure & Readiness |
Facility/Street/Highway | VA - within METRO service area |
Limits | |
Description | Retrofit existing facilities for charging/refueliing infrastructure and related improvements to psupport fleet conversion to ZEVs |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $100,000,000.00 |
Project ID | 882 |
Agency Name | METRO |
Project Title | Other BOOST Corridors (4 corridors) |
Facility/Street/Highway | VA |
Limits | VA |
Description | Optimize bus operations using a toolbox of improvements - traffic sign al prioritization, real-time travel information, shelters, level boarding, etc. |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $100,000,000.00 |
Project ID | 883 |
Agency Name | METRO |
Project Title | Buffalo Bayou Day Lot |
Facility/Street/Highway | @ McKee St. |
Limits | |
Description | Relocate and expand existing mid-day layover facility |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $100,000,000.00 |
Project ID | 884 |
Agency Name | METRO |
Project Title | Connection to HSR terminal |
Facility/Street/Highway | North Post Oak |
Limits | NWTC to HSR Terminal (former site of NW Mall) |
Description | New busway |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $106,000,000.00 |
Project ID | 885 |
Agency Name | METRO |
Project Title | Extension of Purple Line |
Facility/Street/Highway | Rusk/Capitol St. |
Limits | Theater District to Municipal Courthouse |
Description | Extend existing LRT |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $40,000,000.00 |
Project ID | 886 |
Agency Name | METRO |
Project Title | Gessner BOOST |
Facility/Street/Highway | Gessner Rd. |
Limits | W Little York P&R to Fondren Meadow Dr. |
Description | Optimize bus operations using a toolbox of improvements - traffic sign al prioritization, real-time travel information, shelters, level boarding, etc. |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $25,000,000.00 |
Project ID | 887 |
Agency Name | METRO |
Project Title | Gulfton TC |
Facility/Street/Highway | Gulfton St. |
Limits | @Gulfton St |
Description | Construct new transit center |
Timeframe | Long Term (6-10 Years) |
Estimated Cost | $52,000,000.00 |
Project ID | 888 |
Agency Name | METRO |
Project Title | I 45 S HOV |
Facility/Street/Highway | Downtown |
Limits | Bay Area Blvd. |
Description | Convert 1-way to 2-way HOV |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $122,000,000.00 |
Project ID | 889 |
Agency Name | METRO |
Project Title | I 45 S HOV |
Facility/Street/Highway | I 45 S |
Limits | Nasa 1 Bypass to SH 146 |
Description | Construct 2-way diamond lanes |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $668,000,000.00 |
Project ID | 890 |
Agency Name | METRO |
Project Title | I 69 2-way HOV - Phase 2 |
Facility/Street/Highway | I 69 S |
Limits | Loop 610W to BW 8 |
Description | Convert 1-way to 2-way HOV |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $50,000,000.00 |
Major Projects Questionnaire | View Questionnaire |
Project ID | 891 |
Agency Name | METRO |
Project Title | Louetta P&R |
Facility/Street/Highway | SH 249 |
Limits | @ Louetta Rd. |
Description | Construct new park & ride |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $52,000,000.00 |
Project ID | 892 |
Agency Name | METRO |
Project Title | Missouri City Park & Ride |
Facility/Street/Highway | US 90A@BW 8 |
Limits | |
Description | Construct new park and ride in vicinity of US 90A and BW 8 |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $36,000,000.00 |
Project ID | 893 |
Agency Name | METRO |
Project Title | P&R Service Enhancements/FLM Improvements for Reverse Commute |
Facility/Street/Highway | VA - within METRO service area |
Limits | |
Description | Modify/improve service and facilities to accommodate reverse commute and enhance FLM connectivity |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $20,000,000.00 |
Project ID | 894 |
Agency Name | METRO |
Project Title | SH 249 HOV |
Facility/Street/Highway | SH 249 |
Limits | Boudreaux Rd. to Hollister Dr. |
Description | Construct new 2-way HOV facility |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $301,000,000.00 |
Project ID | 895 |
Agency Name | METRO |
Project Title | SH 249 P&R |
Facility/Street/Highway | SH 249 |
Limits | @ Boudreaux Rd. |
Description | Construct new park & ride |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $52,000,000.00 |
Project ID | 896 |
Agency Name | METRO |
Project Title | State of Good Repair |
Facility/Street/Highway | VA - within METRO service area |
Limits | |
Description | Upgrade, rehab and retrofit facilities and infrastructure as needed to maintain SOGR |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $100,000,000.00 |
Project ID | 897 |
Agency Name | METRO |
Project Title | Tidwell Intermodal Center |
Facility/Street/Highway | VA |
Limits | @ Tidwell |
Description | Construct new multimodal center |
Timeframe | Short Term (6-10 Years) |
Estimated Cost | $52,000,000.00 |
Project ID | 898 |
Agency Name | METRO |
Project Title | Universal Accessibility (UA) - Phase 3 |
Facility/Street/Highway | VA - within METRO service area |
Limits | |
Description | Program to standardize all bus stops to meet & exceed ADA requirements |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $30,000,000.00 |
Project ID | 899 |
Agency Name | METRO |
Project Title | University BRT |
Facility/Street/Highway | VA |
Limits | |
Description | Construct new BRT corridor |
Timeframe | Short Term (6-10 Years) |
Estimated Cost | $1,760,000,000.00 |
Project ID | 900 |
Agency Name | METRO |
Project Title | Westheimer Signature Bus Service |
Facility/Street/Highway | VA |
Limits | Downtown to SH 6 (West Oaks Mall) |
Description | Rolling Stop for high speed overlay service |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $30,000,000.00 |
Project ID | 901 |
Agency Name | METRO |
Project Title | Willowbrook TC |
Facility/Street/Highway | SH 249 |
Limits | @ FM 1960 |
Description | Construct new transit center |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $35,000,000.00 |
Project ID | 902 |
Agency Name | METRO |
Project Title | BRT Service to IAH |
Facility/Street/Highway | VA |
Limits | Downtown to IAH |
Description | New BRT corridor |
Timeframe | Long Term (More Than 10 Years) |
Estimated Cost | $358,000,000.00 |
Project ID | 903 |
Agency Name | METRO |
Project Title | Downtown Transit Corridors |
Facility/Street/Highway | VA |
Limits | Downtown Bus Routes |
Description | Redesign and construct bus lanes to improve signage and pavement markings , signal timing and operations, bus stop design and spacing, and other passenger improvements |
Timeframe | Short Term (0-5 years) |
Estimated Cost | $35,000,000.00 |
Project ID | 904 |
Agency Name | METRO |
Project Title | Fairfield Park & Ride |
Facility/Street/Highway | US 290 |
Limits | @ US 290 & SH 99 |
Description | Construct new park & ride |
Timeframe | Long Term (More Than 10 Years) |
Estimated Cost | $35,000,000.00 |
Project ID | 905 |
Agency Name | METRO |
Project Title | Future BOOST Corridors |
Facility/Street/Highway | VA - within METRO service area |
Limits | |
Description | Optimize bus operations using a toolbox of improvements - traffic sign al prioritization, real-time travel information, shelters, level boarding, etc. |
Timeframe | Long Term (More Than 10 Years) |
Estimated Cost | $103,000,000.00 |
Project ID | 906 |
Agency Name | METRO |
Project Title | Hempstead Rd. TC |
Facility/Street/Highway | Hempstead Rd. |
Limits | @ North Post Oak Rd. |
Description | Construct new transit center |
Timeframe | Long Term (More Than 10 Years) |
Estimated Cost | $24,000,000.00 |
Project ID | 907 |
Agency Name | METRO |
Project Title | Kingwood Dr. P&R |
Facility/Street/Highway | US 59 N |
Limits | @ Kingwood Dr. |
Description | Construct new park & ride |
Timeframe | Long Term (More Than 10 Years) |
Estimated Cost | $63,000,000.00 |
Project ID | 908 |
Agency Name | METRO |
Project Title | LRT Extension to Hobby Airport |
Facility/Street/Highway | VA |
Limits | MLK/Griggs Rd to Hobby Airport |
Description | Extension of Green/Purple to airport |
Timeframe | Long Term (More Than 10 Years) |
Estimated Cost | $1,500,000,000.00 |
Project ID | 909 |
Agency Name | METRO |
Project Title | Maxey Rd. P&R |
Facility/Street/Highway | Maxey Rd. |
Limits | @ Maxey Rd. |
Description | Construct new park & ride |
Timeframe | Long Term (More Than 10 Years) |
Estimated Cost | $41,000,000.00 |
Project ID | 910 |
Agency Name | METRO |
Project Title | Memorial City TC |
Facility/Street/Highway | I 10 W |
Limits | @ Gessner Rd. |
Description | New TC in vicinity of Gessner and I-10 W |
Timeframe | Long Term (More Than 10 Years) |
Estimated Cost | $35,000,000.00 |
Project ID | 911 |
Agency Name | METRO |
Project Title | Park PLace Multimodal Center |
Facility/Street/Highway | Green Line |
Limits | @ Park Place Blvd |
Description | Construct new multimodal center |
Timeframe | Long Term (More Than 10 Years) |
Estimated Cost | $66,000,000.00 |
Project ID | 912 |
Agency Name | METRO |
Project Title | Red Line Extension |
Facility/Street/Highway | VA |
Limits | Northline TC to N Shepherd P&R |
Description | Extension of Red Line |
Timeframe | Long Term (More Than 10 Years) |
Estimated Cost | $1,097,000,000.00 |
Project ID | 913 |
Agency Name | METRO |
Project Title | Red Line Extension |
Facility/Street/Highway | VA |
Limits | Fannin South TC to Missouri City |
Description | Red Line extension (planning phase) |
Timeframe | Long Term (More Than 10 Years) |
Estimated Cost | $18,000,000.00 |
Project ID | 914 |
Agency Name | METRO |
Project Title | Southwest Corridor |
Facility/Street/Highway | US 90A Corridor |
Limits | TMC to Missouri City |
Description | Develop new transit corridor |
Timeframe | Long Term (More Than 10 Years) |
Estimated Cost | $365,000,000.00 |
Project ID | 915 |
Agency Name | METRO |
Project Title | Springwoods P&R |
Facility/Street/Highway | I 45 N |
Limits | @ Springwoods Village Pkwy |
Description | Construct new park & ride |
Timeframe | Long Term (More Than 10 Years) |
Estimated Cost | $83,000,000.00 |
Project ID | 916 |
Agency Name | METRO |
Project Title | State of Good Repair |
Facility/Street/Highway | VA - within METRO service area |
Limits | |
Description | Upgrade, rehab and retrofit facilities and infrastructure as needed to maintain SOGR |
Timeframe | Long Term (More Than 10 Years) |
Estimated Cost | $1,000,000,000.00 |
Project ID | 917 |
Agency Name | METRO |
Project Title | TMC Transit Improvement and Service Integration |
Facility/Street/Highway | |
Limits | @ TMC |
Description | Improve and better integrate local bus, commuter bus and LRT service within TMC |
Timeframe | Long Term (More Than 10 Years) |
Estimated Cost | $30,000,000.00 |
Project ID | 918 |
Agency Name | METRO |
Project Title | West Houston BRT Corridor |
Facility/Street/Highway | BW 8 |
Limits | Missouri City P&R to W Little York P&R |
Description | New BRT corridor |
Timeframe | Long Term (More Than 10 Years) |
Estimated Cost | $1,700,000,000.00 |
Project ID | 919 |
Agency Name | METRO |
Project Title | Other BOOST Corridors (6 corridors) |
Facility/Street/Highway | VA |
Limits | VA |
Description | Optimize bus operations using a toolbox of improvements - traffic sign al prioritization, real-time travel information, shelters, level boarding, etc. |
Timeframe | Long Term (More than 10 Years) |
Estimated Cost | $150,000,000.00 |
Project ID | 920 |
Agency Name | METRO |
Project Title | Future Signature Service |
Facility/Street/Highway | VA - within METRO service area |
Limits | |
Description | Place Holder |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $75,000,000.00 |
Project ID | 921 |
Agency Name | METRO |
Project Title | Future Signature Service |
Facility/Street/Highway | VA - within METRO service area |
Limits | |
Description | Place Holder |
Timeframe | Long Term (More Than 10 Years) |
Estimated Cost | $75,000,000.00 |
Project ID | 922 |
Agency Name | METRO |
Project Title | Regional Vanpool |
Facility/Street/Highway | VA |
Limits | |
Description | Place Holder |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $0.00 |
Project ID | 923 |
Agency Name | METRO |
Project Title | Regional Vanpool |
Facility/Street/Highway | VA |
Limits | |
Description | Place Holder |
Timeframe | Long Term (More Than 10 Years) |
Estimated Cost | $0.00 |
Project ID | 924 |
Agency Name | METRO |
Project Title | Replacement Buses |
Facility/Street/Highway | VA - within METRO service area |
Limits | |
Description | Place Holder |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $75,000,000.00 |
Project ID | 925 |
Agency Name | METRO |
Project Title | Replacement Buses |
Facility/Street/Highway | VA - within METRO service area |
Limits | |
Description | Place Holder |
Timeframe | Long Term (More Than 10 Years) |
Estimated Cost | $75,000,000.00 |
Project ID | 926 |
Agency Name | METRO |
Project Title | METROLift Vans |
Facility/Street/Highway | VA - within METRO service area |
Limits | |
Description | Place Holder |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $50,000,000.00 |
Project ID | 927 |
Agency Name | METRO |
Project Title | METROLift Vans |
Facility/Street/Highway | VA - within METRO service area |
Limits | |
Description | Place Holder |
Timeframe | Long Term (More Than 10 Years) |
Estimated Cost | $50,000,000.00 |
Project ID | 928 |
Agency Name | METRO |
Project Title | ADA Support |
Facility/Street/Highway | VA - within METRO service area |
Limits | |
Description | Place Holder |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $30,000,000.00 |
Project ID | 929 |
Agency Name | METRO |
Project Title | ADA Support |
Facility/Street/Highway | VA - within METRO service area |
Limits | |
Description | Place Holder |
Timeframe | Long Term (More Than 10 Years) |
Estimated Cost | $30,000,000.00 |
Project ID | 930 |
Agency Name | North Houston District |
Project Title | Imperial Valley Walking & Biking Connections (Revised) |
Facility/Street/Highway | Imperial Valley Drive; Regional Park Drive; Wayforest |
Limits | Imperial Valley Drive from 50' north of Rankin Road to Greens Road; Regional Park Drive from Imperial Valley Drive to Chisholm Trail; Wayforest Dr. from Regional Park Dr. to Seminar Dr. |
Description | Provide safe, connected sidewalks and trails that connect schools, neighborhoods, businesses, community facilities to Tom Wussow Park, new Central Park and Greens Bayou Trail. This includes 5' and 6' wide sidewalks and 10' wide multi-use sidepaths, new bus pads and improved intersections with high-visibility crosswalks, pedestrian refuges, and improved pedestrian signal timing. Improved pedestrian and bicycle crossings on Imperial Valley Dr. include Rectangular Rapid Flashing Beacons (RRFB) and upgraded signage and striping to comport with City's new mid-block crossing standards. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $4,246,000.00 |
Project ID | 931 |
Agency Name | North Houston District |
Project Title | I-45 Trail Connector |
Facility/Street/Highway | Greens Bayou |
Limits | North Houston Bike Park to Knobcrest Drive |
Description | Construct an off-street trail on both sides of Greens Bayou across I-45 creating safe, regional connections between parks, jobs, community facilities, and neighborhoods. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $1,276,500.00 |
Project ID | 932 |
Agency Name | North Houston District |
Project Title | Jack Drake Park to West Hardy Trail Connector |
Facility/Street/Highway | Greens Bayou |
Limits | Jack Drake Park to W. Hardy Rd |
Description | Develop an off-street trail on the south side of Greens Bayou connecting Jack Drake Park to pedestrian and bicycle connections at W. Hardy Rd along Greens Bayou to increase safe, accessible multimodal connections for the community. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $390,000.00 |
Project ID | 933 |
Agency Name | North Houston District |
Project Title | West Road Safety & Access Improvements |
Facility/Street/Highway | West Road |
Limits | I-45 Frontage Road to Airline Dr |
Description | Reconstruct the corridor as a 4-lane divided corridor improve current poor roadway conditions and pavement quality, fill gaps in sidewalk infrastructure and bring existing sidewalks in poor condition up to ADA standards, enhance crosswalks and intersections for multimodal safety, and improve bus stops with bus pads and shelters. Will provide improved access to Aldine High School and existing businesses while also creating opportunities for placemaking for the neighborhoods to the east of Airline Drive. |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $5,650,000.00 |
Project ID | 934 |
Agency Name | North Houston District |
Project Title | Rankin Road Corridor Improvements |
Facility/Street/Highway | Rankin Road |
Limits | I-45 to West Hardy Road |
Description | Reconstruct Rankin Road to be a 4-lane curb and gutter facility with drainage improvements and new sidewalks facilitating safe connections for people walking or accessing transit from surrounding destinations and neighborhoods. Improvements will improve accessibility for freight to surrounding industrial uses and accessibility. |
Timeframe | Long Term (More than 10 Years) |
Estimated Cost | $21,795,000.00 |
Project ID | 935 |
Agency Name | PORT OF HOUSTON AUTHORITY |
Project Title | Second Rail Track |
Facility/Street/Highway | PORT TERMINAL RAILROAD ASSN (PTRA) TRACK |
Limits | STRANG YARD to RED BLUFF |
Description | CONSTRUCT 2ND RAIL TRACK |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $97,100,000.00 |
Project ID | 936 |
Agency Name | PORT OF HOUSTON AUTHORITY |
Project Title | Broadway Expansion |
Facility/Street/Highway | BROADWAY ST |
Limits | BARBOURS CUT BLVD to L STREET N |
Description | WIDEN TO 4-LANE ROAD |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $2,632,382.00 |
Project ID | 937 |
Agency Name | PORT OF HOUSTON AUTHORITY |
Project Title | Bayport Intermodal Yard |
Facility/Street/Highway | RAILROAD TRACK |
Limits | AT BAYPORT |
Description | CONSTRUCT INTERMODAL RAIL YARD INCL 6 STORAGE TRACKS, 3 WORKING TRACKS, AND 1 CONTAINER TRACK |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $61,000,000.00 |
Project ID | 938 |
Agency Name | PORT OF HOUSTON AUTHORITY |
Project Title | Double Track Rail |
Facility/Street/Highway | PORT TERMINAL RAILROAD ASSN (PTRA) TRACK |
Limits | MAINLINE TO INTERMODAL YARD |
Description | CONSTRUCT DOUBLE TRACK RAIL LINES AND RUN-AROUND TRACK FROM MAINLINE TO THE BAYPORT TERMINAL INTERMODAL YARD |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $29,600,000.00 |
Project ID | 939 |
Agency Name | PORT OF HOUSTON AUTHORITY |
Project Title | BPT Intermodal Yard |
Facility/Street/Highway | RAILROAD TRACK |
Limits | AT BAYPORT |
Description | CONSTRUCT INTERMODAL RAIL YARD INCL 6 STORAGE TRACKS, 3 WORKING TRACKS, 2 CONTAINER TRACKS AND 1 RUNAROUND TRACK |
Timeframe | Long Term (More than 10 Years) |
Estimated Cost | $44,398,000.00 |
Project ID | 940 |
Agency Name | PORT OF HOUSTON AUTHORITY |
Project Title | Grade Separation Expansion over Rail |
Facility/Street/Highway | SPENCER HWY |
Limits | AT MAINLINE DOUBLE-RAILTRACK TO NE DOUBLE RAILTRACK |
Description | CONSTRUCT GRADE SEPARATION OVER MAINLINE DOUBLE-RAIL TRACK |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $16,300,000.00 |
Project ID | 941 |
Agency Name | PORT OF HOUSTON AUTHORITY |
Project Title | Bayport Container Terminal Overpass. |
Facility/Street/Highway | PORT RD |
Limits | FM 146 TO CRUISE ST |
Description | CONSTRUCTION OF RAILROAD OVERPASS ON PORT ROAD LEADING TO THE BAYPORT CONTAINER TERMINAL. |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $18,996,668.00 |
Regional Goods Movement Questionnaire | View Questionnaire |
Project ID | 942 |
Agency Name | PORT OF HOUSTON AUTHORITY |
Project Title | Port Houston Barbours Cut Terminal Container Yard 6 Upgrade |
Facility/Street/Highway | BARBOURS CUT CONTAINER YARD |
Limits | AT BARBOURS CUT |
Description | RECONSTRUCT CONTAINER YARD 6 AT BAYPORT TO INCLUDE STRENGTHEN INFRASTRUCTURE. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $42,250,000.00 |
Regional Goods Movement Questionnaire | View Questionnaire |
Project ID | 943 |
Agency Name | PORT OF HOUSTON AUTHORITY |
Project Title | Port Houston Barbours Cut Terminal Container Yard 7 Upgrade |
Facility/Street/Highway | BARBOURS CUT CONTAINER YARD |
Limits | AT BARBOURS CUT |
Description | RECONSTRUCT CONTAINER YARD 7 AT BAYPORT TO INCLUDE STRENGTHEN INFRASTRUCTURE. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $53,300,000.00 |
Regional Goods Movement Questionnaire | View Questionnaire |
Project ID | 944 |
Agency Name | PORT OF HOUSTON AUTHORITY |
Project Title | Barbours Cut Container Terminal Wharf Rehabilitation |
Facility/Street/Highway | BARBOURS CUT WHARF |
Limits | AT BARBOURS CUT |
Description | RECONSTRUCT 1,337 LF OF WHARF AT BAYPORT TO INCLUDE STRENGTHEN INFRASTRUCTURE. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $69,342,000.00 |
Regional Goods Movement Questionnaire | View Questionnaire |
Project ID | 945 |
Agency Name | PORT OF HOUSTON AUTHORITY |
Project Title | Keep the Supply Chain Moving with the Bayport Terminal Yard Expansion |
Facility/Street/Highway | BAYPORT CONTAINER YARD |
Limits | AT BAYPORT |
Description | CONSTRUCT 46 ACRES OF CONTAINER YARD AT BAYPORT TERMINAL. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $95,018,093.00 |
Regional Goods Movement Questionnaire | View Questionnaire |
Project ID | 946 |
Agency Name | PORT OF HOUSTON AUTHORITY/other |
Project Title | Freight Shuttle |
Facility/Street/Highway | Off-network |
Limits | Harris County to Chambers County |
Description | Build an alternative freight movement system connecting Port Houston's container terminals and distribution and warehousing in Chambers County |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $700,000,000.00 |
Project ID | 947 |
Agency Name | PORT OF HOUSTON AUTHORITY/HCTRA |
Project Title | BW-8 connectivity |
Facility/Street/Highway | Intersection of SH-225 and Jacintoport Blvd |
Limits | Jacintoport Blvd and BW-8 intersection |
Description | Design and construct connectivity between PH BW-8 property and BW-8 |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $0.00 |
Project ID | 948 |
Agency Name | PORT OF HOUSTON AUTHORITY/Harris County |
Project Title | Old SH-146 widening |
Facility/Street/Highway | Old SH-146 |
Limits | Red Bluff Road and Port Road |
Description | WIDEN TO 4-LANE ROAD |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $0.00 |
Project ID | 949 |
Agency Name | PORT OF HOUSTON AUTHORITY/TxDOT |
Project Title | SH-225 PEL Projects (BCT connectivity) |
Facility/Street/Highway | Barbours Cut Blvd and SH-146 connectivity |
Limits | Barbours Cut Blvd and SH-146 |
Description | Design and construct improved connectivity between SH-146, SH-225 and Barbours Cut Blvd |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $0.00 |
Project ID | 950 |
Agency Name | PORT OF HOUSTON AUTHORITY/TxDOT |
Project Title | 610 Bridge replacement and associated connectivity |
Facility/Street/Highway | 610 East Ship Channel Bridge |
Limits | I-10 to the north and I-45 to the south and all associated connectivity inbetween |
Description | Design and construct a taller and wider replacement bridge over the HSC |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $2,400,000,000.00 |
Project ID | 951 |
Agency Name | PORT OF HOUSTON AUTHORITY/Harris County |
Project Title | Barbours Cut Blvd widening |
Facility/Street/Highway | Barbours Cut Blvd |
Limits | SH-146 and termination at Barbours Cut Terminal |
Description | Widen to 6-lane road and coordinated with Barbours Cut Blvd connectivity to SH-146 |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $0.00 |
Project ID | 952 |
Agency Name | PORT OF HOUSTON AUTHORITY/Harris County |
Project Title | Sheldon Road widening |
Facility/Street/Highway | Sheldon Road |
Limits | Market Street to Jacintoport Blvd |
Description | Widen and rehab Sheldon Road |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $14,000,000.00 |
Project ID | 953 |
Agency Name | PORT OF HOUSTON AUTHORITY/Harris County |
Project Title | Jacintoport Blvd widening and connection to Penn City Road (from Peninsula Blvd to Penn City) |
Facility/Street/Highway | Jacintoport Blvd |
Limits | Peninsula Blvd and Penn City Road |
Description | Widen and rehab Jacontoport Blvd |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $0.00 |
Project ID | 954 |
Agency Name | PORT OF HOUSTON AUTHORITY/Harris County |
Project Title | Penn City Road widening |
Facility/Street/Highway | Penn City Road |
Limits | Jacintoport Blvd and I-10 frontage road |
Description | Widen and rehab Penn City Road |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $0.00 |
Project ID | 955 |
Agency Name | PORT OF HOUSTON AUTHORITY/other |
Project Title | Alternative fuels fueling stations |
Facility/Street/Highway | Varies |
Limits | Varies |
Description | Install eight alternative fuels fueing stations. |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $70,000,000.00 |
Project ID | 956 |
Agency Name | PORT OF HOUSTON AUTHORITY |
Project Title | u-shaped property connectivity |
Facility/Street/Highway | Port Road Connectivity to PH u-shaped property |
Limits | Port Road |
Description | Build connectivity between PH's u-shaped property and Port Road at the NW corner of Port Road and SH-146 |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $0.00 |
Project ID | 957 |
Agency Name | PORT OF HOUSTON AUTHORITY |
Project Title | Terminal 3 connectivity |
Facility/Street/Highway | Port Houston Temrinal 3. |
Limits | Unknown |
Description | Construct the connecting roads to Port Houston's Terminal 3 |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $0.00 |
Project ID | 958 |
Agency Name | The Woodlands Township |
Project Title | Commuter Bus Purchase |
Facility/Street/Highway | N/A |
Limits | N/A |
Description | Purchase 32 commuter bus vehicles. |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $31,280,000.00 |
Project ID | 959 |
Agency Name | The Woodlands Township |
Project Title | Transit Maintenance Facility |
Facility/Street/Highway | N/A |
Limits | N/A |
Description | Design and construct new transit maintenance facility |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $10,000,000.00 |
Project ID | 960 |
Agency Name | The Woodlands Township |
Project Title | Safe School Access Shared Use Paths |
Facility/Street/Highway | Kuykendahl Road Kuykendahl Road Kuykendahl Road Panther Creek Drive Research Forest Dr |
Limits | HEB (3601 FM 1488) to FM 1488 Lake Woodlands Drive to Research Forest Drive Creekside Green Drive to Timarron Drive McCullough JHS (East of Coralberry Road) to Spiral Vine Circle Woodlands High School (Cats Cradle Drive) to Bear Branch Sports Fields (East of East Trillium Circle) |
Description | Fill bicycle/pedestrian gaps via 12-FT wide concrete paths |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $1,000,000.00 |
Project ID | 961 |
Agency Name | The Woodlands Township |
Project Title | Harpers Landing / SH 242 Connection |
Facility/Street/Highway | SH 242 Trade Center Parkway |
Limits | FM 1488 to Trade Center Pkwy SH 242 to Harpers Landing |
Description | Construct 5.5 mile 12-FT wide shared use path to include intersection safety improvements. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $8,350,000.00 |
Project ID | 962 |
Agency Name | TxDOT Beaumont District |
Project Title | IH-10 Ramp Relocations |
Facility/Street/Highway | IH-10 |
Limits | From SH 146 to FM 565 |
Description | Relocate entrance / exit ramps |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $35,000,000.00 |
Regional Goods Movement Questionnaire | View Questionnaire |
Project ID | 963 |
Agency Name | TxDOT Beaumont District |
Project Title | FM 1405 Widening |
Facility/Street/Highway | FM 1405 |
Limits | From SH 99 south to FM 2354 |
Description | Widen from 2 to 4 lanes with center turn lane |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $16,000,000.00 |
High Growth Area Needs Questionnaire | View Questionnaire |
Operational Improvements and Congestion Management Questionnaire | View Questionnaire |
Regional Goods Movement Questionnaire | View Questionnaire |
Project ID | 964 |
Agency Name | TxDOT Beaumont District |
Project Title | FM 1405 Widening |
Facility/Street/Highway | FM 1405 |
Limits | From FM 565 south to SH 99 |
Description | Widen from 2 to 4 lanes with center turn lane |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $16,000,000.00 |
High Growth Area Needs Questionnaire | View Questionnaire |
Operational Improvements and Congestion Management Questionnaire | View Questionnaire |
Regional Goods Movement Questionnaire | View Questionnaire |
Project ID | 965 |
Agency Name | TxDOT Beaumont District |
Project Title | FM 565 Widening |
Facility/Street/Highway | FM 565 |
Limits | From FM 1409 to FM 3180 |
Description | Add center turn lane and 10 foot shoulders |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $15,000,000.00 |
Operational Improvements and Congestion Management Questionnaire | View Questionnaire |
Project ID | 966 |
Agency Name | TxDOT Beaumont District |
Project Title | SH 105 Widening |
Facility/Street/Highway | SH 105 |
Limits | From Montgomery County Line to BS 105T |
Description | Widen from 2 to 4 lanes divided |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $20,000,000.00 |
Regional Goods Movement Questionnaire | View Questionnaire |
Project ID | 967 |
Agency Name | TxDOT Beaumont District |
Project Title | FM 2025 Widening |
Facility/Street/Highway | FM 2025 |
Limits | From US 59 to SL 573 |
Description | Widen roadway and bridge to include turn lanes. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $4,500,000.00 |
High Growth Area Needs Questionnaire | View Questionnaire |
Operational Improvements and Congestion Management Questionnaire | View Questionnaire |
Project ID | 968 |
Agency Name | TxDOT Beaumont District |
Project Title | FM 1960 Widening |
Facility/Street/Highway | FM 1960 |
Limits | From SH 321 to SH 99 |
Description | Widen from 2 to 4 lanes |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $27,500,000.00 |
High Growth Area Needs Questionnaire | View Questionnaire |
Operational Improvements and Congestion Management Questionnaire | View Questionnaire |
Regional Goods Movement Questionnaire | View Questionnaire |
Project ID | 969 |
Agency Name | TxDOT Beaumont District |
Project Title | SH 146 TURN LANES |
Facility/Street/Highway | SH 146 |
Limits | AT IH10 |
Description | DUAL TURN LANES FOR NB |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $1,000,000.00 |
Regional Goods Movement Questionnaire | View Questionnaire |
Project ID | 970 |
Agency Name | TxDOT Beaumont District |
Project Title | SH 146 Widening |
Facility/Street/Highway | SH 146 |
Limits | From IH-10 south to Cedar Bayou |
Description | Widen from 4 to 6 lanes |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $100,000,000.00 |
High Growth Area Needs Questionnaire | View Questionnaire |
Major Projects Questionnaire | View Questionnaire |
Operational Improvements and Congestion Management Questionnaire | View Questionnaire |
Regional Goods Movement Questionnaire | View Questionnaire |
Project ID | 971 |
Agency Name | TxDOT Beaumont District |
Project Title | US 90 - Klemp Rd Interchange |
Facility/Street/Highway | US 90 |
Limits | At Klemp Rd |
Description | Construct new interchange on US 90 with RR overpass on Klemp Rd |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $70,000,000.00 |
High Growth Area Needs Questionnaire | View Questionnaire |
Operational Improvements and Congestion Management Questionnaire | View Questionnaire |
Resiliency and State of Good Repair Questionnaire | View Questionnaire |
Project ID | 972 |
Agency Name | TxDOT Beaumont District |
Project Title | FM 787 Trinity River Bridge |
Facility/Street/Highway | FM 787 |
Limits | At the Trinity River |
Description | Realign crossing of FM 787 at the Trinity River to address river migration threat. |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $27,000,000.00 |
Resiliency and State of Good Repair Questionnaire | View Questionnaire |
Project ID | 973 |
Agency Name | TxDOT Beaumont District |
Project Title | Dayton Relief Route |
Facility/Street/Highway | US 90 |
Limits | TBD |
Description | Construct relief route around Dayton |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $75,000,000.00 |
High Growth Area Needs Questionnaire | View Questionnaire |
Operational Improvements and Congestion Management Questionnaire | View Questionnaire |
Regional Goods Movement Questionnaire | View Questionnaire |
Resiliency and State of Good Repair Questionnaire | View Questionnaire |
Project ID | 974 |
Agency Name | TxDOT Houston District |
Project Title | 36A Planning Studies |
Facility/Street/Highway | 36A |
Limits | From South of Needville to IH 10 W |
Description | Preliminary engineering study in preparation for a possible DEIS (CONSTRUCT FOUR-LANE DIVIDED ON NEW LOCATION) |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $8,194,000.00 |
High Growth Area Needs Questionnaire | View Questionnaire |
Project ID | 975 |
Agency Name | TxDOT Houston District |
Project Title | 36A Planning Studies |
Facility/Street/Highway | 36A |
Limits | From IH 10 W to US 290 /SH 6 near Hempstead |
Description | Preliminary engineering study in preparation for a possible DEIS |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $7,500,000.00 |
High Growth Area Needs Questionnaire | View Questionnaire |
Project ID | 976 |
Agency Name | TxDOT Houston District |
Project Title | FM 1093 Pedestrian and Bike Improvements |
Facility/Street/Highway | FM 1093 |
Limits | From FM 1464 (S Barker Cypress Rd) to SH 6 |
Description | The project includes a 5- to 6- foot wide sidewalks NB and a 10ft shared use path SB, high visibility crossing striping, ADA ramps, pavement markings, median refuge and signage as well as other associated intersection improvements. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $4,500,000.00 |
Operational Improvements and Congestion Management Questionnaire | View Questionnaire |
Transit Questionnaire | View Questionnaire |
Project ID | 977 |
Agency Name | TxDOT Houston District |
Project Title | FM 1093 Widening |
Facility/Street/Highway | FM 1093 |
Limits | From FM 1489 to FM 359 in Fulshear |
Description | Reconstruct and widen existing roadway from 2 to 4 lanes divided. This configuration would match the section of FM 1093 in Fulshear. The space between the divided facilities would create an opportunity for future mainlanes (Westpark Tollway). |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $110,680,000.00 |
Major Projects Questionnaire | View Questionnaire |
Project ID | 978 |
Agency Name | TxDOT Houston District |
Project Title | FM 1097 Drainage Improvements |
Facility/Street/Highway | FM 1097 |
Limits | At Akins Creek |
Description | Construct drainage improvements including culvert replacements and limited channel work. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $2,800,000.00 |
Resiliency and State of Good Repair Questionnaire | View Questionnaire |
Project ID | 979 |
Agency Name | TxDOT Houston District |
Project Title | FM 1097 at IH 45 N Construct New Interchange |
Facility/Street/Highway | FM 1097 |
Limits | At IH 45 N |
Description | This project proposes interchange improvements based on the results of the feasibility study. |
Timeframe | Long Term (More than 10 Years) |
Estimated Cost | $25,000,000.00 |
Operational Improvements and Congestion Management Questionnaire | View Questionnaire |
Project ID | 980 |
Agency Name | TxDOT Houston District |
Project Title | FM 1128 Widening |
Facility/Street/Highway | FM 1128 |
Limits | From FM 518 to Bailey Ave |
Description | Widen from a 2-lane to a 4-lane divided roadway |
Timeframe | Long Term (More than 10 Years) |
Estimated Cost | $23,000,000.00 |
High Growth Area Needs Questionnaire | View Questionnaire |
Operational Improvements and Congestion Management Questionnaire | View Questionnaire |
Project ID | 981 |
Agency Name | TxDOT Houston District |
Project Title | FM 1314 Widening |
Facility/Street/Highway | FM 1314 |
Limits | From SH 105 to SH 242 |
Description | Widen from a 2-lane to a 4-lane divided roadway |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $140,600,000.00 |
Major Projects Questionnaire | View Questionnaire |
Project ID | 982 |
Agency Name | TxDOT Houston District |
Project Title | FM 1458 Bike Tourism Trail |
Facility/Street/Highway | FM 1458 |
Limits | From 359 to Park Rd 38 |
Description | The project includes a 8- to 10- foot shoulders, high visibility crossing striping, ADA ramps, pavement markings, resting area pads and signage as well as other associated intersection improvements. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $5,400,000.00 |
Transit Questionnaire | View Questionnaire |
Project ID | 983 |
Agency Name | TxDOT Houston District |
Project Title | FM 1458 Reconstruct/Realign and Widen |
Facility/Street/Highway | FM 1458 |
Limits | From FM 359 to Austin C/L |
Description | Widen from 2-lane to 4-lanes and implement access management treatments including turn lanes, intersection improvements, and realigning existing roadway curves to improve safety and mobility. |
Timeframe | Long Term (More than 10 Years) |
Estimated Cost | $70,000,000.00 |
High Growth Area Needs Questionnaire | View Questionnaire |
Operational Improvements and Congestion Management Questionnaire | View Questionnaire |
Project ID | 984 |
Agency Name | TxDOT Houston District |
Project Title | FM 1485 Widening |
Facility/Street/Highway | FM 1485 |
Limits | From SH 242 to Kidd Cemetery Road |
Description | Widen from 2-lane to 4-lanes and implement access management treatments including raised medians, realignment of curves, and bike/pedestrian accommodations. |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $103,600,000.00 |
Major Projects Questionnaire | View Questionnaire |
Project ID | 985 |
Agency Name | TxDOT Houston District |
Project Title | Magnolia Bypass (currently given an FM 1488 control number) |
Facility/Street/Highway | FM 1488 |
Limits | From Business FM 1488-P to SH 249 |
Description | Construct 4-Lane on New Location Roadway (Magnolia Bypass) |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $70,650,000.00 |
Major Projects Questionnaire | View Questionnaire |
Project ID | 986 |
Agency Name | TxDOT Houston District |
Project Title | FM 1488 Widening and Realignment |
Facility/Street/Highway | FM 1488 |
Limits | From BU 290 to FM 1098 |
Description | Widen from 2-lane to 4-lanes and implement access management treatments including a raised median, realignment of curve, and bike/ped facilities. |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $44,650,000.00 |
High Growth Area Needs Questionnaire | View Questionnaire |
Major Projects Questionnaire | View Questionnaire |
Project ID | 987 |
Agency Name | TxDOT Houston District |
Project Title | FM 1488 Widening/Other Improvements |
Facility/Street/Highway | FM 1488 |
Limits | From FM 1098 to Harris C/L |
Description | Widen from 2-lane to 4-lanes and implement access management treatments including a raised median, realignment of curve, and bike/ped facilities. |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $71,640,000.00 |
Major Projects Questionnaire | View Questionnaire |
Project ID | 988 |
Agency Name | TxDOT Houston District |
Project Title | FM 1488 Widening/Other Improvements |
Facility/Street/Highway | FM 1488 |
Limits | From Waller C/L West to Waller C/L East |
Description | Widen from 2-lane to 4-lanes and implement access management treatments including a raised median, realignment of curve, and bike/ped facilities. |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $8,950,000.00 |
Major Projects Questionnaire | View Questionnaire |
Project ID | 989 |
Agency Name | TxDOT Houston District |
Project Title | FM 1488 Widening/Other Improvements |
Facility/Street/Highway | FM 1488 |
Limits | From Harris C/L to Joseph Road |
Description | Widen from 2-lane to 4-lanes and implement access management treatments including a raised median, realignment of curve, and bike/ped facilities. |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $140,350,000.00 |
High Growth Area Needs Questionnaire | View Questionnaire |
Major Projects Questionnaire | View Questionnaire |
Project ID | 990 |
Agency Name | TxDOT Houston District |
Project Title | FM 1488 Widening and Access Management |
Facility/Street/Highway | FM 1488 |
Limits | From FM 2978 to IH 45 N |
Description | Widen from 4 to 6 Lanes |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $67,800,000.00 |
Major Projects Questionnaire | View Questionnaire |
Regional Goods Movement Questionnaire | View Questionnaire |
Project ID | 991 |
Agency Name | TxDOT Houston District |
Project Title | FM 1489 Widening |
Facility/Street/Highway | FM 1489 |
Limits | From south of IH 10 W to FM 359 |
Description | Widen the existing FM 1489 from 2 to 4 lanes and extend it north on new location to FM 359 (Durkin Road) and includes intersection improvements at FM 359. |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $20,000,000.00 |
High Growth Area Needs Questionnaire | View Questionnaire |
Operational Improvements and Congestion Management Questionnaire | View Questionnaire |
Project ID | 992 |
Agency Name | TxDOT Houston District |
Project Title | FM 1489 Widening |
Facility/Street/Highway | FM 1489 |
Limits | From SH 36 to IH 10 W |
Description | Reconstruct and widen from 2 to 4 lanes. |
Timeframe | Long Term (More than 10 Years) |
Estimated Cost | $225,000,000.00 |
Major Projects Questionnaire | View Questionnaire |
Project ID | 993 |
Agency Name | TxDOT Houston District |
Project Title | FM 1489 Widening |
Facility/Street/Highway | FM 1489 |
Limits | From SH 36 to FM 1093 |
Description | Reconstruct and widen from 2 to 4 lanes. |
Timeframe | Long Term (More than 10 Years) |
Estimated Cost | $75,000,000.00 |
Major Projects Questionnaire | View Questionnaire |
Project ID | 994 |
Agency Name | TxDOT Houston District |
Project Title | FM 149 |
Facility/Street/Highway | FM 149 |
Limits | From FM 1791 to Grimes County Line |
Description | Add 5 -foot shoulders, 1.5 inch mill and overlay. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $9,500,000.00 |
Operational Improvements and Congestion Management Questionnaire | View Questionnaire |
Resiliency and State of Good Repair Questionnaire | View Questionnaire |
Project ID | 995 |
Agency Name | TxDOT Houston District |
Project Title | FM 149 Extension to SH 249 on new location |
Facility/Street/Highway | FM 149 |
Limits | From SH 249 to E of Stillwater Blvd |
Description | Construct new location four-lane roadway with raised medians and bridge over BNSF RR / Jackson Road. |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $75,000,000.00 |
High Growth Area Needs Questionnaire | View Questionnaire |
Project ID | 996 |
Agency Name | TxDOT Houston District |
Project Title | FM 1495 Widening |
Facility/Street/Highway | FM 1495 |
Limits | From FM 523 to North of Brazos River Bridge |
Description | Widen from 2-lane to 4 -lane roadway |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $17,000,000.00 |
High Growth Area Needs Questionnaire | View Questionnaire |
Regional Goods Movement Questionnaire | View Questionnaire |
Project ID | 997 |
Agency Name | TxDOT Houston District |
Project Title | FM 1960 Access Management Improvements (Phase 1) |
Facility/Street/Highway | FM 1960 |
Limits | From IH 45 N to BF 1960 (East of Humble) |
Description | Phase 1 implementation of short-term recommendations (remainder of raised medians not constructed by 1685-02-056, sidewalks, ITS, etc.) |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $5,000,000.00 |
High Growth Area Needs Questionnaire | View Questionnaire |
Operational Improvements and Congestion Management Questionnaire | View Questionnaire |
Resiliency and State of Good Repair Questionnaire | View Questionnaire |
Project ID | 998 |
Agency Name | TxDOT Houston District |
Project Title | FM 1960 Access Management Improvements (Phase 2) |
Facility/Street/Highway | FM 1960 |
Limits | From IH 45 N to IH 69 N |
Description | Phase 2 implementation of short-term recommendations |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $5,000,000.00 |
Operational Improvements and Congestion Management Questionnaire | View Questionnaire |
Resiliency and State of Good Repair Questionnaire | View Questionnaire |
Project ID | 999 |
Agency Name | TxDOT Houston District |
Project Title | FM 1960 Grade Separation at Jones Rd Intersection |
Facility/Street/Highway | FM 1960 |
Limits | AT JONES RD |
Description | CONSTRUCT GRADE SEPARATION |
Timeframe | Long Term (More than 10 Years) |
Estimated Cost | $44,400,000.00 |
Project ID | 1000 |
Agency Name | TxDOT Houston District |
Project Title | FM 2004 Bridge Replacement |
Facility/Street/Highway | FM 2004 |
Limits | At Chocolate Bayou |
Description | Replace existing bridge and approaches (NBI No. 12-020-0-2523-02-011) - Demolish the existing bridge and roadway approaches and replace with a new, 2-lane bridge and new bridge approaches and bring the bridge and approaches up to current standards. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $75,000,000.00 |
Operational Improvements and Congestion Management Questionnaire | View Questionnaire |
Regional Goods Movement Questionnaire | View Questionnaire |
Resiliency and State of Good Repair Questionnaire | View Questionnaire |
Project ID | 1001 |
Agency Name | TxDOT Houston District |
Project Title | FM 2094 Pedestrian Improvements |
Facility/Street/Highway | FM 2094 |
Limits | Twin Oaks Blvd to Lawrence |
Description | Construct 5-foot wide Pedestrian Path and a 10-foot wide Shared Use Path with intersection improvements and pedestrian crossings between Twin Oaks Blvd and Lawrence Road |
Timeframe | Long Term (More than 10 Years) |
Estimated Cost | $10,000,000.00 |
Project ID | 1002 |
Agency Name | TxDOT Houston District |
Project Title | FM 2234 Intersection Improvements |
Facility/Street/Highway | FM 2234 |
Limits | From North of US 90A to South of US 90A |
Description | Construct intersection improvements. |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $30,900,000.00 |
Operational Improvements and Congestion Management Questionnaire | View Questionnaire |
Regional Goods Movement Questionnaire | View Questionnaire |
Project ID | 1003 |
Agency Name | TxDOT Houston District |
Project Title | FM 270 Widening |
Facility/Street/Highway | FM 270 |
Limits | From FM 518 to FM 646 |
Description | Reconstruct and widen from 2-lane to 4-lane roadway and implement access management treatments including raised median and bike/ped facilities. |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $40,800,000.00 |
High Growth Area Needs Questionnaire | View Questionnaire |
Operational Improvements and Congestion Management Questionnaire | View Questionnaire |
Regional Goods Movement Questionnaire | View Questionnaire |
Project ID | 1004 |
Agency Name | TxDOT Houston District |
Project Title | FM 2759 Reconstruction and Widen |
Facility/Street/Highway | FM 2759 |
Limits | From FM 762 to Thompson Road |
Description | Reconstruct and widen from 2 to 4 lane concrete curb and gutter road. |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $70,000,000.00 |
High Growth Area Needs Questionnaire | View Questionnaire |
Project ID | 1005 |
Agency Name | TxDOT Houston District |
Project Title | FM 2855 Extension to IH 10 W |
Facility/Street/Highway | FM 2855 |
Limits | From US 90 to IH 10 W |
Description | Reconstruct and Widen from 2 to 4 lanes and extend FM 2855 (currently known as Brookline Rd) to IH 10 W |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $35,000,000.00 |
High Growth Area Needs Questionnaire | View Questionnaire |
Regional Goods Movement Questionnaire | View Questionnaire |
Project ID | 1006 |
Agency Name | TxDOT Houston District |
Project Title | FM 2920 Widening |
Facility/Street/Highway | FM 2920 |
Limits | From BU 290-H to Becker Rd. |
Description | Reconstruct and widen from 2 to 4 lanes - The project proposes to address congestion along the roadway between Cypress-Rosehill and US 290 by reconstructing and widening the existing two-lane portion of FM 2920 between Becker Road and US 290. This roadway section will resemble the four-lane section that exists from Cypress-Rosehill eastward. The project will include sidewalks and cyclists can ride on the wide shoulders. |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $73,710,000.00 |
Major Projects Questionnaire | View Questionnaire |
Project ID | 1007 |
Agency Name | TxDOT Houston District |
Project Title | FM 2920 Widening |
Facility/Street/Highway | FM 2920 |
Limits | From Cypress-Rosehill Road to SH 249 |
Description | Widen from 4 to 6 lanes - The project proposes to address congestion along the roadway between Cypress-Rosehill and SH 249 by widening the existing four-lane portion of FM 2920 between Cypress Rosehill and SH 249. The project will include sidewalks and cyclists can ride on the wide shoulders. |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $116,000,000.00 |
Major Projects Questionnaire | View Questionnaire |
Project ID | 1008 |
Agency Name | TxDOT Houston District |
Project Title | FM 2920 Widening |
Facility/Street/Highway | FM 2920 |
Limits | From Becker Rd to Cypress-Rosehill Rd |
Description | Reconstruct and widen from 2 to 4 lanes - The project proposes to address congestion along the roadway between Cypress-Rosehill and US 290 by reconstructing and widening the existing two-lane portion of FM 2920 between Becker Road and Cypress Rosehill Road. The project will include sidewalks and cyclists can ride on the wide shoulders. |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $57,200,000.00 |
Major Projects Questionnaire | View Questionnaire |
Project ID | 1009 |
Agency Name | TxDOT Houston District |
Project Title | FM 2977 Widening |
Facility/Street/Highway | FM 2977 |
Limits | From FM 762 to FM 361 |
Description | Widen from 2-lane to 4-lane. This project proposes to add two new lanes, raised medians, and bicycle/pedestrian facilities. |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $86,900,000.00 |
Major Projects Questionnaire | View Questionnaire |
Project ID | 1010 |
Agency Name | TxDOT Houston District |
Project Title | FM 3083 Widening |
Facility/Street/Highway | FM 3083 |
Limits | From SH 105 W to IH 45 |
Description | Widen from 2-lane to a 4-lane divided roadway. |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $33,750,000.00 |
High Growth Area Needs Questionnaire | View Questionnaire |
Regional Goods Movement Questionnaire | View Questionnaire |
Project ID | 1011 |
Agency Name | TxDOT Houston District |
Project Title | FM 359 Bike Tourism Trail |
Facility/Street/Highway | FM 359 |
Limits | From 1458 to Gessner Rd |
Description | The project includes a 8- to 10- foot shoulders, high visibility crossing striping, ADA ramps, pavement markings, resting area pads and signage as well as other associated intersection improvements. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $5,400,000.00 |
Transit Questionnaire | View Questionnaire |
Project ID | 1012 |
Agency Name | TxDOT Houston District |
Project Title | FM 359 Widening |
Facility/Street/Highway | FM 359 |
Limits | From South IH 10 W to US 90 |
Description | Widen from 2 lanes to 4 lane urban divided roadway |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $7,750,000.00 |
Major Projects Questionnaire | View Questionnaire |
Regional Goods Movement Questionnaire | View Questionnaire |
Project ID | 1013 |
Agency Name | TxDOT Houston District |
Project Title | FM 359 Widening |
Facility/Street/Highway | FM 359 |
Limits | From FM 362 to FM 1458 |
Description | Reconstruct and widening from 2 to 4 lanes and intersection improvements. |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $35,000,000.00 |
High Growth Area Needs Questionnaire | View Questionnaire |
Project ID | 1014 |
Agency Name | TxDOT Houston District |
Project Title | FM 359 Widening |
Facility/Street/Highway | FM 359 |
Limits | From FM 1093 to Mason |
Description | Widen from 2 lanes to a 4 -lane urban divided roadway for approximately 9.5 miles. |
Timeframe | Long Term (More than 10 Years) |
Estimated Cost | $137,750,000.00 |
Major Projects Questionnaire | View Questionnaire |
Project ID | 1015 |
Agency Name | TxDOT Houston District |
Project Title | FM 359 Reconstruct/Realign and Widen |
Facility/Street/Highway | FM 359 |
Limits | From US 290 to FM 1458 |
Description | Reconstruct and widen from 2 to 4 lanes, realigning existing curves, turn lanes, and intersection improvements. |
Timeframe | Long Term (More than 10 Years) |
Estimated Cost | $230,000,000.00 |
Major Projects Questionnaire | View Questionnaire |
Project ID | 1016 |
Agency Name | TxDOT Houston District |
Project Title | FM 359 Widening |
Facility/Street/Highway | FM 359 |
Limits | From FM 1093 to IH 10 W |
Description | Reconstruct and widen from 2 to 4 lanes and intersection improvements. |
Timeframe | Long Term (More than 10 Years) |
Estimated Cost | $70,000,000.00 |
Major Projects Questionnaire | View Questionnaire |
Project ID | 1017 |
Agency Name | TxDOT Houston District |
Project Title | FM 362 Widening |
Facility/Street/Highway | FM 362 |
Limits | From FM 359 to FM 529 |
Description | Reconstruct and widen from 2 to 4 lanes and intersection improvements. |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $63,000,000.00 |
Major Projects Questionnaire | View Questionnaire |
Project ID | 1018 |
Agency Name | TxDOT Houston District |
Project Title | FM 362 Reconstruct/Realign and widening |
Facility/Street/Highway | FM 362 |
Limits | From FM 1736 to FM 529 |
Description | Reconstruct and widen from 2 to 4 lanes, realigning existing curves (including intersection at FM 1488 and FM 1736), turn lanes, and intersection improvements. |
Timeframe | Long Term (More than 10 Years) |
Estimated Cost | $200,000,000.00 |
Major Projects Questionnaire | View Questionnaire |
Project ID | 1019 |
Agency Name | TxDOT Houston District |
Project Title | FM 517 Widening |
Facility/Street/Highway | FM 517 |
Limits | From FM 3436 to SH 146 |
Description | WIDEN TO 4-LANE DIVIDED W/ CURB & GUTTER |
Timeframe | Long Term (More than 10 Years) |
Estimated Cost | $14,910,000.00 |
High Growth Area Needs Questionnaire | View Questionnaire |
Project ID | 1020 |
Agency Name | TxDOT Houston District |
Project Title | FM 518 Widening |
Facility/Street/Highway | FM 518 |
Limits | From FM 865 to SH 35 |
Description | Widen from 4-lanes to 6-lanes. A raised median will be included and may vary between 14 and 18 feet. Convert the existing open ditch drainage system to a curb and gutter drainage system. In addition, outside pedestrian sidewalks and bikeways are proposed. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $76,380,000.00 |
High Growth Area Needs Questionnaire | View Questionnaire |
Regional Goods Movement Questionnaire | View Questionnaire |
Project ID | 1021 |
Agency Name | TxDOT Houston District |
Project Title | FM 518 Bike/Ped Improvements, Landscaping/Streetscaping Improvements. |
Facility/Street/Highway | FM 518 (Main St) |
Limits | Magnolia to Iowa Ave |
Description | Landscaping and streetscaping enhancements along Main St including pedestrian improvements, off street parking locations, transferringoverhead utilities to underground, and a visible entrance way into the Downtown (sign to be located along FM 518 near Magnolia Aveintersection). |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $500,000.00 |
Operational Improvements and Congestion Management Questionnaire | View Questionnaire |
Project ID | 1022 |
Agency Name | TxDOT Houston District |
Project Title | FM 518 Reconstruction and Bike/Ped improvements |
Facility/Street/Highway | FM 518 (Main St) |
Limits | From Walker to Webster |
Description | Reconstruct roadway to include curb and gutter, multiple drainage improvements, and Bike/Ped improvements |
Timeframe | Long Term (More than 10 Years) |
Estimated Cost | $10,000,000.00 |
Operational Improvements and Congestion Management Questionnaire | View Questionnaire |
Project ID | 1023 |
Agency Name | TxDOT Houston District |
Project Title | FM 518 Intersection Improvements |
Facility/Street/Highway | FM 518 (Main St) |
Limits | AT SH 3 |
Description | INTERSECTION IMPROVEMENTS |
Timeframe | Long Term (More than 10 Years) |
Estimated Cost | $5,000,000.00 |
High Growth Area Needs Questionnaire | View Questionnaire |
Project ID | 1024 |
Agency Name | TxDOT Houston District |
Project Title | FM 521 |
Facility/Street/Highway | FM 521 |
Limits | SH 6 to Brazoria C/L (CR 56) |
Description | WIDEN FROM 2 LANES TO 4 LANES DIVIDED |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $70,000,000.00 |
Major Projects Questionnaire | View Questionnaire |
Project ID | 1025 |
Agency Name | TxDOT Houston District |
Project Title | FM 521 Sidewalks |
Facility/Street/Highway | FM 521 |
Limits | From West Airport Blvd. to South SL 8 |
Description | The project includes a 5- to 6- foot wide sidewalks, high visibility crossing striping, ADA ramps, pavement markings, bus stop pads, and signage as well as other associated intersection improvements. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $1,700,000.00 |
Transit Questionnaire | View Questionnaire |
Project ID | 1026 |
Agency Name | TxDOT Houston District |
Project Title | FM 521 Widening and Railroad grade separation |
Facility/Street/Highway | FM 521 |
Limits | From CR 56 to SH 6 |
Description | Widen from 4-lanes to 6-lanes divided. The FM 521 project extends from State Highway 6 to County Road 56 in Fort Bend County. The project includes a railroad grade separation. The area is rapidly developing with new subdivisions and a new high school adjacent to the road. |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $53,600,000.00 |
Major Projects Questionnaire | View Questionnaire |
Regional Goods Movement Questionnaire | View Questionnaire |
Project ID | 1027 |
Agency Name | TxDOT Houston District |
Project Title | FM 521 Widening and Bike/Ped improvements |
Facility/Street/Highway | FM 521 |
Limits | From FM 1462 to CR 56 |
Description | Widen from 2-lanes to 4-lanes. This project proposes to add two new lanes, raised medians, and bicycle/pedestrian facilities. |
Timeframe | Long Term (More than 10 Years) |
Estimated Cost | $81,480,000.00 |
Project ID | 1028 |
Agency Name | TxDOT Houston District |
Project Title | FM 528 Widening |
Facility/Street/Highway | FM 528 |
Limits | From BS 35 to SH 35 BYPASS |
Description | Widen from 2-lanes to 4-lanes. This project proposes to add two new lanes, raised medians, curb and gutter, and bicycle/pedestrian facilities. |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $8,450,000.00 |
Resiliency and State of Good Repair Questionnaire | View Questionnaire |
Project ID | 1029 |
Agency Name | TxDOT Houston District |
Project Title | FM 528 New Roadway |
Facility/Street/Highway | FM 528 |
Limits | From BS 35 (N Gordon St) to SH 6 |
Description | Construct new location (On existing portions of Midtown Pkwy and Brazos St), 2-lane roadway with railroad grade separation. |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $21,200,000.00 |
High Growth Area Needs Questionnaire | View Questionnaire |
Project ID | 1030 |
Agency Name | TxDOT Houston District |
Project Title | FM 529 Widening |
Facility/Street/Highway | FM 529 |
Limits | From Waller County Line to Katy Hockley Cutoff |
Description | Widen from 2-lanes to 4-lanes. This rural section will include widening FM 529 to a four-lane roadway, with a raised median between Katy Hockley Cut Off Road and the Waller County Line. The roadway will include an 18-foot median with openings, 12-foot outside shoulders, and 10-foot wide shared use path on each side of the roadway. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $50,000,000.00 |
Major Projects Questionnaire | View Questionnaire |
Regional Goods Movement Questionnaire | View Questionnaire |
Project ID | 1031 |
Agency Name | TxDOT Houston District |
Project Title | FM 529 Widening |
Facility/Street/Highway | FM 529 |
Limits | From Katy Hockley Cutoff to SH 99 |
Description | Widen from 2-lanes to 6-lanes divided. The proposed improvements will include an urban roadway section with 6-travel lanes, 3 in each direction, with curb and gutter. The roadway would include an 18-foot median with openings and 10-foot shared-use paths for cyclists and pedestrians. The proposed new right-of-way width would be 150 feet, which is 30 feet wider than the existing right-of-way. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $53,000,000.00 |
Major Projects Questionnaire | View Questionnaire |
Regional Goods Movement Questionnaire | View Questionnaire |
Project ID | 1032 |
Agency Name | TxDOT Houston District |
Project Title | FM 529 Widening |
Facility/Street/Highway | FM 529 |
Limits | From FM 362 to Harris County Line |
Description | Widen from 2-lanes to 4-lanes. This rural section will include widening FM 529 to a four-lane roadway, with a raised median between Katy Hockley Cut Off Road and the Waller County Line. The roadway will include an 18-foot median with openings, 12-foot outside shoulders, and 10-foot wide shared use paths on each of side of the roadway. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $78,100,000.00 |
Major Projects Questionnaire | View Questionnaire |
Regional Goods Movement Questionnaire | View Questionnaire |
Project ID | 1033 |
Agency Name | TxDOT Houston District |
Project Title | FM 529 Reconstruct/Realign on new location |
Facility/Street/Highway | FM 529 |
Limits | From FM 362 to FM 359 |
Description | Remove/Realign the dog-leg on FM 529 along FM 362 and move FM 529 to new location including intersection improvements at FM 362. |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $45,000,000.00 |
Major Projects Questionnaire | View Questionnaire |
Project ID | 1034 |
Agency Name | TxDOT Houston District |
Project Title | FM 529 Widening |
Facility/Street/Highway | FM 529 |
Limits | From FM 359 to Austin C/L |
Description | Reconstruct and widen from 2 to 4 lanes and intersection improvements. |
Timeframe | Long Term (More than 10 Years) |
Estimated Cost | $70,000,000.00 |
Major Projects Questionnaire | View Questionnaire |
Project ID | 1035 |
Agency Name | TxDOT Houston District |
Project Title | FM 723 Widening |
Facility/Street/Highway | FM 723 |
Limits | From Avenue D to US 90A/ Avenue H |
Description | Widen from 2-lanes to 4-lanes. |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $8,400,000.00 |
High Growth Area Needs Questionnaire | View Questionnaire |
Project ID | 1036 |
Agency Name | TxDOT Houston District |
Project Title | FM 762 Extension |
Facility/Street/Highway | FM 762 (10th St) |
Limits | From Clay Street to McCrary/Peek |
Description | Extend FM 762 on new location (and on 10th Street) north over the Brazos River to connect with McCrary Road. |
Timeframe | Long Term (More than 10 Years) |
Estimated Cost | $120,000,000.00 |
Major Projects Questionnaire | View Questionnaire |
Project ID | 1037 |
Agency Name | TxDOT Houston District |
Project Title | FM 830 Widening |
Facility/Street/Highway | FM 830 |
Limits | From Old Montgomery Road to SH 75 |
Description | Widen roadway from 2 to 4 lanes. |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $34,100,000.00 |
High Growth Area Needs Questionnaire | View Questionnaire |
Operational Improvements and Congestion Management Questionnaire | View Questionnaire |
Project ID | 1038 |
Agency Name | TxDOT Houston District |
Project Title | Hempstead Road |
Facility/Street/Highway | Hempstead Road |
Limits | From Mangum Road to 43rd/Clay Road |
Description | Reconstruct Hempstead Road and add one transit lane in each direction at grade and construct 4 elevated managed lanes |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $314,563,107.00 |
Major Projects Questionnaire | View Questionnaire |
Project ID | 1039 |
Agency Name | TxDOT Houston District |
Project Title | Hempstead Road |
Facility/Street/Highway | Hempstead Road |
Limits | From 43rd/Clay Road to Gessner Road |
Description | Reconstruct Hempstead Road and add one transit lane in each direction at grade and construct 4 elevated managed lanes |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $262,135,922.00 |
Major Projects Questionnaire | View Questionnaire |
Project ID | 1040 |
Agency Name | TxDOT Houston District |
Project Title | Hempstead Road |
Facility/Street/Highway | Hempstead Road |
Limits | From west of Huffmeister Road to Jones Road |
Description | Construct 4 managed lanes (non-toll) |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $91,000,000.00 |
Major Projects Questionnaire | View Questionnaire |
Project ID | 1041 |
Agency Name | TxDOT Houston District |
Project Title | Hempstead Road |
Facility/Street/Highway | Hempstead Road |
Limits | From Gessner Road to Jones Road |
Description | Reconstruct Hempstead Road and add one transit lane in each direction at grade and construct 4 elevated managed lanes |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $270,873,786.00 |
Major Projects Questionnaire | View Questionnaire |
Project ID | 1042 |
Agency Name | TxDOT Houston District |
Project Title | Hempstead Road |
Facility/Street/Highway | Hempstead Road |
Limits | From SH 99 to west of Huffmeister Road |
Description | Construct 4 managed lanes (non-toll) |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $260,000,000.00 |
Major Projects Questionnaire | View Questionnaire |
Project ID | 1043 |
Agency Name | TxDOT Houston District |
Project Title | Hempstead Road |
Facility/Street/Highway | Hempstead Road |
Limits | From IH 610 to Mangum Road |
Description | Reconstruct Hempstead Road and add one transit lane in each direction at grade and construct 4 elevated managed lanes |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $52,427,185.00 |
Major Projects Questionnaire | View Questionnaire |
Project ID | 1044 |
Agency Name | TxDOT Houston District |
Project Title | Hempstead Road |
Facility/Street/Highway | Hempstead Road |
Limits | From 43rd St/Clay Rd to W of SL 8 |
Description | RECONSTRUCT AS DIVIDED 4 LANE ROADWAY (FUTURE HEMPSTEAD HIGHWAY FRONTAGE ROADS) |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $275,000,000.00 |
Major Projects Questionnaire | View Questionnaire |
Project ID | 1045 |
Agency Name | TxDOT Houston District |
Project Title | Hempstead Road |
Facility/Street/Highway | Hempstead Road |
Limits | From IH 610 W to Mangum Road |
Description | RECONSTRUCT AS DIVIDED 4 LANE ROADWAY (FUTURE HEMPSTEAD HIGHWAY FRONTAGE ROADS) |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $120,000,000.00 |
Major Projects Questionnaire | View Questionnaire |
Project ID | 1046 |
Agency Name | TxDOT Houston District |
Project Title | Hempstead Road |
Facility/Street/Highway | Hempstead Road |
Limits | From Mangum Road to 43rd St/ Clay Rd |
Description | RECONSTRUCT AS DIVIDED 4 LANE ROADWAY (FUTURE HEMPSTEAD HIGHWAY FRONTAGE ROADS) |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $215,000,000.00 |
Major Projects Questionnaire | View Questionnaire |
Project ID | 1047 |
Agency Name | TxDOT Houston District |
Project Title | Hempstead Road DCs at IH 610 W |
Facility/Street/Highway | Hempstead Road |
Limits | From W of Mangum/18th St to S of Old Katy Rd on IH 610 W |
Description | CONSTRUCT INTERCHANGE WITH MANAGED LANES AND 2 DIRECT CONNECTORS (EB - SB, WB - NB) |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $352,140,000.00 |
Major Projects Questionnaire | View Questionnaire |
Project ID | 1048 |
Agency Name | TxDOT Houston District |
Project Title | IH 10 Resiliency |
Facility/Street/Highway | IH 10 |
Limits | From Studemont Street to Houston Avenue |
Description | Reconstruct the existing IH-10 W mainlanes and HOV lanes to raise the roadway out of the White Oak Bayou floodway and Construct a new shared use path along White Oak Bayou. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $347,000,000.00 |
Regional Goods Movement Questionnaire | View Questionnaire |
Project ID | 1049 |
Agency Name | TxDOT Houston District |
Project Title | IH 10 Inner Katy Drainage Improvements (Polo Fields) |
Facility/Street/Highway | IH 10 |
Limits | From IH 10 south through Memorial Park (Adjacent to Polo Fields) |
Description | Construct detention pond upgrades, construct outfall channel adjacent to polo fields and provide pump station upgrades. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $4,200,000.00 |
Resiliency and State of Good Repair Questionnaire | View Questionnaire |
Project ID | 1050 |
Agency Name | TxDOT Houston District |
Project Title | IH 10 Inner Katy Reconstruction and Managed Lanes |
Facility/Street/Highway | IH 10 |
Limits | From IH 610 W to Washington Ave |
Description | INNER KATY SEG 3: Reconstruct 10 mainlanes and two 3-lane frontage roads. Construct 4 new non-tolled managed lanes and drainage improvements |
Timeframe | Long Term (More than 10 Years) |
Estimated Cost | $275,000,000.00 |
Major Projects Questionnaire | View Questionnaire |
Regional Goods Movement Questionnaire | View Questionnaire |
Project ID | 1051 |
Agency Name | TxDOT Houston District |
Project Title | IH 10 Inner Katy Reconstruction and Managed Lanes |
Facility/Street/Highway | IH 10 |
Limits | From Washington Ave to E of Patterson St |
Description | INNER KATY SEG 2: Reconstruct 10 mainlanes and two 3-lane frontage roads. Construct 4 new non-tolled managed lanes and drainage improvements |
Timeframe | Long Term (More than 10 Years) |
Estimated Cost | $465,000,000.00 |
Major Projects Questionnaire | View Questionnaire |
Regional Goods Movement Questionnaire | View Questionnaire |
Project ID | 1052 |
Agency Name | TxDOT Houston District |
Project Title | IH 10 Inner Katy Reconstruction and Managed Lanes |
Facility/Street/Highway | IH 10 |
Limits | From E of Patterson St to E of Studemont |
Description | INNER KATY SEG 1: Reconstruct 10 mainlanes and two 3-lane frontage roads. Construct 4 new non-tolled managed lanes and drainage improvements |
Timeframe | Long Term (More than 10 Years) |
Estimated Cost | $275,000,000.00 |
Major Projects Questionnaire | View Questionnaire |
Regional Goods Movement Questionnaire | View Questionnaire |
Project ID | 1053 |
Agency Name | TxDOT Houston District |
Project Title | IH 10 E SAN JACINTO RIVER BRIDGE AND SS 330 INTERCHANGE RECONSTRUCTION |
Facility/Street/Highway | IH 10 E |
Limits | W OF MAGNOLIA ST TO W OF THOMPSON RD/SS 330 INTERCHANGE |
Description | RECONSTRUCT SAN JACINTO RIVER BRIDGE AND WIDEN FROM 6 TO 11 MAIN LANES AND CONSTRUCT 4 NON-TOLLED MANAGED LANES AND SS 330 INTERCHANGE RECONSTRUCTION |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $555,000,000.00 |
Major Projects Questionnaire | View Questionnaire |
Regional Goods Movement Questionnaire | View Questionnaire |
Project ID | 1054 |
Agency Name | TxDOT Houston District |
Project Title | IH 10 E Widening/Operational Improvements |
Facility/Street/Highway | IH 10 E |
Limits | From IH 69 to SL 8 |
Description | RECONSTRUCT AND WIDEN FROM 8 TO 12 LANE (ADD 4 MANAGED LANES) - Safety, operational and mobility improvements to IH 10 mainlanes and frontage roads, based on results of the IH 10 East PEL study |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $362,000,000.00 |
Major Projects Questionnaire | View Questionnaire |
Regional Goods Movement Questionnaire | View Questionnaire |
Project ID | 1055 |
Agency Name | TxDOT Houston District |
Project Title | IH 10 E Widening/Operational Improvements |
Facility/Street/Highway | IH 10 E |
Limits | From SL 8 to SS 330 |
Description | RECONSTRUCT AND WIDEN FROM 8 TO 12 LANE (ADD 4 MANAGED LANES) - Safety, operational and mobility improvements to IH 10 mainlanes and frontage roads, based on results of the IH 10 East PEL study |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $313,000,000.00 |
Major Projects Questionnaire | View Questionnaire |
Regional Goods Movement Questionnaire | View Questionnaire |
Project ID | 1056 |
Agency Name | TxDOT Houston District |
Project Title | IH 10 E Widening |
Facility/Street/Highway | IH 10 E |
Limits | From SPUR 330 to CHAMBERS C/L |
Description | RECONSTRUCT AND WIDEN FROM 8 TO 12 LANE (ADD 4 MANAGED LANES) - Safety, operational and mobility improvements to IH 10 E mainlanes and frontage roads, based on results of the IH 10 East PEL study |
Timeframe | Long Term (More than 10 Years) |
Estimated Cost | $200,000,000.00 |
Major Projects Questionnaire | View Questionnaire |
Regional Goods Movement Questionnaire | View Questionnaire |
Project ID | 1057 |
Agency Name | TxDOT Beaumont District |
Project Title | IH 10 E Widening |
Facility/Street/Highway | IH 10 E |
Limits | HARRIS C/L TO SH 99 |
Description | RECONSTRUCT AND WIDEN FROM 8 TO 12 LANE (ADD 4 MANAGED LANES) - Safety, operational and mobility improvements to IH 10 E mainlanes and frontage roads, based on results of the IH 10 East PEL study |
Timeframe | Long Term (More than 10 Years) |
Estimated Cost | $200,000,000.00 |
Major Projects Questionnaire | View Questionnaire |
Regional Goods Movement Questionnaire | View Questionnaire |
Project ID | 1058 |
Agency Name | TxDOT Houston District |
Project Title | IH 10 W Frontage Roads |
Facility/Street/Highway | IH 10 W |
Limits | From FM 359 to Fort Bend County Line |
Description | CONSTRUCT 2 TWO LANE FRONTAGE ROADS ON NEW LOCATION (EASTBOUND AND WESTBOUND). This project fills in the gap of the frontage road system in Fort Bend County on IH 10. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $50,750,000.00 |
Regional Goods Movement Questionnaire | View Questionnaire |
Project ID | 1059 |
Agency Name | TxDOT Houston District |
Project Title | IH 10 W Frontage Roads |
Facility/Street/Highway | IH 10 W |
Limits | From Waller County Line to Cane Island Parkway |
Description | CONSTRUCT 2 TWO LANE FRONTAGE ROADS ON NEW LOCATION (EASTBOUND AND WESTBOUND). This project fills in the gap of the frontage road system in Fort Bend County on IH 10. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $3,700,000.00 |
Regional Goods Movement Questionnaire | View Questionnaire |
Project ID | 1060 |
Agency Name | TxDOT Houston District |
Project Title | IH 10 W Frontage Road Pedestrian Improvements |
Facility/Street/Highway | IH 10 W |
Limits | At Snake Creek north of Willow Fork |
Description | Construct a pedestrian/bicycle underpass for newly constructed frontage roads |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $1,000,000.00 |
Project ID | 1061 |
Agency Name | TxDOT Houston District |
Project Title | IH 10 W Frontage Road Pedestrian Improvements |
Facility/Street/Highway | IH 10 W |
Limits | At Cane Island Branch |
Description | Construct a pedestrian/bicycle underpass for newly constructed frontage roads |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $1,000,000.00 |
Project ID | 1062 |
Agency Name | TxDOT Houston District |
Project Title | IH 10 W Frontage Road Pedestrian Improvements |
Facility/Street/Highway | IH 10 W |
Limits | At Pederson Road |
Description | Construct 10-foot wide sidewalk and bridge structure from the existing north frontage to the existing south frontage road |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $2,000,000.00 |
Project ID | 1063 |
Agency Name | TxDOT Houston District |
Project Title | IH 10 W Frontage Road Pedestrian Improvements |
Facility/Street/Highway | IH 10 W |
Limits | From Cane Island Branch to Danover Road |
Description | Construct 10-foot sidewalks along north and south frontage roads |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $2,500,000.00 |
Project ID | 1064 |
Agency Name | TxDOT Houston District |
Project Title | IH 10 W Sidepath |
Facility/Street/Highway | IH 10 W |
Limits | From Mason Road to Mason Creek |
Description | The project includes a 10-foot wide sidepath, high visibility crossing striping, ADA ramps, pavement markings, and signage as well as other associated intersection improvements. The project also includes a underpass at IH 10 W. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $1,300,000.00 |
Project ID | 1065 |
Agency Name | TxDOT Houston District |
Project Title | IH 10 W (Inner Katy) Reconstruction and Managed Lanes |
Facility/Street/Highway | IH 10 W |
Limits | From Voss Rd to IH 610 W |
Description | INNER KATY SEG 4: Reconstruct 10 mainlanes and two 3-lane frontage roads. Construct 4 new non-tolled managed lanes and drainage improvements |
Timeframe | Long Term (More than 10 Years) |
Estimated Cost | $25,000,000.00 |
Major Projects Questionnaire | View Questionnaire |
Regional Goods Movement Questionnaire | View Questionnaire |
Project ID | 1066 |
Agency Name | TxDOT Houston District |
Project Title | IH 45 NHHIP, Segment 3A |
Facility/Street/Highway | IH 45 |
Limits | from SH 288 to SP 527 |
Description | RECONSTRUCT AND WIDEN FROM 6 TO 10 MAIN LANES (NHHIP SEG 3A) |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $639,360,000.00 |
Project ID | 1067 |
Agency Name | TxDOT Houston District |
Project Title | IH 45 N HOV Extension |
Facility/Street/Highway | IH 45 |
Limits | From North of FM 1488 to SL 336 |
Description | Restripe existing northbound wide shoulder to extend HOV Lane beyond its current end point north of FM 1488. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $251,973.00 |
Project ID | 1068 |
Agency Name | TxDOT Houston District |
Project Title | IH 45 NHHIP, Segment 3D |
Facility/Street/Highway | IH 45 |
Limits | from IH 69 to IH 10 |
Description | CONSTRUCT PARKWAY CONNECTORS INTO DOWNTOWN HOUSTON AND REMOVE EXISTING PIERCE ELEVATED (NHHIP SEG 3D) |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $241,462,070.00 |
Project ID | 1069 |
Agency Name | TxDOT Houston District |
Project Title | IH 45 NHHIP, Segment 3C-1 |
Facility/Street/Highway | IH 45 |
Limits | at IH 10 |
Description | RECONSTRUCT IH45/IH10 INTERCHANGE. IH10 REALIGN/WIDEN FROM 6 TO 8 MAINLANES (ML) FROM WEST OF HOUSTON STREET TO WEST OF MAIN STREET; CONSTRUCT 4 IH10 EXPRESS LANES FROM WEST OF HOUSTON STREET TO WEST OF MAIN STREET; IH45 REALIGN FROM 6 TO 6 ML INCLUDING 3 LANES NB AND 3 LANES SB (3 ML AND 1 AUX LANE) FROM QUITMAN STREET TO WEST OF MAIN STREET; IH-45 WIDENING FROM 1 TO 4 MANAGED LANES FROM QUITMAN STREET TO MILAM/TRAVIS STREETS (NHHIP SEG 3C-1) |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $1,078,560,000.00 |
Project ID | 1070 |
Agency Name | TxDOT Houston District |
Project Title | IH 45 NHHIP, Segment 3D |
Facility/Street/Highway | IH 45 |
Limits | at IH 69 S |
Description | RECONSTRUCT IH45/IH69 INTERCHANGE. IH45 REALIGN/WIDEN FROM 6 TO 7 MAINLANES (ML) INCLUDING 3 ML NB AND 4 ML SB FROM SAUER ST. TO RUNNELS ST.; IH69 RECONSTRUCT FROM 8 TO 8 ML FROM W. OF PIERCE ST. TO S. OF RUNNEL ST. W/ 2, 3-LANE CONTINUOUS FRONTAGE ROADS. (NHHIP SEG 3D) |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $1,336,721,392.00 |
Project ID | 1071 |
Agency Name | TxDOT Houston District |
Project Title | IH 45 Resiliency |
Facility/Street/Highway | IH 45 |
Limits | At Cullen Blvd. |
Description | Rehabilitate pump station and construct new detention pond |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $1,891,235.00 |
Project ID | 1072 |
Agency Name | TxDOT Houston District |
Project Title | IH 45 NHHIP, Segment 3C-2 |
Facility/Street/Highway | IH 45 |
Limits | at IH 69/IH 10 |
Description | RECONSTRUCT IH45/IH10/IH69 INTERCHANGES. IH10 REALIGN/RECONSTRUCT 8 MAINLANES (ML) FROM W. OF MAIN ST. TO WACO ST.; CONSTRUCT 4 IH10 EXPRESS LANES FROM W. OF MAIN ST. TO W. OF WACO ST.; REALIGN/WIDEN IH45 FROM 6 TO 7 ML INCLUDING 3 LANES EB AND 4 LANES WB FROM S. OF RUNNELS ST. TO W. OF MAIN ST.; RECONSTRUCT IH-69 FROM 8 TO 8 ML FROM S. OF RUNNELS ST. TO N. OF LYONS AVE. (NHHIP SEG 3C-2) |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $1,216,320,000.00 |
Project ID | 1073 |
Agency Name | TxDOT Houston District |
Project Title | IH 45 NHHIP, Segment 1D |
Facility/Street/Highway | IH 45 |
Limits | From South of West Rd to SL 8 |
Description | RECONSTRUCT 8 MAIN LANES, RECONSTRUCT AND WIDEN FROM 1 TO 4 MANAGED LANES TRANSITIONING INTO TWO ENTERING AND EXITING LANES AT REVERSIBLE HOV LANE NORTH OF SL8, AND RECONSTRUCT AND WIDEN FROM TWO 2 AND 3-LANES FRONTAGE ROADS TO TWO 2- AND 3- LANES FRONTAGE ROADS (NHHIP SEG 1D) |
Timeframe | Long Term (More than 10 Years) |
Estimated Cost | $325,700,000.00 |
Major Projects Questionnaire | View Questionnaire |
Regional Goods Movement Questionnaire | View Questionnaire |
Project ID | 1074 |
Agency Name | TxDOT Houston District |
Project Title | IH 45 NHHIP, Segment 1C |
Facility/Street/Highway | IH 45 |
Limits | From South of Shepherd Drive to South of West Road |
Description | RECONSTRUCT/WIDEN FROM 8 TO 10 MAINLANES, RECONSTRUCT/WIDEN FROM 1 TO 4 MANAGED LANES; RECONSTRUCT/WIDEN FROM TWO, 2- AND 3-LANE FRONTAGE ROADS TO TWO, 2- AND 3-LANE FRONTAGE ROADS. (NHHIP SEG 1C) |
Timeframe | Long Term (More than 10 Years) |
Estimated Cost | $480,500,000.00 |
Major Projects Questionnaire | View Questionnaire |
Regional Goods Movement Questionnaire | View Questionnaire |
Project ID | 1075 |
Agency Name | TxDOT Houston District |
Project Title | IH 45 N Improvements based on IH 45 N PEL Study |
Facility/Street/Highway | IH 45 N |
Limits | From SL 8 to SH 99 |
Description | RECONSTRUCT AND WIDEN FROM 8 TO 12 LANE (ADD 4 MANAGED LANES) - Safety, operational and mobility improvements to IH 45 N mainlanes and frontage roads, based on results of the IH 45 North Freeway PEL study |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $200,000,000.00 |
Major Projects Questionnaire | View Questionnaire |
Project ID | 1076 |
Agency Name | TxDOT Houston District |
Project Title | IH 45 N Improvements based on IH 45 N PEL Study |
Facility/Street/Highway | IH 45 N |
Limits | From SH 99 to SH 242 |
Description | RECONSTRUCT AND WIDEN FROM 8 TO 12 LANE (ADD 4 MANAGED LANES) - Safety, operational and mobility improvements to IH 45 N mainlanes and frontage roads, based on results of the IH 45 North Freeway PEL study |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $200,000,000.00 |
Major Projects Questionnaire | View Questionnaire |
Project ID | 1077 |
Agency Name | TxDOT Houston District |
Project Title | IH 45 N Improvements based on IH 45 N PEL Study |
Facility/Street/Highway | IH 45 N |
Limits | From SH 242 to LP 336 |
Description | RECONSTRUCT AND WIDEN FROM 8 TO 12 LANE (ADD 4 MANAGED LANES) - Safety, operational and mobility improvements to IH 45 N mainlanes and frontage roads, based on results of the IH 45 North Freeway PEL study |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $70,000,000.00 |
Major Projects Questionnaire | View Questionnaire |
Project ID | 1078 |
Agency Name | TxDOT Houston District |
Project Title | IH 45 NHHIP, Segment 1B |
Facility/Street/Highway | IH 45 N |
Limits | From Airline Dr to South of Shepherd Dr |
Description | RECONSTRUCT MAIN LNS, CONSTRUCT 4 MANAGED LNS, AND RECONSTRUCT AND WIDEN FROM TWO 2-LN FRONTAGE RDS TO TWO 3-LN FRONTAGE RDS (NHHIP SEG 1B) |
Timeframe | Long Term (More than 10 Years) |
Estimated Cost | $393,500,000.00 |
Major Projects Questionnaire | View Questionnaire |
Regional Goods Movement Questionnaire | View Questionnaire |
Project ID | 1079 |
Agency Name | TxDOT Houston District |
Project Title | IH 45 NHHIP, Segment 2 |
Facility/Street/Highway | IH 45 N |
Limits | From IH 10 to IH 610 |
Description | RECONSTRUCT AND WIDEN FROM 4 TO 5 MAIN LANES, CONSTRUCT 4 MANAGED LANES AND RECONSTRUCT AND WIDEN FROM TWO 2- AND 3-LN FRS TO TWO 3-LN FRS (NHHIP SEG 2) |
Timeframe | Long Term (More than 10 Years) |
Estimated Cost | $489,135,576.00 |
Project ID | 1080 |
Agency Name | TxDOT Houston District |
Project Title | IH 45 NHHIP, Segment 1A |
Facility/Street/Highway | IH 45 N |
Limits | From IH 610 to Airline Drive |
Description | RECONSTRUCT AND WIDEN FROM 8 TO 12 MAIN LANES, RECONSTRUCT AND WIDEN FROM 1 TO 4 MANAGED LANES AND RECONSTRUCT AND WIDEN FROM TWO 2- AND 3-LANES FRONTAGE ROADS TO TWO 2- AND 3-LANES FRONTAGE ROADS (NHHIP SEG 1A) |
Timeframe | Long Term (More than 10 Years) |
Estimated Cost | $675,400,000.00 |
Major Projects Questionnaire | View Questionnaire |
Regional Goods Movement Questionnaire | View Questionnaire |
Project ID | 1081 |
Agency Name | TxDOT Houston District |
Project Title | IH 45 NHHIP, Segment 2 |
Facility/Street/Highway | IH 45 N |
Limits | At IH 610 N |
Description | RECONSTRUCT INTERCHANGE (NHHIP SEG 2) |
Timeframe | Long Term (More than 10 Years) |
Estimated Cost | $670,472,971.00 |
Project ID | 1082 |
Agency Name | TxDOT Houston District |
Project Title | IH 45 S Improvements based on IH 45 S PEL Study |
Facility/Street/Highway | IH 45 S |
Limits | From IH 69 to SPUR 5 |
Description | RECONSTRUCT AND WIDEN FROM 8 TO 12 LANE (ADD 4 MANAGED LANES) - Safety, operational, and mobility improvements to IH 45 S mainlanes and frontage roads, based on results of the IH 45 South Gulf Freeway PEL study |
Timeframe | Long Term (More than 10 Years) |
Estimated Cost | $200,000,000.00 |
Major Projects Questionnaire | View Questionnaire |
Project ID | 1083 |
Agency Name | TxDOT Houston District |
Project Title | IH 45 S Improvements based on IH 45 S PEL Study |
Facility/Street/Highway | IH 45 S |
Limits | From SPUR 5 to IH 610 S |
Description | RECONSTRUCT AND WIDEN FROM 8 TO 12 LANE (ADD 4 MANAGED LANES) - Safety, operational, and mobility improvements to IH 45 S mainlanes and frontage roads, based on results of the IH 45 South Gulf Freeway PEL study |
Timeframe | Long Term (More than 10 Years) |
Estimated Cost | $200,000,000.00 |
Major Projects Questionnaire | View Questionnaire |
Project ID | 1084 |
Agency Name | TxDOT Houston District |
Project Title | IH 45 S Improvements based on IH 45 S PEL Study |
Facility/Street/Highway | IH 45 S |
Limits | From IH 610 S to SL 8 |
Description | RECONSTRUCT AND WIDEN FROM 8 TO 12 LANE (ADD 4 MANAGED LANES) - Safety, operational, and mobility improvements to IH 45 S mainlanes and frontage roads, based on results of the IH 45 South Gulf Freeway PEL study |
Timeframe | Long Term (More than 10 Years) |
Estimated Cost | $200,000,000.00 |
Major Projects Questionnaire | View Questionnaire |
Project ID | 1085 |
Agency Name | TxDOT Houston District |
Project Title | IH 610 E Ship Channel Bridge |
Facility/Street/Highway | IH 610 E |
Limits | From N of Mississippi St to S of SH 225 |
Description | RECONSTRUCT AND WIDEN FROM 8 TO 14 LANE (ADD 2 GENERAL PURPOSE LANES AND 4 MANAGED LANES) AND RAISE SHIP CHANNEL BRIDGE |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $2,400,000,000.00 |
Major Projects Questionnaire | View Questionnaire |
Regional Goods Movement Questionnaire | View Questionnaire |
Project ID | 1086 |
Agency Name | TxDOT Houston District |
Project Title | IH 610 E Reconstruction and Widening to add Managed lanes |
Facility/Street/Highway | IH 610 E |
Limits | From IH 10 E to SH 225 |
Description | RECONSTRUCT AND WIDEN FROM 8 TO 12 LANE (ADD 4 MANAGED LANES) - Safety, operational and mobility improvements to the IH 610 E mainlanes and frontage roads, based on results of the SH 225 PEL/IH 610 East PEL study |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $150,000,000.00 |
Major Projects Questionnaire | View Questionnaire |
Regional Goods Movement Questionnaire | View Questionnaire |
Project ID | 1087 |
Agency Name | TxDOT Houston District |
Project Title | IH 610 E Reconstruction and Widening to add Managed lanes |
Facility/Street/Highway | IH 610 E |
Limits | From SH 225 to IH 45 S |
Description | RECONSTRUCT AND WIDEN FROM 8 TO 12 LANE (ADD 4 MANAGED LANES) - Safety, operational and mobility improvements to the IH 610 E mainlanes and frontage roads, based on results of the SH 225 PEL/IH 610 East PEL study |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $50,000,000.00 |
Major Projects Questionnaire | View Questionnaire |
Regional Goods Movement Questionnaire | View Questionnaire |
Project ID | 1088 |
Agency Name | TxDOT Houston District |
Project Title | IH 610 N Reconstruction |
Facility/Street/Highway | IH 610 N |
Limits | From US 290 to IH 45 N |
Description | Safety, operational and mobility improvements to IH 610 N mainlanes and frontage roads, based on results of IH 610 North Feasibility Study |
Timeframe | Long Term (More than 10 Years) |
Estimated Cost | $250,000,000.00 |
Major Projects Questionnaire | View Questionnaire |
Project ID | 1089 |
Agency Name | TxDOT Houston District |
Project Title | IH 610 N Reconstruction |
Facility/Street/Highway | IH 610 N |
Limits | From IH 45 N to IH 69 N |
Description | Safety, operational and mobility improvements to IH 610 N mainlanes and frontage roads, based on results of IH 610 North Feasibility Study |
Timeframe | Long Term (More than 10 Years) |
Estimated Cost | $100,000,000.00 |
Major Projects Questionnaire | View Questionnaire |
Project ID | 1090 |
Agency Name | TxDOT Houston District |
Project Title | IH 610 S Reconstruction and Widening |
Facility/Street/Highway | IH 610 S |
Limits | From IH 45 S to SH 35 (SS 5/Mykawa) |
Description | RECONSTRUCT AND WIDEN FROM 8 TO 12 LANE (ADD 4 MANAGED LANES) |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $129,950,000.00 |
Major Projects Questionnaire | View Questionnaire |
Resiliency and State of Good Repair Questionnaire | View Questionnaire |
Project ID | 1091 |
Agency Name | TxDOT Houston District |
Project Title | IH 610 S Reconstruction and Widening |
Facility/Street/Highway | IH 610 S |
Limits | From SH 35 (SS 5 /Mykawa) to FM 521 |
Description | RECONSTRUCT AND WIDEN FROM 8 TO 12 LANE (ADD 4 MANAGED LANES) |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $180,100,000.00 |
Major Projects Questionnaire | View Questionnaire |
Project ID | 1092 |
Agency Name | TxDOT Houston District |
Project Title | IH 610 West Express Lanes |
Facility/Street/Highway | IH 610 W |
Limits | From IH 69 S to IH 10 W |
Description | This project proposes to construct four express lanes from IH 10 W to IH 69 S and connect to existing and proposed managed lanes along IH 10 W and US 290. |
Timeframe | Long Term (More than 10 Years) |
Estimated Cost | $350,000,000.00 |
Major Projects Questionnaire | View Questionnaire |
Regional Goods Movement Questionnaire | View Questionnaire |
Project ID | 1093 |
Agency Name | TxDOT Houston District |
Project Title | IH 45 NHHIP, Segment 3B |
Facility/Street/Highway | IH 69 |
Limits | from SH 288 to IH 45 |
Description | RECONSTRUCT AND WIDEN FROM 8 TO 10 MAIN LANES AND RECONSTRUCT IH 69/SH 288 INTERCHANGE (NHHIP SEG 3B) |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $515,846,188.00 |
Project ID | 1094 |
Agency Name | TxDOT Houston District |
Project Title | IH 69 Rehab Pump Station at Hazard Street |
Facility/Street/Highway | IH 69 |
Limits | At Hazard Street |
Description | Rehabilitate pump station including baffles, trash collection system and control system and address concrete flatwork settling |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $3,342,003.00 |
Resiliency and State of Good Repair Questionnaire | View Questionnaire |
Project ID | 1095 |
Agency Name | TxDOT Houston District |
Project Title | IH 69 Rehab Pump Station at Mandell Street |
Facility/Street/Highway | IH 69 |
Limits | At Mandell Street |
Description | Rehabilitate pump station, improve trash collection system and upgrade control system |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $150,000.00 |
Resiliency and State of Good Repair Questionnaire | View Questionnaire |
Project ID | 1096 |
Agency Name | TxDOT Houston District |
Project Title | NHHIP SEG 3B - Drainage Improvements |
Facility/Street/Highway | IH 69 |
Limits | From N of IH 45 to Buffalo Bayou |
Description | INSTALL PUMP STATION OUTFALL, STORM SEWER, AND CONSTRUCT NEW DETENTION POND (NHHIP SEG 3B) |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $86,184,270.00 |
Project ID | 1097 |
Agency Name | TxDOT Houston District |
Project Title | IH 69 S Bridge Resiliency at Brazos River |
Facility/Street/Highway | IH 69 S |
Limits | At Brazos River |
Description | EROSION CONTROL AND LENGTHEN BRIDGE - The project consists of removing part of the bridge structure along the east bank of the Brazos River and lengthening the bridge section to 1,085 feet to counteract the erosion on the north side of the bridge. Also included are erosion control infrastructure to protect the bridge structure and turnaround lanes from damage. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $50,961,538.00 |
Project ID | 1098 |
Agency Name | TxDOT Houston District |
Project Title | IH 69 S Frontage Road replacement (Local Connection to Brazos River Park) |
Facility/Street/Highway | IH 69 S |
Limits | From East University Drive to IH 69 S |
Description | Provide for a new east-west road through the U of H Sugarland campus to provide connectivity to the University and to Brazos River Park. Compensates for removal of U turn on IH 69 S which has been destroyed by erosion. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $20,000,000.00 |
Operational Improvements and Congestion Management Questionnaire | View Questionnaire |
Resiliency and State of Good Repair Questionnaire | View Questionnaire |
Project ID | 1099 |
Agency Name | TxDOT Houston District |
Project Title | IH 69S RECONSTRUCT AND WIDEN |
Facility/Street/Highway | IH 69 S |
Limits | From SS 527 to SL 8 S |
Description | RECONSTRUCT AND WIDEN FROM 8 LANES TO 10 LANES |
Timeframe | Long Term (More than 10 Years) |
Estimated Cost | $1,267,500,000.00 |
Project ID | 1100 |
Agency Name | TxDOT Houston District |
Project Title | IH 45 NHHIP, Segment 3B |
Facility/Street/Highway | MCGOWEN, TUAM, AND ELGIN ST |
Limits | AT IH 69 |
Description | RECONSTRUCT 3 BRIDGES (NHHIP SEG 3B) |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $59,701,585.00 |
Project ID | 1101 |
Agency Name | TxDOT Houston District |
Project Title | SH 146 DC Ramps to Barbours Cut Port Terminal |
Facility/Street/Highway | SH 146 |
Limits | AT BARBOURS CUT BLVD |
Description | CONSTRUCT 3 DCs (SB-EB, WB-NB [SH 146], WB-NB [SH 225]) |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $50,000,000.00 |
Major Projects Questionnaire | View Questionnaire |
Regional Goods Movement Questionnaire | View Questionnaire |
Project ID | 1102 |
Agency Name | TxDOT Houston District |
Project Title | SH 146 Widening and other improvements |
Facility/Street/Highway | SH 146 |
Limits | From Ferry Road to Chambers C/L (Cedar Bayou) |
Description | Reconstruct and widen from 4 to 6 lanes, median, bicycle/pedestrian facilities and intersection improvements. |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $90,000,000.00 |
Operational Improvements and Congestion Management Questionnaire | View Questionnaire |
Regional Goods Movement Questionnaire | View Questionnaire |
Project ID | 1103 |
Agency Name | TxDOT Houston District |
Project Title | SH 225 at SL 8 Three Remaining DC ramps |
Facility/Street/Highway | SH 225 |
Limits | AT SL 8 |
Description | CONSTRUCT 3 DIRECT CONNECTOR RAMPS (EB-NB, EB-SB, WB-SB) |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $95,000,000.00 |
High Growth Area Needs Questionnaire | View Questionnaire |
Operational Improvements and Congestion Management Questionnaire | View Questionnaire |
Regional Goods Movement Questionnaire | View Questionnaire |
Project ID | 1104 |
Agency Name | TxDOT Houston District |
Project Title | SH 225 Widening/Operational Improvements |
Facility/Street/Highway | SH 225 |
Limits | From IH 610 to RED BLUFF RD |
Description | RECONSTRUCT AND WIDEN FROM 6 TO 12 LANE (ADD 2 GENERAL PURPOSE LANES AND 4 MANAGED LANES), INCLUDING SH 225/IH 610 INTERCHANGE - Safety, operational and mobility improvements to SH 225 mainlanes and frontage roads, based on results of the SH 225 PEL/IH 610 East PEL study |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $351,960,000.00 |
Major Projects Questionnaire | View Questionnaire |
Regional Goods Movement Questionnaire | View Questionnaire |
Project ID | 1105 |
Agency Name | TxDOT Houston District |
Project Title | SH 225 Widening/Operational Improvements |
Facility/Street/Highway | SH 225 |
Limits | From RED BLUFF RD to SL 8 |
Description | RECONSTRUCT AND WIDEN FROM 6 TO 12 LANE (ADD 2 GENERAL PURPOSE LANES AND 4 MANAGED LANES) - Safety, operational and mobility improvements to SH 225 mainlanes and frontage roads, based on results of the SH 225 PEL/IH 610 East PEL study |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $146,400,000.00 |
Major Projects Questionnaire | View Questionnaire |
Regional Goods Movement Questionnaire | View Questionnaire |
Project ID | 1106 |
Agency Name | TxDOT Houston District |
Project Title | SH 225 Widening/Operational Improvements |
Facility/Street/Highway | SH 225 |
Limits | From SL 8 to SH 146 |
Description | RECONSTRUCT AND WIDEN FROM 6 TO 12 LANE (ADD 2 GENERAL PURPOSE LANES AND 4 MANAGED LANES) - Safety, operational and mobility improvements to SH 225 mainlanes and frontage roads, based on results of the SH 225 PEL/IH 610 East PEL study |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $200,000,000.00 |
Major Projects Questionnaire | View Questionnaire |
Regional Goods Movement Questionnaire | View Questionnaire |
Project ID | 1107 |
Agency Name | TxDOT Houston District |
Project Title | SH 249 Widening |
Facility/Street/Highway | SH 249 |
Limits | From BW 8 to IH 45 |
Description | Reconstruct and widen from 6 to 8 lanes. Remove existing flush median, replace with raised median to increase safety, provide bike and ped accommodation, interconnect signals, provide for METRO boost bus stops and improve drainage to reduce flooding. |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $150,000,000.00 |
Major Projects Questionnaire | View Questionnaire |
Project ID | 1108 |
Agency Name | TxDOT Houston District |
Project Title | SH 288 Widening |
Facility/Street/Highway | SH 288 |
Limits | From SH 99 (CR 60) to FM 1462 |
Description | Reconstruct and widen from 4-lanes to 6-lanes. The proposed project will widen to the inside, adding two additional lanes (one in each direction), along with turn lanes at select locations. It will provide drainage for stormwater to accommodate the additional pavement. Frontage roads are not included in this project. |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $56,300,000.00 |
Major Projects Questionnaire | View Questionnaire |
Regional Goods Movement Questionnaire | View Questionnaire |
Project ID | 1109 |
Agency Name | TxDOT Houston District |
Project Title | SH 288 Widening |
Facility/Street/Highway | SH 288 |
Limits | From SH 35 to SH 332 |
Description | Reconstruct and widen from 4-lane to 6-lanes. The proposed project will widen to the inside, adding two additional lanes (one in each direction), along with turn lanes at select locations. It will provide drainage for stormwater to accommodate the additional pavement. Frontage roads are not included in this project. |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $209,300,000.00 |
Major Projects Questionnaire | View Questionnaire |
Regional Goods Movement Questionnaire | View Questionnaire |
Project ID | 1110 |
Agency Name | TxDOT Houston District |
Project Title | SH 288 Widening |
Facility/Street/Highway | SH 288 |
Limits | From FM 1462 to SH 35 |
Description | Reconstruct and widen from 4-lanes to 6-lanes. The proposed project will widen to the inside, adding two additional lanes (one in each direction), along with turn lanes at select locations. It will provide drainage for stormwater to accommodate the additional pavement. Frontage roads are not included in this project. |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $351,100,000.00 |
Major Projects Questionnaire | View Questionnaire |
Regional Goods Movement Questionnaire | View Questionnaire |
Project ID | 1111 |
Agency Name | TxDOT Houston District |
Project Title | SH 288 Submittals for RTP/Conformity model purposes only |
Facility/Street/Highway | SH 288 |
Limits | From SH 332 to BS 288 SOUTH |
Description | WIDEN FROM 4 TO 6 LANES |
Timeframe | Long Term (More than 10 Years) |
Estimated Cost | $153,900,000.00 |
Project ID | 1112 |
Agency Name | TxDOT Houston District |
Project Title | SH 288 Submittals for RTP/Conformity model purposes only |
Facility/Street/Highway | SH 288 |
Limits | From BS 288/SH 332 to SH 36 |
Description | WIDEN FROM 6 TO 8 MAIN LANES |
Timeframe | Long Term (More than 10 Years) |
Estimated Cost | $118,700,000.00 |
Project ID | 1113 |
Agency Name | TxDOT Houston District |
Project Title | SH 288 Submittals for RTP/Conformity model purposes only |
Facility/Street/Highway | SH 288 |
Limits | From IH 610 S to BRAZORIA C/L |
Description | CONSTRUCT 6 ULTIMATE TOLL LANES WITH ULTIMATE IH 610 DCs INTERCHANGE |
Timeframe | Long Term (More than 10 Years) |
Estimated Cost | $327,600,000.00 |
Project ID | 1114 |
Agency Name | TxDOT Houston District |
Project Title | SH 288 B (Velasco St.) Sidewalks |
Facility/Street/Highway | SH 288 B |
Limits | From East Ceder St. to E Orange St. |
Description | The project includes a 5 to 6-foot sidewalks, high visibility crossing striping, ADA ramps, pavement markings, and signage as well as other associated intersection improvements. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $4,000,000.00 |
Project ID | 1115 |
Agency Name | TxDOT Houston District |
Project Title | SH 3 Multiple Intersection Improvements |
Facility/Street/Highway | SH 3 |
Limits | At South Richey, Edgebrook Dr, El Dorado Blvd, and Bay Area Blvd |
Description | Change signals to mast arms, replace RR arms, and gates, and lengthen railroad planking. The purpose of the project is to extend sidewalks across the RR tracks parallel to SH 3. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $4,840,000.00 |
Regional Goods Movement Questionnaire | View Questionnaire |
Project ID | 1116 |
Agency Name | TxDOT Houston District |
Project Title | SH 3 Sidepath |
Facility/Street/Highway | SH 3 |
Limits | From FM 1765 to FM 519 |
Description | The project includes a 10-foot wide sidepath on SH 3 SB, high visibility crossing striping, ADA ramps, pavement markings, and signage as well as other associated intersection improvements. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $1,300,000.00 |
Project ID | 1117 |
Agency Name | TxDOT Houston District |
Project Title | SH 332 Grade Separation at FM 523 |
Facility/Street/Highway | SH 332 |
Limits | From N of FM 523 to S of FM 523 |
Description | Construct grade separation at FM 523. |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $24,710,000.00 |
High Growth Area Needs Questionnaire | View Questionnaire |
Regional Goods Movement Questionnaire | View Questionnaire |
Project ID | 1118 |
Agency Name | TxDOT Houston District |
Project Title | SH 332 Widening |
Facility/Street/Highway | SH 332 |
Limits | From East of FM 521 to SH 288 |
Description | WIDEN FROM 2 TO 4 LANES (FM 521 TO FM 2004) AND FROM 4 TO 6 LANES (FM 2004 TO SH 288) |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $114,000,000.00 |
Major Projects Questionnaire | View Questionnaire |
Project ID | 1119 |
Agency Name | TxDOT Houston District |
Project Title | SH 35 Feasibility Study |
Facility/Street/Highway | SH 35 |
Limits | From DIXIE DR to BS 35 S (N GORDON ST) |
Description | Conduct a mobility study to identify mobility and safety improvements on SH 35. Previously MPOIDs 309, 310, 18717, and 18718 |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $3,500,000.00 |
Major Projects Questionnaire | View Questionnaire |
Project ID | 1120 |
Agency Name | TxDOT Houston District |
Project Title | SH 35 New Location Roadway in Alvin |
Facility/Street/Highway | SH 35 |
Limits | from BS 35C N to SH 99 |
Description | Construct new location, 4-lane roadway |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $70,000,000.00 |
Major Projects Questionnaire | View Questionnaire |
Project ID | 1121 |
Agency Name | TxDOT Houston District |
Project Title | SH 35 Widen to 4 Lane Divided Rural |
Facility/Street/Highway | SH 35 |
Limits | From BS 35-C (South) to FM 2403 |
Description | Extend the 4-lane divided rural section roadway from where BS 35 connects at SH 35 down to FM 2403 |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $14,240,000.00 |
Major Projects Questionnaire | View Questionnaire |
Project ID | 1122 |
Agency Name | TxDOT Houston District |
Project Title | SH 35 Widening |
Facility/Street/Highway | SH 35 |
Limits | From FM 2403 to FM 523 |
Description | WIDEN FROM 2 TO 4 LANES - This project proposes to add two new lanes, raised medians, and bicycle/pedestrian facilities. |
Timeframe | Long Term (More than 10 Years) |
Estimated Cost | $192,300,000.00 |
Major Projects Questionnaire | View Questionnaire |
Project ID | 1123 |
Agency Name | TxDOT Houston District |
Project Title | SH 35 New Location |
Facility/Street/Highway | SH 35 |
Limits | From SH 99 to BS 35C South |
Description | CONSTRUCT 4 LANE FREEWAY ON NEW LOCATION - The proposed project will add four mainlanes on new location. |
Timeframe | Long Term (More than 10 Years) |
Estimated Cost | $80,920,000.00 |
Major Projects Questionnaire | View Questionnaire |
Project ID | 1124 |
Agency Name | TxDOT Houston District |
Project Title | SH 35 Construct frontage roads |
Facility/Street/Highway | SH 35 |
Limits | From S OF SH 6 to BS 35C S |
Description | CONSTRUCT TWO 2-LANE FRONTAGE ROADS |
Timeframe | Long Term (More than 10 Years) |
Estimated Cost | $28,100,000.00 |
Project ID | 1125 |
Agency Name | TxDOT Houston District |
Project Title | SH 35 Widening |
Facility/Street/Highway | SH 35 |
Limits | From FM 518 to S OF SH 6 |
Description | Widen roadway from 4 to 6 lanes |
Timeframe | Long Term (More than 10 Years) |
Estimated Cost | $175,700,000.00 |
Major Projects Questionnaire | View Questionnaire |
Project ID | 1126 |
Agency Name | TxDOT Houston District |
Project Title | SH 6 Pump Station Rehab and Detention Pond |
Facility/Street/Highway | SH 6 |
Limits | At BNSF RR near Avenue C/Perry Lane |
Description | Reconstruct Pump Station and Install New Detention Pond. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $2,931,283.00 |
Project ID | 1127 |
Agency Name | TxDOT Houston District |
Project Title | SH 6 Pedestrian Improvements |
Facility/Street/Highway | SH 6 |
Limits | From FM 1093 (Westheimer Road) to Piping Rock Lane |
Description | The project includes a 5- to 6- foot wide sidewalks NB and a 10ft shared use path SB, high visibility crossing striping, ADA ramps, pavement markings, median refuge and signage as well as other associated intersection improvements. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $2,500,000.00 |
Operational Improvements and Congestion Management Questionnaire | View Questionnaire |
Transit Questionnaire | View Questionnaire |
Project ID | 1128 |
Agency Name | TxDOT Houston District |
Project Title | SH 6 Intersection Improvements at FM 529 |
Facility/Street/Highway | SH 6 |
Limits | At FM 529 |
Description | INTERSECTION IMPROVEMENTS |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $15,500,000.00 |
Regional Goods Movement Questionnaire | View Questionnaire |
Project ID | 1129 |
Agency Name | TxDOT Houston District |
Project Title | SH 6 Construct Grade Separation |
Facility/Street/Highway | SH 6 |
Limits | From Pine Forest Road to Royal Mile Lane |
Description | Construct Grade Separation and Intersection Improvements |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $32,500,000.00 |
Operational Improvements and Congestion Management Questionnaire | View Questionnaire |
Project ID | 1130 |
Agency Name | TxDOT Houston District |
Project Title | SH 6 Safety and Operational Improvements |
Facility/Street/Highway | SH 6 |
Limits | From Westheimer (FM 1093) to IH 10 W |
Description | This project proposes safety and operational improvements. |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $40,000,000.00 |
Operational Improvements and Congestion Management Questionnaire | View Questionnaire |
Resiliency and State of Good Repair Questionnaire | View Questionnaire |
Project ID | 1131 |
Agency Name | TxDOT Houston District |
Project Title | SH 6 Resiliency at Addicks Reservoir |
Facility/Street/Highway | SH 6 |
Limits | From IH 10 W to Clay Road |
Description | Raise roadway to eliminate flooding from Addicks Reservoir. |
Timeframe | Long Term (More than 10 Years) |
Estimated Cost | $250,000,000.00 |
Major Projects Questionnaire | View Questionnaire |
Project ID | 1132 |
Agency Name | TxDOT Houston District |
Project Title | SH 75 Widening, Drainage Improvements, and Bike/Ped Improvements |
Facility/Street/Highway | SH 75 |
Limits | From FM 3083 (Teas Nursery Road) to League Line Road |
Description | RECONSTRUCT AND WIDEN TO 4-LANE DIVIDED ROADWAY - The proposed project will widen the existing two-lane roadway to a four-lane divided roadway with curbs and gutters. It will provide drainage for stormwater and add five-foot sidewalks on both sides of the roadway. |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $17,700,000.00 |
High Growth Area Needs Questionnaire | View Questionnaire |
Project ID | 1133 |
Agency Name | TxDOT Houston District |
Project Title | SH 75 Widening, Drainage Improvements, and Bike/Ped Improvements |
Facility/Street/Highway | SH 75 |
Limits | From League Line Road to FM 830 |
Description | RECONSTRUCT AND WIDEN TO 4-LANE DIVIDED ROADWAY - The proposed project will widen the existing two-lane roadway to a four-lane divided roadway with curbs and gutters. It will provide drainage for stormwater and add five-foot sidewalks on both sides of the roadway. |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $21,800,000.00 |
High Growth Area Needs Questionnaire | View Questionnaire |
Project ID | 1134 |
Agency Name | TxDOT Houston District |
Project Title | SH 75 Widening, Drainage Improvements, and Bike/Ped Improvements |
Facility/Street/Highway | SH 75 |
Limits | From FM 830 to FM 2432 |
Description | RECONSTRUCT AND WIDEN TO 4-LANE DIVIDED ROADWAY - The proposed project will widen the existing two-lane roadway to a four-lane divided roadway with curbs and gutters. It will provide drainage for stormwater and add five-foot sidewalks on both sides of the roadway. |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $33,500,000.00 |
High Growth Area Needs Questionnaire | View Questionnaire |
Project ID | 1135 |
Agency Name | TxDOT Houston District |
Project Title | Construct New Ferry Boat |
Facility/Street/Highway | SH 87 |
Limits | At Galveston Ferry |
Description | CONSTRUCT NEW FERRY BOAT (ADDITIONAL SHIP TO FLEET - NOT A REPLACEMENT SHIP) at the Galveston-Bolivar Ferry. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $43,800,000.00 |
Project ID | 1136 |
Agency Name | TxDOT Houston District |
Project Title | SH 87 Bolivar Bridge |
Facility/Street/Highway | SH 87 |
Limits | From Ferry Rd to SH 108 |
Description | Construct 4 lane Bridge on new location to replace ferry operations |
Timeframe | Long Term (More than 10 Years) |
Estimated Cost | $1,200,000,000.00 |
Major Projects Questionnaire | View Questionnaire |
Project ID | 1137 |
Agency Name | TxDOT Houston District |
Project Title | SH 96 Widening and Grade separation at SH 3 |
Facility/Street/Highway | SH 96 |
Limits | From IH 45 S to Hometown Heroes Dr/ Tuscan Village Dr |
Description | Widen the freeway from 4 to 6 lanes and provide a grade separation at SH 3 to relieve congestion. |
Timeframe | Long Term (More than 10 Years) |
Estimated Cost | $50,000,000.00 |
High Growth Area Needs Questionnaire | View Questionnaire |
Operational Improvements and Congestion Management Questionnaire | View Questionnaire |
Project ID | 1138 |
Agency Name | TxDOT Houston District |
Project Title | SH 99 Frontage Road Pedestrian Improvements |
Facility/Street/Highway | SH 99 |
Limits | From IH 10 W to Mercantile Pkwy across SH 99 to Mason Road |
Description | The project includes side path, high visibility crossing striping, ADA ramps, pavement markings, and signage as well as other associated intersection improvements. Construct a pedestrian/bicycle underpass |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $2,000,000.00 |
Project ID | 1139 |
Agency Name | TxDOT Houston District |
Project Title | SH 99 Frontage Rd |
Facility/Street/Highway | SH 99 |
Limits | From NB Westheimer Pkwy to Cinco Ranch Blvd |
Description | Construction of a two lane concrete curb and gutter frontage road. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $12,000,000.00 |
Project ID | 1140 |
Agency Name | TxDOT Houston District |
Project Title | SH 99 Frontage Rd |
Facility/Street/Highway | SH 99 |
Limits | From NB Fry Rd to Westheimer Pkwy |
Description | Construction of a two lane concrete curb and gutter frontage road. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $25,000,000.00 |
Project ID | 1141 |
Agency Name | TxDOT Houston District |
Project Title | SH 99 Sidepath |
Facility/Street/Highway | SH 99 |
Limits | From Colonial Pkwy to IH 10 W |
Description | The project includes a 10-foot wide sidepath, high visibility crossing striping, ADA ramps, pavement markings, and signage as well as other associated intersection improvements. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $2,000,000.00 |
Project ID | 1142 |
Agency Name | TxDOT Houston District |
Project Title | SH 99 Construct 4 lane tollway |
Facility/Street/Highway | SH 99 |
Limits | AT IH 69 S (SUGARLAND) |
Description | Construct 4-lane toll way 3rd level overpass. (SEG D) |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $39,800,000.00 |
Project ID | 1143 |
Agency Name | TxDOT Houston District |
Project Title | SH 99 Submittals for RTP/Conformity model Purposes Only |
Facility/Street/Highway | SH 99 |
Limits | From LANGSTON DR to KILGORE PWKY/IH 10 E OVERPASS |
Description | WIDEN FROM 2 LANES TO 4 LANES (TOLL ROAD) (SEG I-1 AND I-2) |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $33,000,000.00 |
Project ID | 1144 |
Agency Name | TxDOT Houston District |
Project Title | SH 99 Submittals for RTP/Conformity model Purposes Only |
Facility/Street/Highway | SH 99 |
Limits | From SH 288 to FORT BEND C/L |
Description | WIDEN EXISTING PAVEMENT FROM 4 TO 6 LANES TOLLWAY (SEG C-3) |
Timeframe | Long Term (More than 10 Years) |
Estimated Cost | $120,600,000.00 |
Project ID | 1145 |
Agency Name | TxDOT Houston District |
Project Title | SH 99 Submittals for RTP/Conformity model Purposes Only |
Facility/Street/Highway | SH 99 |
Limits | From LIBERTY C/L to E OF SH 146 (IN MONT BELVIEU) |
Description | WIDEN FROM 2 LANES TO 4 LANES (TOLL ROAD) (SEG I-1) |
Timeframe | Long Term (More than 10 Years) |
Estimated Cost | $40,000,000.00 |
Project ID | 1146 |
Agency Name | TxDOT Houston District |
Project Title | SH 99 Submittals for RTP/Conformity model Purposes Only |
Facility/Street/Highway | SH 99 |
Limits | From 0.3 MI S OF FM 1093 to 0.3 MI N OF FM 1093 |
Description | WIDEN EXISTING PAVEMENT FROM 4 TO 6 LANE TOLL BRIDGE AND APPROACHES (PHASE 2) (SEG D) |
Timeframe | Long Term (More than 10 Years) |
Estimated Cost | $31,500,000.00 |
Project ID | 1147 |
Agency Name | TxDOT Houston District |
Project Title | SH 99 Submittals for RTP/Conformity model Purposes Only |
Facility/Street/Highway | SH 99 |
Limits | AT US 90A |
Description | WIDEN EXISTING PAVEMENT FROM 4 TO 6 LANE BRIDGE AND APPROACHES (TOLL FEASIBLE) (PHASE 2) (SEG D) |
Timeframe | Long Term (More than 10 Years) |
Estimated Cost | $19,000,000.00 |
Project ID | 1148 |
Agency Name | TxDOT Houston District |
Project Title | SH 99 Submittals for RTP/Conformity model Purposes Only |
Facility/Street/Highway | SH 99 |
Limits | From S OF FM 1093 to IH 69 S |
Description | WIDEN EXISTING PAVEMENT FROM 4 TO 6 LANE TOLLWAY (PHASE 2) (SEG D) |
Timeframe | Long Term (More than 10 Years) |
Estimated Cost | $68,200,000.00 |
Project ID | 1149 |
Agency Name | TxDOT Houston District |
Project Title | SH 99 Submittals for RTP/Conformity model Purposes Only |
Facility/Street/Highway | SH 99 |
Limits | From FM 762 to IH 69 S |
Description | WIDEN EXISTING PAVEMENT FROM 4 TO 6 LANE TOLLWAY (PHASE 2) (SEG C-1) |
Timeframe | Long Term (More than 10 Years) |
Estimated Cost | $41,400,000.00 |
Project ID | 1150 |
Agency Name | TxDOT Houston District |
Project Title | SH 99 Submittals for RTP/Conformity model Purposes Only |
Facility/Street/Highway | SH 99 |
Limits | From BRAZORIA C/L to FM 762 |
Description | WIDEN EXISTING PAVEMENT FROM 4 TO 6 LANE TOLLWAY (PHASE 2) (SEG C-2) |
Timeframe | Long Term (More than 10 Years) |
Estimated Cost | $155,000,000.00 |
Project ID | 1151 |
Agency Name | TxDOT Houston District |
Project Title | SH 99 Submittals for RTP/Conformity model Purposes Only |
Facility/Street/Highway | SH 99 |
Limits | AT IH 69 S |
Description | CONSTRUCT 4 DIRECT CONNECTORS (TOLL) (SEG D) (EB-NB, WB-NB, SB-EB, SB-WB) |
Timeframe | Long Term (More than 10 Years) |
Estimated Cost | $104,000,000.00 |
Project ID | 1152 |
Agency Name | TxDOT Houston District |
Project Title | SH 99 Submittals for RTP/Conformity model Purposes Only |
Facility/Street/Highway | SH 99 |
Limits | From SH 146 to IH 45 S |
Description | CONSTRUCT 4-LANE TOLLWAY WITH LIMITED TWO 2-LANE FRONTAGE ROADS (SEG A) |
Timeframe | Long Term (More than 10 Years) |
Estimated Cost | $138,000,000.00 |
Project ID | 1153 |
Agency Name | TxDOT Houston District |
Project Title | SH 99 Submittals for RTP/Conformity model Purposes Only |
Facility/Street/Highway | SH 99 |
Limits | From IH 45 S to BRAZORIA C/L |
Description | WIDEN EXISTING PAVEMENT FROM 4 TO 6 LANES (TOLLWAY) (PHASE 2) (SEG B) |
Timeframe | Long Term (More than 10 Years) |
Estimated Cost | $144,500,000.00 |
Project ID | 1154 |
Agency Name | TxDOT Houston District |
Project Title | SH 99 Submittals for RTP/Conformity model Purposes Only |
Facility/Street/Highway | SH 99 |
Limits | AT IH 45 S |
Description | CONSTRUCT 4 DIRECT CONNECTORS (TOLL) (SEG A) (WB-NB, WB-SB, NB-EB, SB-EB) |
Timeframe | Long Term (More than 10 Years) |
Estimated Cost | $88,300,000.00 |
Project ID | 1155 |
Agency Name | TxDOT Houston District |
Project Title | SH 99 Submittals for RTP/Conformity model Purposes Only |
Facility/Street/Highway | SH 99 |
Limits | AT SH 146 |
Description | CONSTRUCT 4 DIRECT CONNECTORS (TOLL) (SEG A) (EB-NB, EB-SB, SB-WB, NB-WB) |
Timeframe | Long Term (More than 10 Years) |
Estimated Cost | $88,300,000.00 |
Project ID | 1156 |
Agency Name | TxDOT Houston District |
Project Title | SH 99 Submittals for RTP/Conformity model Purposes Only |
Facility/Street/Highway | SH 99 |
Limits | From SH 146E to CHAMBERS C/L |
Description | WIDEN EXISTING PAVEMENT FROM 4 TO 6 LANES TOLLWAY AND OVERPASSES (PHASE 2) (SEG I-2) |
Timeframe | Long Term (More than 10 Years) |
Estimated Cost | $87,000,000.00 |
Project ID | 1157 |
Agency Name | TxDOT Houston District |
Project Title | SH 99 Submittals for RTP/Conformity model Purposes Only |
Facility/Street/Highway | SH 99 |
Limits | From IH 45 N to MONTGOMERY C/L |
Description | WIDEN EXISTING PAVEMENT FROM 4 TO 6 LANES TOLLWAY (PHASE 2) (SEG G) |
Timeframe | Long Term (More than 10 Years) |
Estimated Cost | $19,800,000.00 |
Project ID | 1158 |
Agency Name | TxDOT Houston District |
Project Title | SH 99 Submittals for RTP/Conformity model Purposes Only |
Facility/Street/Highway | SH 99 |
Limits | AT SH 146 |
Description | CONSTRUCT 2 DIRECT CONNECTORS (TOLL) (SEG I-2) (SB-EB, WB-NB) |
Timeframe | Long Term (More than 10 Years) |
Estimated Cost | $46,600,000.00 |
Project ID | 1159 |
Agency Name | TxDOT Houston District |
Project Title | SH 99 Submittals for RTP/Conformity model Purposes Only |
Facility/Street/Highway | SH 99 |
Limits | AT HARDY TOLL RD |
Description | CONSTRUCT 4 DIRECT CONNECTORS (TOLL) (WB-NB, EB-NB, SB-WB, SB-EB) (SEG G) |
Timeframe | Long Term (More than 10 Years) |
Estimated Cost | $93,200,000.00 |
Project ID | 1160 |
Agency Name | TxDOT Houston District |
Project Title | SH 99 Submittals for RTP/Conformity model Purposes Only |
Facility/Street/Highway | SH 99 |
Limits | From COMMUNITY DR to US 90 |
Description | WIDEN FROM 2 LANE TOLLWAY TO 4 LANE TOLLWAY (SEG H) |
Timeframe | Long Term (More than 10 Years) |
Estimated Cost | $265,700,000.00 |
Project ID | 1161 |
Agency Name | TxDOT Houston District |
Project Title | SH 99 Submittals for RTP/Conformity model Purposes Only |
Facility/Street/Highway | SH 99 |
Limits | From US 90 to CHAMBERS C/L |
Description | WIDEN FROM 2 LANE TOLLWAY TO 4 LANE TOLLWAY (SEG I-1) |
Timeframe | Long Term (More than 10 Years) |
Estimated Cost | $212,600,000.00 |
Project ID | 1162 |
Agency Name | TxDOT Houston District |
Project Title | SH 99 Submittals for RTP/Conformity model Purposes Only |
Facility/Street/Highway | SH 99 |
Limits | From HARRIS C/L to IH 69 N |
Description | WIDEN EXISTING PAVEMENT FROM 4 TO 6 LANES TOLLWAY (PHASE 2) (SEG G) |
Timeframe | Long Term (More than 10 Years) |
Estimated Cost | $82,100,000.00 |
Project ID | 1163 |
Agency Name | TxDOT Houston District |
Project Title | SL 8 Frontage Road Pedestrian Improvements |
Facility/Street/Highway | SL 8 |
Limits | From Woodforest Blvd to Wallisville Road (SL 8 NB) and from Wallisville Road to Dalton Oaks Drive (SL 8 SB) |
Description | The project includes a -5 to 6- foot wide sidewalks, high visibility crossing striping, ADA ramps, pavement markings, and signage as well as other associated intersection improvements. The project also includes a pedestrian bridge. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $2,000,000.00 |
Operational Improvements and Congestion Management Questionnaire | View Questionnaire |
Transit Questionnaire | View Questionnaire |
Project ID | 1164 |
Agency Name | TxDOT Houston District |
Project Title | SL 8 Pump Station |
Facility/Street/Highway | SL 8 |
Limits | At Hardy Toll Road near Glee Ln. |
Description | Reconstruct pump station and outfall system to bring the facilities up to current code. |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $3,518,019.00 |
Resiliency and State of Good Repair Questionnaire | View Questionnaire |
Project ID | 1165 |
Agency Name | TxDOT Houston District |
Project Title | SL 8 Pump Station |
Facility/Street/Highway | SL 8 |
Limits | At IH 69 North |
Description | Rehabilitate existing pump station and upgrade the pump controls and trash collection system. |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $3,252,770.00 |
Resiliency and State of Good Repair Questionnaire | View Questionnaire |
Project ID | 1166 |
Agency Name | TxDOT Houston District |
Project Title | SL 8 Widening |
Facility/Street/Highway | SL 8 |
Limits | From North of US 90 to Woodforest Blvd |
Description | Widen From 4 to 8 Lanes - The roadway will be expanded from a four-lane facility to an eight-lane facility. |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $60,400,000.00 |
High Growth Area Needs Questionnaire | View Questionnaire |
Regional Goods Movement Questionnaire | View Questionnaire |
Project ID | 1167 |
Agency Name | TxDOT Houston District |
Project Title | SL 8 Pump Station |
Facility/Street/Highway | SL 8 |
Limits | At UA 90 |
Description | Rehabilitate Pump Station and Install New Detention Pond. |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $3,081,033.00 |
Project ID | 1168 |
Agency Name | TxDOT Houston District |
Project Title | SS 10 Widening |
Facility/Street/Highway | SS 10 |
Limits | From SH 36 West of Rosenberg to IH 69 S |
Description | WIDEN TO 4-LANE DIVIDED ROADWAY |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $53,870,000.00 |
Regional Goods Movement Questionnaire | View Questionnaire |
Project ID | 1169 |
Agency Name | TxDOT Houston District |
Project Title | ITS Support for Transtar |
Facility/Street/Highway | Transtar |
Limits | At Transtar |
Description | Provide ITS support to Transtar as part of annual support to the facility as a partner and to enhance operations. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $4,000,000.00 |
Operational Improvements and Congestion Management Questionnaire | View Questionnaire |
Project ID | 1170 |
Agency Name | TxDOT Houston District |
Project Title | ITS Support for Transtar |
Facility/Street/Highway | Transtar |
Limits | At Transtar |
Description | Provide ITS support to Transtar as part of annual support to the facility as a partner and to enhance operations. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $1,000,000.00 |
Operational Improvements and Congestion Management Questionnaire | View Questionnaire |
Project ID | 1171 |
Agency Name | TxDOT Houston District |
Project Title | ITS Support for Transtar |
Facility/Street/Highway | Transtar |
Limits | At Transtar |
Description | Provide ITS support to Transtar as part of annual support to the facility as a partner and to enhance operations. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $3,000,000.00 |
Operational Improvements and Congestion Management Questionnaire | View Questionnaire |
Project ID | 1172 |
Agency Name | TxDOT Houston District |
Project Title | ITS Support for Transtar |
Facility/Street/Highway | Transtar |
Limits | At Transtar |
Description | Provide ITS support to Transtar as part of annual support to the facility as a partner and to enhance operations. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $1,500,000.00 |
Operational Improvements and Congestion Management Questionnaire | View Questionnaire |
Project ID | 1173 |
Agency Name | TxDOT Houston District |
Project Title | US 90A Pump Station and drainage improvements |
Facility/Street/Highway | UA 90A |
Limits | At Griggs Road |
Description | Reconstruct Pump Station and Install New Detention Pond. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $2,795,445.00 |
Resiliency and State of Good Repair Questionnaire | View Questionnaire |
Project ID | 1174 |
Agency Name | TxDOT Houston District |
Project Title | US 290 Widening |
Facility/Street/Highway | US 290 |
Limits | From SH 6 to Harris County Line |
Description | Reconstruct and wide from 4 to 6 lanes. This project will widen the existing highway to the middle adding a third lane in each direction. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $133,790,000.00 |
Major Projects Questionnaire | View Questionnaire |
Regional Goods Movement Questionnaire | View Questionnaire |
Project ID | 1175 |
Agency Name | TxDOT Houston District |
Project Title | US 290 Widening |
Facility/Street/Highway | US 290 |
Limits | From Washington County Line to SH 6 |
Description | Reconstruct and wide from 4 to 6 lanes. This project will widen the existing highway to the middle adding a third lane in each direction. |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $188,640,000.00 |
Major Projects Questionnaire | View Questionnaire |
Regional Goods Movement Questionnaire | View Questionnaire |
Project ID | 1176 |
Agency Name | TxDOT Houston District |
Project Title | US 90 Greens Bayou Bridge |
Facility/Street/Highway | US 90 |
Limits | From W of Greens Bayou to E of Greens Bayou |
Description | Construct bridge (6 Main Lanes) over Greens Bayou in gap of US 90 mainlanes. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $29,100,000.00 |
Regional Goods Movement Questionnaire | View Questionnaire |
Project ID | 1177 |
Agency Name | TxDOT Houston District |
Project Title | US 90 Widening |
Facility/Street/Highway | US 90 |
Limits | From IH 10 W to FM 2855 |
Description | Widen from 2-lanes to 4-lanes divided. Reconstruct highway from 2 to 4 lanes and install medians and left turn bays. Also reconstruct and widen bridges at Kellner Creek, Brookshire Creek, Willow Fork Creek, and Snake Creek. Construct pedestrian and bicycle facilities and convert the existing open-ditch drainage to a closed stormwater system. |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $78,200,000.00 |
Major Projects Questionnaire | View Questionnaire |
Regional Goods Movement Questionnaire | View Questionnaire |
Project ID | 1178 |
Agency Name | TxDOT Houston District |
Project Title | US 90 Widening |
Facility/Street/Highway | US 90 |
Limits | From FM 2855 to Fort Bend County Line |
Description | Widen from 2-lane to 4-lane divided |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $57,790,000.00 |
Major Projects Questionnaire | View Questionnaire |
Regional Goods Movement Questionnaire | View Questionnaire |
Project ID | 1179 |
Agency Name | TxDOT Houston District |
Project Title | US 90 Reconstruct and Operational Improvements |
Facility/Street/Highway | US 90 |
Limits | From Waller County Line to FM 1463 |
Description | Reconstruct 4 lanes and operational improvements |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $5,460,000.00 |
Major Projects Questionnaire | View Questionnaire |
Regional Goods Movement Questionnaire | View Questionnaire |
Project ID | 1180 |
Agency Name | TxDOT Houston District |
Project Title | US 90 Grade Separation at Purple Sage |
Facility/Street/Highway | US 90 |
Limits | From West of Purple Sage to East of Purple Sage |
Description | Construct grade separation (6 Main Lanes) in gap of US 90 mainlanes at Purple Sage intersection. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $34,300,000.00 |
Regional Goods Movement Questionnaire | View Questionnaire |
Project ID | 1181 |
Agency Name | TxDOT Houston District |
Project Title | US 90 A Widening |
Facility/Street/Highway | US 90 A |
Limits | From FM 359 to SH 99 |
Description | RECONSTRUCT AND WIDEN FROM 4 TO 6 LANES DIVIDED |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $48,200,000.00 |
Major Projects Questionnaire | View Questionnaire |
Regional Goods Movement Questionnaire | View Questionnaire |
Project ID | 1182 |
Agency Name | TxDOT Houston District |
Project Title | Widen US 90 A |
Facility/Street/Highway | US 90 A |
Limits | From WHARTON C/L to MARICK RD |
Description | WIDEN FROM 2 TO 4 LANES |
Timeframe | Long Term (More than 10 Years) |
Estimated Cost | $76,100,000.00 |
Project ID | 1183 |
Agency Name | TxDOT Houston District |
Project Title | Widen US 90 A |
Facility/Street/Highway | US 90 A |
Limits | From MARICK RD to W OF SH 36 |
Description | WIDEN FROM 2 TO 4 LANES |
Timeframe | Long Term (More than 10 Years) |
Estimated Cost | $90,100,000.00 |
Project ID | 1184 |
Agency Name | TxDOT Houston District |
Project Title | US 90A Widening |
Facility/Street/Highway | US 90A |
Limits | From FM 762 to FM 359 |
Description | Widen from 4-lanes to 6-lanes divided (phase 3 of 3) |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $28,570,000.00 |
Regional Goods Movement Questionnaire | View Questionnaire |
Project ID | 1185 |
Agency Name | TxDOT Houston District |
Project Title | ITS Equipment Support |
Facility/Street/Highway | VA |
Limits | Various locations district-wide |
Description | Install new ITS equipment at various locations |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $5,000,000.00 |
Project ID | 1186 |
Agency Name | TxDOT Houston District |
Project Title | CCTV Replacement |
Facility/Street/Highway | VA |
Limits | Various locations district-wide |
Description | Replace CCTV equipment with new upgraded equipment |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $1,000,000.00 |
Project ID | 1187 |
Agency Name | TxDOT Houston District |
Project Title | ITS Equipment Support |
Facility/Street/Highway | VA |
Limits | Various locations district-wide |
Description | Install new ITS equipment at various locations |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $5,000,000.00 |
Project ID | 1188 |
Agency Name | TxDOT Houston District |
Project Title | DMS Upgrades |
Facility/Street/Highway | VA |
Limits | Various locations district-wide |
Description | Upgrade dynamic message sign boards |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $1,000,000.00 |
Project ID | 1189 |
Agency Name | TxDOT Houston District |
Project Title | ITS Equipment Support |
Facility/Street/Highway | VA |
Limits | Various locations district-wide |
Description | Provide ITS support |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $5,000,000.00 |
Operational Improvements and Congestion Management Questionnaire | View Questionnaire |
Project ID | 1190 |
Agency Name | TxDOT Houston District |
Project Title | CCTV Replacement |
Facility/Street/Highway | VA |
Limits | Various locations district-wide |
Description | Replace CCTV equipment with new upgraded equipment |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $2,000,000.00 |
Project ID | 1191 |
Agency Name | TxDOT Houston District |
Project Title | ITS Equipment Support |
Facility/Street/Highway | VA |
Limits | Various locations district-wide |
Description | Provide ITS support |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $3,500,000.00 |
Operational Improvements and Congestion Management Questionnaire | View Questionnaire |
Project ID | 1192 |
Agency Name | TxDOT Houston District |
Project Title | DMS Upgrades |
Facility/Street/Highway | VA |
Limits | Various locations district-wide |
Description | Upgrade dynamic message sign boards |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $1,000,000.00 |
Project ID | 1193 |
Agency Name | TxDOT Houston District |
Project Title | Communication Upgrades |
Facility/Street/Highway | VA |
Limits | Various locations district-wide |
Description | Upgrade communications system |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $2,000,000.00 |
Project ID | 1194 |
Agency Name | TxDOT Houston District |
Project Title | Connect Smart Phase 2 (FY 23, 24, 25) - Marketing and Outreach |
Facility/Street/Highway | VA |
Limits | Various locations district-wide |
Description | ConnectSmart Phase 2 – Marketing and Outreach |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $3,000,000.00 |
Project ID | 1195 |
Agency Name | TxDOT Houston District |
Project Title | Connect Smart Phase 2 (FY 23, 24, 25) - Features Expansion |
Facility/Street/Highway | VA |
Limits | Various locations district-wide |
Description | ConnectSmart Phase 2 – Features Expansion |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $12,000,000.00 |
Project ID | 1196 |
Agency Name | TxDOT Houston District |
Project Title | Connect Smart Phase 2 (FY 23, 24, 25) - Operations and Maintenance |
Facility/Street/Highway | VA |
Limits | Various locations district-wide |
Description | ConnectSmart Phase 2 – Operations and Maintenance |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $900,000.00 |
Project ID | 1197 |
Agency Name | Waller County |
Project Title | Woods Rd North Expansion |
Facility/Street/Highway | Woods Rd |
Limits | US-90 to IH-10 |
Description | Expans existing 2 lane road to 4 Lanes road with CLTL |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $4,700,000.00 |
Project ID | 1198 |
Agency Name | City of Bunker Hill Village |
Project Title | Memorial Drive Phase 2 |
Facility/Street/Highway | Memorial Drive Gessner Lane |
Limits | Tallowood Road to Warrenton Drive Just north of Memorial Drive to Vanderpool Lane |
Description | Reconstruction of Memorial Drive and a components of Gessner (reconstruct northbound travel lanes; construct 6-FT sidewalks on southbound side) to improve access management, multimodal safety, transit access, and drainage. Includes pedestrian and bicycle facilities. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $29,200,000.00 |
High Growth Area Needs Questionnaire | View Questionnaire |
Resiliency and State of Good Repair Questionnaire | View Questionnaire |
Project ID | 1199 |
Agency Name | City of Houston |
Project Title | Dairy Ashford |
Facility/Street/Highway | Dairy Ashford Rd. |
Limits | From Briar Forest Dr. to Memorial Dr. Intersection improvements at Briar Patch Dr. & Briar Forest Dr. |
Description | Improvements include Reconstruction of the roadway while maintaining existing number of lanes along Dairy Ashford and with 6-foot sidewalks, new bridges over Buffalo Bayou, and drainage improvements to convey the runoff from the project area and meet COH design requirements. Improvements also include intersection improvements as well as installation of new pedestrian crosswalks at 3 locations. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $36,336,900.00 |
Resiliency and State of Good Repair Questionnaire | View Questionnaire |
Project ID | 1200 |
Agency Name | City of Houston |
Project Title | Lower Westheimer |
Facility/Street/Highway | Westheimer Rd. |
Limits | From Montrose Blvd to Main St |
Description | Improvements include reconstruction of Westheimer Road and all intersections within the project limits to facilitate safe transportation options for all roadway users, including those walking, biking, taking transit, and driving. The proposed 3-lane cross section will accommodate safe and efficient traffic operations, support Metro BOOST transit improvements, and prioritize space for wide sidewalk areas and pedestrian amenities. Safe crossings for people walking, biking, and taking transit will be provided at regular intervals along the corridor. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $25,000,000.00 |
Resiliency and State of Good Repair Questionnaire | View Questionnaire |
Project ID | 1201 |
Agency Name | City of Houston |
Project Title | Oates Rd |
Facility/Street/Highway | Oates Rd. |
Limits | From Wallisville to Beaumont Highway |
Description | Improvements include full concrete reconstruction of the corridor to include two 11-ft lanes (with 1-ft offsets) with a 12-ft center turn lane in the middle, as well as pedestrian improvements which include two 10-ft shared use paths on both sides of the road. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $29,500,000.00 |
Regional Goods Movement Questionnaire | View Questionnaire |
Resiliency and State of Good Repair Questionnaire | View Questionnaire |
Project ID | 1202 |
Agency Name | City of Houston |
Project Title | Parker Road |
Facility/Street/Highway | Parker Rd. |
Limits | W. Little York & Jensen |
Description | Improvements include reducing vehicle lanes to meet capacity and improving intersections for all road users including pedestrian enhancements and bikeways on either side of the roadway |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $4,000,000.00 |
Project ID | 1203 |
Agency Name | City of Houston |
Project Title | Aldine-Westfield |
Facility/Street/Highway | Aldine-Westfield |
Limits | From BW 8 to S of Little York Rd. |
Description | The proposed project would improve the roadway from the existing 2-way road to a 4-lane divided corridor with a median, improved intersections and turning lanes, upgraded signals, and pedestrian facilities. Improvements to the drainage along the corridor include replacing the open ditch drainage system with a curb and gutter system. Improvement include pedestrian enhancements such as a sidewalk and bikeway on either side of the roadway. |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $155,000,000.00 |
Major Projects Questionnaire | View Questionnaire |
Project ID | 1204 |
Agency Name | City of Houston |
Project Title | Gellhorn Dr. |
Facility/Street/Highway | Gellhorn Dr. |
Limits | Between I-10 on the south and I-610 on the north |
Description | Project includes improvement of freight connectivity between IH-610 & IH-10 as well as intersection operations. Improvements will also create safer pedestrian & bicycle facilities and mitigate storm sewer deficiencies. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $17,786,415.00 |
Regional Goods Movement Questionnaire | View Questionnaire |
Resiliency and State of Good Repair Questionnaire | View Questionnaire |
Project ID | 1205 |
Agency Name | City of Houston |
Project Title | City of Houston - Safety Package |
Facility/Street/Highway | W 43rd St. Bailey St. Beauchamp St. Bissonnet St. Campbell Rd. Cook Rd. Newhouse St. TC Jester Blvd. Westpark Dr. Cavalcade @ Hirsch Yale @ 6th Fannin @ Pease Memorial @ Pierce 75th/Garland @ Griggs Fannin @ Pierce Aldine Westfield @ Aldine Mail Route |
Limits | W 43rd St. & Curtin St. From 2034 Bailey St. to 100 McGowen St. From 2614 Beauchamp St. to 1602 White Oak Dr. Bissonnet St. & Court Glen Dr. Intersection Campbell Rd. and Peppermill Rd. 6900 Cook Rd. From 1112 S Shepherd Dr. to 1200 S. Shepherd Dr. From 500' South of W 18th St. to 50' North of W 18th St. From Newcastle Dr. to Weslayan St. Cavalcade St. Cavalcade @ Hirsch Yale @ 6th Fannin @ Pease Memorial @ Pierce 75th/Garland @ Griggs Fannin @ Pierce Aldine Westfield @ Aldine Mail Route |
Description | The Safety Package project includes the installation of high visibility crosswalks with Pedestrian Hybrid Beacons, traffic signal, pavement markings, curb extensions, curb ramps at intersections, crosswalk improvements, median reconstruction, road diet, roundabouts, etc. at specified locations. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $9,202,531.00 |
Project ID | 1206 |
Agency Name | City of Houston |
Project Title | City of Houston - Railroad Quiet Zones |
Facility/Street/Highway | Alabonson Rd North Houston-Rosslyn Lyons Ave Holcombe Blvd Old Spanish Trail Yale Courtland North Main Cornell Binkman Alba Golf Ella Blvd Oak Forest East TC Jester West TC Jester S. 75th Lawndale Redwood Bobby Lee 66th St Cesar Chavez Blvd / 67th 70th Street Golf Course 65th 66th S Cesar Chavez Blvd / 67th S Sergeant Macario Garcia Dr Wayside 70th St Golf Course N 71st N 72nd Cullen Leeland Milby McKinney York Sampson Laurentide Pleasantville Portwall St Erath St E Hedrick (UP STRANG SUB) 75th (PTRA SOUTHSHORE) 76th (PTRA SOUTHSHORE) 75th (UP BOOTH YARD) 75th (PTRA NONE) |
Limits | Alabonson Rd North Houston-Rosslyn Lyons Ave Holcombe Blvd Old Spanish Trail Yale Courtland North Main Cornell Binkman Alba Golf Ella Blvd Oak Forest East TC Jester West TC Jester S. 75th Lawndale Redwood Bobby Lee 66th St Cesar Chavez Blvd / 67th 70th Street Golf Course 65th 66th S Cesar Chavez Blvd / 67th S Sergeant Macario Garcia Dr Wayside 70th St Golf Course N 71st N 72nd Cullen Leeland Milby McKinney York Sampson Laurentide Pleasantville Portwall St Erath St E Hedrick (UP STRANG SUB) 75th (PTRA SOUTHSHORE) 76th (PTRA SOUTHSHORE) 75th (UP BOOTH YARD) 75th (PTRA NONE) |
Description | Quiet Zone project includes installation of Constant Warning( CW) technology, Supplemental Saftey Measures (SMM) and Alternative Safety Measures (ASM) at specified locations. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $11,275,000.00 |
Project ID | 1207 |
Agency Name | City of Houston |
Project Title | Waugh Dr. - Package 1 |
Facility/Street/Highway | Waugh Dr. |
Limits | Pedestrian & bicycle connections over Memorial Dr. & Buffalo Bayou |
Description | This project package includes all short-term pedestrian and bicycle connections over Memorial Drive and Buffalo Bayou. This package was developed to be a short-term series of projects to provide needed access as soon as possible. Project includes construction of multiple pedestrian bridges and intersection connections. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $24,980,000.00 |
Project ID | 1208 |
Agency Name | City of Houston |
Project Title | Waugh Dr. - Package 2 - 4 |
Facility/Street/Highway | Waugh Dr. |
Limits | From Washington St. on the north through the cloverleaf intersection to Allen Parkway |
Description | Project includes replacement of cloverleaf interchange with SPUI at Memorial Dr., Realignment & rebuild of Bat Bridge over Buffalo Bayou, Realignment and rebuild of Allen Parkway bridge, rebuild of roadway from Washington to Allen Parkway including Waugh & S. Heights, drainage improvements & detention, water line improvements, regional trail connectivity, enhancements of Spotts park & remedial landscape enhancements. |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $120,780,000.00 |
Major Projects Questionnaire | View Questionnaire |
Project ID | 1209 |
Agency Name | City of Houston / Memorial Heights Redevelopment Authority |
Project Title | Shepherd-Durham Infrastructure Improvements |
Facility/Street/Highway | Shepherd and Durham Drives and Various Cross Streets (11th, 12th, 14th) |
Limits | W. 15th Street to IH 10 WB FR |
Description | Roadway reconstruction to include re-configuration of travel lanes from 4 to 3, addition of bike facilities, and pedestrian infrastrucure |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $65,000,000.00 |
Project ID | 1210 |
Agency Name | City of Houston/Hermann Park Conservancy |
Project Title | Hermann Park Connectivity & Safety Improvements |
Facility/Street/Highway | Hermann Park Drive Improvements Hermann Park Drive, Caroline Street, Cambridge Street Bayou Connector Trail |
Limits | Hermann Park Drive Improvements - Hermann Park Drive (Fannin Street to Cambridge Street) - Caroline Street (Hermann Drive to Hermann Park Drive) - Cambridge Street (Hermann Park Drive to MacGregor Way) Bayou Connector Trail Hermann Park Drive to Brays Bayou Trail including new connection underneath MacGregor Way |
Description | The Hermann Park Drive project will reconfigure Hermann Park Drive with safer intersections and crossings, a dedicated high-comfort bikeway through Hermann Park, more efficient allocation of vehicle travel lanes through the length of the corridor, and better pedestrian and bicycle connections to the City's street, trail, and transit networks. The project requires a mix of reconstruction, repaving, and/or restriping depending on the existing condition of the roadway segment. The Bayou Connector Trail project will also create a new east-west connection from the heart of the park to Brays Bayou trails with a new safe crossing at MacGregor Way. Hermann Park Drive $13.0 million Bayou Connector Trail $13.9 million Total $26.9 million |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $26,900,000.00 |
Project ID | 1211 |
Agency Name | East End District in Coordination with Buffalo Bayou Partnership and Harris County Precinct 2 |
Project Title | Navigation Boulevard Reconfiguration |
Facility/Street/Highway | Navigation Boulevard |
Limits | Lockwood Drive to Mack Street |
Description | Reconfigure multimodal mobility corridor by converting unused lane capacity into a new dedicated commuter bike route, pedestrian amenities and additional greenspace. Project scope includes necessary work on public utilities. Project is a major component of the Buffalo Bayou East Master Plan. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $17,250,000.00 |
Regional Goods Movement Questionnaire | View Questionnaire |
Project ID | 1212 |
Agency Name | Greater Northside Management District |
Project Title | Berry Road Reconstruction |
Facility/Street/Highway | Berry Road |
Limits | Airline Drive to Jensen Drive |
Description | Improve safety and multimodal access on corridor, particularly for students and nearby businesses. Improvements will install new sidewalks or shared use paths, improve lighting and signage, address drainage concerns as needed, and rehabilitate roadway where needed. |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $17,300,000.00 |
High Growth Area Needs Questionnaire | View Questionnaire |
Resiliency and State of Good Repair Questionnaire | View Questionnaire |
Project ID | 1213 |
Agency Name | Greater Northside Management District |
Project Title | Jensen Drive Reconstruction |
Facility/Street/Highway | Jensen Drive |
Limits | Parker Road to Kelley Street |
Description | Reconstruct and reconfigure Jensen Drive from Parker Road to Kelley Street to include modifying the existing cross-section to include continuous bicycle and pedestrian facilities and access to transit facilities. Include stormwater, wastewater, and water improvements. |
Timeframe | Long Term (More than 10 Years) |
Estimated Cost | $95,000,000.00 |
Project ID | 1214 |
Agency Name | Greater Northside Management District |
Project Title | Tidwell Road Reconstruction |
Facility/Street/Highway | Tidwell Road |
Limits | Nordling Street to Irvington Boulevard |
Description | Reconstruct and reconfigure Tidwell Road from Nordling Street to Irvington Blvd to include modifying the existing cross-section to include sidewalks on both sides of the roadway, center median to provide pedestrian refuge, and dedicated left turn lanes throughout the corridor. Includes stormwater, wastewater, and water improvements. |
Timeframe | Long Term (More than 10 Years) |
Estimated Cost | $73,000,000.00 |
Project ID | 1215 |
Agency Name | Greater Northside Management District |
Project Title | Airline Drive Intersection Improvements and Road Diet |
Facility/Street/Highway | Airline Drive |
Limits | Parker Road to North Main Street (Intersection Improvements @ Berry Road and @ Gibbs St/Service St/Link Rd. Repurpose travel lane from E 28th Street to North Main Street) |
Description | Improve safety and access and several intersections on corridor. Repurpose travel lane and install shared use paths between E 28th Street and North Main Street to enhance pedestrian and cyclist realm. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $6,000,000.00 |
Project ID | 1216 |
Agency Name | Greater Northside Management District |
Project Title | Combined Short Term Improvement Projects |
Facility/Street/Highway | Airline Drive, Jensen Drive, Tidwell Road |
Limits | - Airline Drive & Witcher Lane - Airline Drive & Burress Street - Airline Drive & Parker Road - Jensen Drive & Aldine Westfield Road - Jensen Drive south of Tidwell Road at McDonald's entrance - Tidwell Road between Nordling St and Irvington Blvd |
Description | Improve safety and access at intersections on Airline Drive and Jensen Drive, including upgrading pavement markings, crosswalks, ADA-compliant ramps, install rectangular rapid flashing beacons; mitigate turning movement conflicts on Jensen Drive near McDonald's; spot improvements on Tidwell Road to improve sections of inadequate sidewalks, ADA ramps, crosswalks, and pavement markings. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $1,500,000.00 |
Project ID | 1217 |
Agency Name | Greater Northside Management District |
Project Title | Back-of-Curb Short Term Improvement Projects |
Facility/Street/Highway | Fulton, North Main, Boundary, Brooks, and Freeman |
Limits | Various locations |
Description | Install pedestrian lighting, trash receptacles, and bike racks |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $5,000,000.00 |
Project ID | 1218 |
Agency Name | Greater Northside Management District |
Project Title | Safe Access to Transit Improvements |
Facility/Street/Highway | Airline Dr Berry Rd Crosstimbers St Fulton Dr Irvington Blvd Jensen St Parker Rd Tidwell Rd |
Limits | Tidwell Rd to Lyerly St Airline Dr to Irvington Blvd Fulton St to Jensen Dr Berry Rd to Quitman St Cavalcade to Collingsworth St Tidwell Rd to Vance St East of IH-45 to Aldine Westfield Rd Airline Dr to Irvington Blvd |
Description | Comprises of the installation of intersection/crosswalk improvements, medians, access management improvements, multimodal signalization improvements, sidewalks, bicycle improvements, ADA ramps, universal accessibility improvements, pedestrian lighting, and functional landscaping, and will enable associated utility/hardscape modifications to improve access to METRO rail and bus corridors in the Greater Northside Management District boundaries |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $5,000,000.00 |
Project ID | 1219 |
Agency Name | Greater Southeast Management District |
Project Title | Greater Third Ward Neighborhood Improvement Project |
Facility/Street/Highway | Tuam St Anita St Rosalie St Stuart St Francis St Division St Bastron St St Charles St Gray St Webster St Mcllhenny St McGowen St Nagle St Nagle St Sauer St Hadley St Dennis St Drew St Bastrop St St Charles St |
Limits | Chartres St to Sauer St Emancipation to Sauer St Emancipation to Sauer St St Emanuel St to Live Oak St St Emanuel St to Ennis St St Charles St to Live Oak St Elgin St to Alabama St Division St to Alabama St Hutchins St to Sauer St Hutchins St to Nagle St Bastrop St to Live Oak St Hutchins St to Live Oak St Hadley St to Webster St Chaco St to Pierce St Gray St to Pierce St Hutchins St to Nagle St Chartres St to Sauer St Chartres St to Sauer St Pierce St to Dennis St Tuam St to Pierce St |
Description | Project consists of total roadway rehabilitation inclusive of pavement, curb, gutter, sidewalks, drainage, ADA-ramps, and transit pads and access. The project includes a high comfort bicycle facility along Tuam St. Project seeks funding for the FTA-eligible components which are focused on bicycle/pedestrian/transit connectivity. Total Eligible Cost: $10,000,000 |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $10,000,000.00 |
Project ID | 1220 |
Agency Name | Greater Southeast Management District |
Project Title | MLK Blvd and Old Spanish Trail Improvements |
Facility/Street/Highway | MLK Blvd and Old Spanish Trail |
Limits | MLK Blvd and Old Spanish Trail |
Description | Reconfigure intersection to reduce crossing distances and improve safety. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $1,500,000.00 |
Project ID | 1221 |
Agency Name | Greater Southeast Management District |
Project Title | Long, Griggs, Mykawa Rail Safety Improvement Project |
Facility/Street/Highway | Long Drive Griggs Road Mykawa Road |
Limits | Intersection @ UPRR and BNSF |
Description | Construct grade separation to accommodate motorists, bicyclists, pedestrians, and future METRO Light Rail over the BNSF and UPRR railroad tracks. Grade separation will be separate from overhead TxDOT SH-35 project. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $55,000,000.00 |
Project ID | 1222 |
Agency Name | Gulfgate Redevelopment Authority |
Project Title | Telephone Rd Reconstruction |
Facility/Street/Highway | Telephone Rd |
Limits | IH 610 Frontage - Reveille St |
Description | Replace all public infrastructure and reconfigure roadway to enhance multimodal access and safety (roadway, utilities, access management, pedestrian realm, bike lane) |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $45,000,000.00 |
High Growth Area Needs Questionnaire | View Questionnaire |
Operational Improvements and Congestion Management Questionnaire | View Questionnaire |
Regional Goods Movement Questionnaire | View Questionnaire |
Resiliency and State of Good Repair Questionnaire | View Questionnaire |
Project ID | 1223 |
Agency Name | International Management District |
Project Title | Safe Streets and Roads for All Program |
Facility/Street/Highway | Various segments and intersections throughout the International District on the following facilities: Beechnut Street, Howell Sugar Land Road, Boone Loop, Leawood Blvd, D-118 Conveyance Channel, Cook Road |
Limits | •Howell Sugar Land Road from Bellaire Blvd to Alief Clodine Road • Beechnut Street from Boone Road to W Sam Houston Parkway • Boone Loop from Boone Road to Wilcrest Drive • Leawood Blvd at Evesborough Drive • D-118 Conveyance Channel from Leawood Blvd to Landsbury Drive • Intersection at Cook Road and Beechnut Street |
Description | The program will close sidewalk gaps across the District, providing safer connections and enhanced accessibility and connectivity for students, pedestrians, and cyclists. Improvements included as part of the project scope are: installing new and upgrade existing sidewalks and shared use paths; upgrading existing and installing new traffic signals; installing a hooded left turn to eliminate conflicts at turning movements; and installing a new high intensity crosswalk signal near E.A. Olle Middle School. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $4,900,000.00 |
Project ID | 1224 |
Agency Name | International Management District |
Project Title | Bissonnet Street Safe Routes to School |
Facility/Street/Highway | Bissonnet Street |
Limits | Eldridge Parkway to Dairy Ashford |
Description | This project will provide safe routes to school enabling and encouraging children to walk, roll, and bicycle to school in a safer and more appealing environment within the IMD region, particularly for the seven schools adjacent to the project corridor. Improvements include upgrading existing and installing new sidewalks on both sides of Bissonnet Street, installing a new stop sign, installing street lights, upgrading intersections, upgrading bus shelters and bus pads, upgrading existing drainage, and landscaping and beautification to coincide with the District's Landscape Plan. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $10,200,000.00 |
Project ID | 1225 |
Agency Name | International Management District |
Project Title | Bellaire Blvd Signature Reconstruction |
Facility/Street/Highway | Bellaire Blvd |
Limits | SH 6 to W Sam Houston Parkway |
Description | This project aims to reduce fatalities and injuries along the corridor, as well as improve streets to encourage economic development, increase property values, and provide for greater mobility. Improvements include upgrading existing and installing new sidewalks; upgrading existing and installing new traffic signals; installing a hooded left turn to eliminate conflicts at turning movements; upgrading pedestrian crossing signals, pavement markings, and ADA accessibility at intersections; addressing access management based on City requirements; upgrading and improving storm water drainage, as well as sanitary sewer and water pipes; upgrading bus shelters; and landscaping and beautification to coincide with the District's Landscape Plan. |
Timeframe | Long Term (More than 10 Years) |
Estimated Cost | $148,000,000.00 |
Project ID | 1226 |
Agency Name | Memorial Heights Redevelopment Authority |
Project Title | 20th Street Reconstruction & Safety Improvements |
Facility/Street/Highway | 20th Street (becomes 18th at western limits) |
Limits | 20th / 18th & West TC Jester to 20th and just west of Durham Drive |
Description | Reconstruct and reconfigure 20th to include access management, safety, and pedestrian improvements. Project would endeavor to leverage existing rights-of-way to extent possible but may add in a complete or partial center turn lane. Project includes significant drainage improvements to mitigate area flood events. |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $39,000,000.00 |
Project ID | 1227 |
Agency Name | Memorial Heights Redevelopment Authority |
Project Title | 11th Street Shared Use Path |
Facility/Street/Highway | 11th Street |
Limits | Nashua St. to Ella Boulevard |
Description | Construct 12-FT shared use path on the north side of W. 11th to include ADA ramps, high visibility cross-walks and traffic signal improvements. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $1,274,000.00 |
Project ID | 1228 |
Agency Name | Memorial Heights Redevelopment Authority |
Project Title | Washington and Center Reconfiguration |
Facility/Street/Highway | Washington Avenue, Westcott Street, and Center Street |
Limits | Washington Avenue from IH-10 to Bagby Street to include Wescott Street and Center Street to include connecting streets and adjacent intersections. |
Description | Reconstruct and reconfigure Washington, Wescott, and Center to include access management, safety, and bicycle/pedestrian improvements. Improvements to be driven by UPWP-funded planning effort, underway in 2022. |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $202,500,000.00 |
Project ID | 1229 |
Agency Name | Memorial Heights Redevelopment Authority |
Project Title | MHRA Bridge Investment Program |
Facility/Street/Highway | Ella @ White Oak Bayou 18th/20th @ White Oak Bayou Shepherd Dr @ White Oak Bayou Durham Dr @ White Oak Bayou TC Jester @ White Oak Bayou (adjacent Cranston Ct) TC Jester and White Oak Bayou (adjacent Bryce) 11th @ White Oak Bayou |
Limits | Bridge structure plus approaches |
Description | Replace existing bridges to enable appropriate White Oak Bayou stormwater conveyance, enable pedestrian/bicycle access, and improve state of good repair. |
Timeframe | Long Term (More than 10 Years) |
Estimated Cost | $63,000,000.00 |
Project ID | 1230 |
Agency Name | Midtown Management District |
Project Title | Webster Street Reconfiguration |
Facility/Street/Highway | Webster Street |
Limits | Matthews Street to Chenevert |
Description | Reconstruction and reconfiguration of street to accommodate multimodal users and enhance safety and access. Include water, wastewater, and stormwater improvements. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $25,000,000.00 |
High Growth Area Needs Questionnaire | View Questionnaire |
Resiliency and State of Good Repair Questionnaire | View Questionnaire |
Project ID | 1231 |
Agency Name | Midtown Management District |
Project Title | Tuam Street Safety Improvements |
Facility/Street/Highway | Tuam Street |
Limits | Genessee St and Milam St |
Description | Midtown plans to improve existing conditions of Tuam St. between Genessee and Milam. On-street bicycle sharrow markings will be added to the entire segment, as consistent with the Houston Bike Plan. On the western end of the corridor (Genessee to Bagby) Midtown will install landscaping medians, pedestrian refuge islands, and enhanced signage at key locations to reduce crossing distances and improve safety for bicyclists and pedestrians. On the eastern side of the corridor (Bagby to Milam) Midtown will add bicycle phase signals to the existing signalized intersections. The City of Houston will install a traffic signal at Tuam and Smith in 2023; Midtown is performing a signal warrant study at Tuam and Louisiana with the intention of placing a traffic signal as part of this project. Additionally, Midtown will improve sidewalks, curb ramps, and additional lighting along the entire segment of Tuam. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $2,500,000.00 |
Project ID | 1232 |
Agency Name | Midtown Management District |
Project Title | Travis Street Reconfiguration |
Facility/Street/Highway | Travis Street |
Limits | IH-69 to Pierce |
Description | Reconstruction and reconfiguration of street to accommodate multimodal users and enhance safety and access. Include water, wastewater, and stormwater improvements. |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $25,000,000.00 |
Project ID | 1233 |
Agency Name | Midtown Management District |
Project Title | Fannin Street Reconfiguration |
Facility/Street/Highway | Fannin Street |
Limits | IH-69 to Pierce |
Description | Reconstruction and reconfiguration of street to accommodate multimodal users and enhance safety and access. Include water, wastewater, and stormwater improvements. |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $33,750,000.00 |
Project ID | 1234 |
Agency Name | Midtown Management District |
Project Title | Caroline and Wheeler NHHIP Impact Mitigation |
Facility/Street/Highway | Caroline @ Wheeler @ IH-69 |
Limits | Caroline @ Wheeler @ IH-69 |
Description | Enable implementation of connectivity, green space, and community connections as associated with NHHIP Project. |
Timeframe | Long Term (More than 10 Years) |
Estimated Cost | $75,000,000.00 |
High Growth Area Needs Questionnaire | View Questionnaire |
Resiliency and State of Good Repair Questionnaire | View Questionnaire |
Project ID | 1235 |
Agency Name | Montrose TIRZ 27 Redevelopment Authority |
Project Title | Montrose Boulevard Reconstruction |
Facility/Street/Highway | Montrose Boulevard |
Limits | West Clay to US-59/IH-69 |
Description | Replace all public infrastructure (roadway, utilities, access management, pedestrian realm, transit, bike lane) |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $47,000,000.00 |
High Growth Area Needs Questionnaire | View Questionnaire |
Operational Improvements and Congestion Management Questionnaire | View Questionnaire |
Regional Goods Movement Questionnaire | View Questionnaire |
Resiliency and State of Good Repair Questionnaire | View Questionnaire |
Transit Questionnaire | View Questionnaire |
Project ID | 1236 |
Agency Name | Montrose TIRZ 27 Redevelopment Authority |
Project Title | Waugh Drive Bike Lane |
Facility/Street/Highway | Waugh Drive |
Limits | Allen Parkway to West Dallas Street |
Description | Remove one travel lane in each direction to install protected on-street bicycle lanes on both side of the roadway. Replace undersized sidewalks on both sides of the roadway where feasible. This project will tie into existing bicycle lanes on Waugh Drive south of West Dallas Street. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $1,335,000.00 |
Project ID | 1237 |
Agency Name | Montrose TIRZ 27 Redevelopment Authority |
Project Title | Montrose Safe Routes to School Connections |
Facility/Street/Highway | Various streets near the Wharton Dual Language Academy, Carnegie Vangard High School, and Gregory-Lincoln Education Center |
Limits | - West Clay Street (Eberhard St to Stanford St) - Columbus Street (West Dallas St to West Gray St) - West Bell Street (Eberhard St to Marconi St) - Marconi Street (W Clay St to W Gray St) - West Pierce Street (Eberhard St to Marconi St) - West Dallas Street (Columbus St to Standford St) - Crocker Street (500-feet north of West Gray St to West Gray St) - Stanford Street (West Dallas St to Fairview St) - West Gray Street (Montrose Blvd to Taft St) - Peden Street (Montrose Blvd to Taft St) - Taft Street (W Gray St to Fairview St) - Bomar Street (Stanford St to Taft St) |
Description | Improve safety and provide safe routes to neighborhood schools. To include replacing existing sidewalks with six-foot-wide sidewalks to meet current City standards; installation of three regtangular rapid flashing beacons on West Gray Street in crash-prone area. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $7,000,000.00 |
Project ID | 1238 |
Agency Name | Near Northwest Management District |
Project Title | West Little York Phase 2 Project |
Facility/Street/Highway | W. Little York Rd / Victory Drive |
Limits | Chateau Forest Drive to TC Jester Blvd |
Description | Construct intersection crossing improvements, install six-foot sidewalks, pavement markings, ADA-compliant ramps. Provide universally accessible transit stops and shelters. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $11,300,000.00 |
Project ID | 1239 |
Agency Name | Near Northwest Management District |
Project Title | Alabonson Rd Reconstruction |
Facility/Street/Highway | Alabonson Rd |
Limits | Gum Grove Lane to N Houston Rosslyn |
Description | Reconstruct roadway to include additional capacity for turning movements, full depth rehabilitation of roadway, and provision of shared use path, pavement markings, and ADA-compliant ramps. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $16,100,000.00 |
High Growth Area Needs Questionnaire | View Questionnaire |
Operational Improvements and Congestion Management Questionnaire | View Questionnaire |
Resiliency and State of Good Repair Questionnaire | View Questionnaire |
Project ID | 1240 |
Agency Name | Near Northwest Management District |
Project Title | De Soto Bicycle-Pedestrian Access |
Facility/Street/Highway | De Soto St / TC Jester Blvd |
Limits | Antoine Dr to TC Jester / De Soto St to Holder Forest Dr |
Description | Construct intersection crossing improvements, install six-foot sidewalks and/or eight-foot wide shared use path improvements, pavement markings, ADA-compliant ramps. Provide universally accessible transit stops and shelters. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $6,200,000.00 |
Project ID | 1241 |
Agency Name | Near Northwest Management District |
Project Title | TC Jester Pinemont Pedestrian-Transit Improvements |
Facility/Street/Highway | TC Jester Blvd / Pinemont Dr |
Limits | W Tidwell to Pinemont / Antoine to TC Jester |
Description | Construct intersection crossing improvements, install six-foot sidewalks, pavement markings, ADA-compliant ramps. Provide universally accessible transit stops and shelters. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $2,900,000.00 |
Project ID | 1242 |
Agency Name | Near Northwest Management District |
Project Title | Breen Drive Reconstruction |
Facility/Street/Highway | Breen Dr |
Limits | Western District Boundary (Appx. Hollister) to W Montgomery Rd |
Description | Reconstruct roadway to new section which includes two travel lanes, one continuous center turn later, and six-foot wide sidewalks. Project scope will include stormwater improvements. |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $23,000,000.00 |
Project ID | 1243 |
Agency Name | Southwest Houston Redevelopment Authority (TIRZ 20) |
Project Title | Harwin Dr Reconstruction |
Facility/Street/Highway | Harwin Dr |
Limits | S Gessner Rd - Fondren Rd |
Description | Replace all public infrastructure (road diet, utilities, traffic controls, pedestrian realm) |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $18,200,000.00 |
Regional Goods Movement Questionnaire | View Questionnaire |
Project ID | 1244 |
Agency Name | Upper Kirby Management District (Harris County Improvement District #1) |
Project Title | West Alabama Complete Street |
Facility/Street/Highway | West Alabama Street |
Limits | Buffalo Speedway to Chenevert |
Description | Reconstruct and reconfigure West Alabama from Buffalo Speedway to Chenevert to include modifying the existing cross-section to include continuous bicycle and pedestrian facilities. Enhance access to transit by connecting to adjacent high capacity routes (University Line & Westheimer). Include stormwater, wastewater, and water improvements. Project is only seeking funding for FTA-eligible infrastructure elements. Total Eligible Cost: $31,000,000 |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $31,000,000.00 |
Project ID | 1245 |
Agency Name | Uptown Houston District |
Project Title | West Loop Shared Use Path and Bayou Bridge |
Facility/Street/Highway | Woodway Dr / LP 610 |
Limits | Woodway Dr @ LP 610 to Post Oak Boulevard @ LP 610 |
Description | Provide multimodal shared use path connection from Woodway Drive to Post Oak Boulevard. Includes new bridge crossing at Buffalo Bayou. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $17,000,000.00 |
Project ID | 1246 |
Agency Name | Westchase Management District |
Project Title | Meadowglen West Complete Streets |
Facility/Street/Highway | Meadowglen Ln |
Limits | Woodland Park Dr to Rogerdale Rd |
Description | Repurpose road as a complete street through complete rehabilitation. Final product will include pedestrian-transit and bicycle amenities. Safety improvements incorporated through bulbouts and intersection improvements. Only funding for FTA-eligible items is sought. Total eligible project cost: $10,000,000 |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $10,000,000.00 |
Project ID | 1247 |
Agency Name | North Houston District |
Project Title | Wayforest to Seminar Safety & Access Improvements (Cancelled) |
Facility/Street/Highway | Wayforest Drive |
Limits | Regional Park Drive to Seminar Drive |
Description | Multi-use sidepath to be a minimum of 10’ wide on the east side of the corridor from Regional Park Drive to Seminar Drive and improve intersections to be ADA compliant with curb cuts and crossing signage and striping where appropriate. Improve curb cuts and pedestrian refuges at Wayforest Drive @ Greens Road intersection to be ADA compliant, restripe with high visibility crosswalks, and improve pedestrian signal timing. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $775,500.00 |
Project ID | 1249 |
Agency Name | PORT OF HOUSTON AUTHORITY/TxDOT Beaumont District |
Project Title | IH 10 E Widening |
Facility/Street/Highway | IH 10 E |
Limits | HARRIS C/L TO SH 99 |
Description | RECONSTRUCT AND WIDEN FROM 8 TO 12 LANE (ADD 4 MANAGED LANES) - Safety, operational and mobility improvements to IH 10 E mainlanes and frontage roads, based on results of the IH 10 East PEL study |
Timeframe | Long Term (More than 10 Years) |
Estimated Cost | $200,000,000.00 |
Project ID | 1252 |
Agency Name | Harris County Engineering |
Project Title | East Richey Rd Improvement Project |
Facility/Street/Highway | E Richey Road |
Limits | I45 NBFR to Grovedale Rd |
Description | Safety improvements, access management, driveways, sidewalks and improved street geometry. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $6,100,000.00 |
Regional Goods Movement Questionnaire | View Questionnaire |
Project ID | 1256 |
Agency Name | Montgomery County Precinct 4 |
Project Title | Gene Campbell Boulevard |
Facility/Street/Highway | Gene Campbell Boulevard |
Limits | FM 1314 to FM 1485 |
Description | Reconstruct 2-lane asphalt roadway with open ditches to a 4-lane asphalt roadway with open ditches and a center turn lane. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $35,712,720.00 |
Regional Goods Movement Questionnaire | View Questionnaire |
Project ID | 1263 |
Agency Name | Greater Southeast Management District |
Project Title | Cleburne Street Cap and NHHIP Impact Mitigation |
Facility/Street/Highway | Cleburne Street at IH-69, Almeda Road at IH-69, Alabama St at IH-45 |
Limits | Cleburne St. at IH-69, Almeda Road at IH-69, Alabama St. at IH-45, Elgin at IH-45, Tuam at IH-45, McGowen at IH-45 |
Description | Enable implementation of connectivity, green space, and community connections as associated with NHHIP Project. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $50,000,000.00 |
High Growth Area Needs Questionnaire | View Questionnaire |
Resiliency and State of Good Repair Questionnaire | View Questionnaire |
Project ID | 1264 |
Agency Name | Memorial Heights Redevelopment Authority |
Project Title | Waugh Shared Use Path and Jackson Hill Bike/Ped Bridge Replacement |
Facility/Street/Highway | Memorial/Waugh Cloverleaf and Jackson Hill Street |
Limits | Feagan Street to Jackson Hill/Cleveland Park to Buffalo Bayou Hike and Bike Trail |
Description | A 12' shared use path along the Waugh/Memorial cloverleaf to Jackson Hill Street and Cleveland Park. Project includes the replacement of the Jackson Hill bridge over Memorial Drive. In total, the project is slightly more than a half-mile. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $5,000,000.00 |
Project ID | 1265 |
Agency Name | METRO |
Project Title | Test Project |
Facility/Street/Highway | VA |
Limits | Within defined zone |
Description | Shuttle service within selected communities that lack convenient access to transit $12 million/annually ($4 million/annually each) |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $60,000,000.00 |
Project ID | 1266 |
Agency Name | TxDOT Houston District |
Project Title | Test Project |
Facility/Street/Highway | 36A |
Limits | From IH 10 W to US 290 /SH 6 near Hempstead |
Description | Preliminary engineering study in preparation for a possible DEIS |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $7,500,000.00 |
Project ID | 1267 |
Agency Name | Fort Bend County Public Transportation |
Project Title | Test Project |
Facility/Street/Highway | 3737 Bamore Rd Rosenberg, TX |
Limits | |
Description | Bus support equipment and facilities, transit software, hardware and bus wraps FY2020. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $1,281,000.00 |
Project ID | 1268 |
Agency Name | METRO |
Project Title | Replacement Buses FY '23 |
Facility/Street/Highway | METRO Service Area |
Limits | METRO Service Area |
Description | Replace 160 2008-2009 Diesel Hybrid Buses with new Diesel Buses |
Timeframe | 1 - Short Term (0-5 Years) |
Estimated Cost | $115,080,000.00 |
Project ID | 1270 |
Agency Name | City of Sugar Land |
Project Title | Ditch H Trail - Sugar Land Trail Phase 1 and 2 |
Facility/Street/Highway | |
Limits | |
Description | |
Timeframe | |
Estimated Cost | $0.00 |
Project ID | 1271 |
Agency Name | City of Houston |
Project Title | West Belt Railroad Grade Separations |
Facility/Street/Highway | |
Limits | |
Description | |
Timeframe | |
Estimated Cost | $0.00 |
Project ID | 1272 |
Agency Name | City of Missouri City |
Project Title | Installation of new Mast Arm Traffic Signal |
Facility/Street/Highway | |
Limits | |
Description | |
Timeframe | |
Estimated Cost | $0.00 |
Project ID | 1273 |
Agency Name | The Woodlands Township |
Project Title | SH 242 Pathway |
Facility/Street/Highway | |
Limits | |
Description | |
Timeframe | |
Estimated Cost | $0.00 |
Project ID | 1289 |
Agency Name | City of Houston |
Project Title | Broadway St from IH-45 to SH-225 (Paving & Drainage) |
Facility/Street/Highway | Broadway St |
Limits | IH-45 to SH-225 |
Description | Total roadway reconstruction to include shared paths, intersection & accessibility improvements, railroad safety improvements, upgraded Hawk signals for safer schoool crossings, drainage improvements, traffic signal & street lighting upgrades, access management & roadway reconfiguration with wider median to accommodate future Metro LRT |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $45,000,000.00 |
Resiliency and State of Good Repair Questionnaire | View Questionnaire |
Project ID | 1303 |
Agency Name | Montgomery County |
Project Title | FM 1486 Widening |
Facility/Street/Highway | FM 1486 |
Limits | FM 1774 to SH 105 |
Description | Expand FM 1486 from 2-lanes to 4-lane divided |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $240,000,000.00 |
Major Projects Questionnaire | View Questionnaire |
Project ID | 1304 |
Agency Name | Montgomery County |
Project Title | FM 149 Extension |
Facility/Street/Highway | FM 149-A |
Limits | FM 149 to SH 249 Toll Road |
Description | Extend FM 149 from the UPRR (FM 149) to the SH 249 Toll Road. Includes railroad grade separation |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $140,000,000.00 |
Project ID | 1305 |
Agency Name | Montgomery County |
Project Title | FM 149 Widening - South |
Facility/Street/Highway | FM 149 |
Limits | FM 1774 to Jackson Rd |
Description | Expand FM 149 from 2-lanes to 4-lane divided. Includes railroad grade separation |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $150,000,000.00 |
Major Projects Questionnaire | View Questionnaire |
Project ID | 1306 |
Agency Name | Montgomery County |
Project Title | FM 149 Widening - North |
Facility/Street/Highway | FM 149 |
Limits | Jackson Rd to SH 105 |
Description | Expand FM 149 from 2-lanes to 4-lane divided. Includes railroad grade separation |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $160,000,000.00 |
Major Projects Questionnaire | View Questionnaire |
Project ID | 1307 |
Agency Name | Montgomery County |
Project Title | I-45 Ramp Improvements |
Facility/Street/Highway | IH 45 |
Limits | SH 99 to Woodlands Parkway |
Description | Construct braided ramps at the Hardy Toll Interchange. Modify ramps between SH 99 and Woodlands Parkway. Add auxilliary lanes |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $150,000,000.00 |
Major Projects Questionnaire | View Questionnaire |
Project ID | 1308 |
Agency Name | Montgomery County |
Project Title | Keenan Cutoff Extension |
Facility/Street/Highway | Keenan Cutoff Rd |
Limits | SH 249 Toll Road to FM 149 |
Description | Extend Keenan Cutoff Rd from FM 149 to the SH 249 Toll Road. Includes two railroad grade separations and a new crossing of Lake Creek |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $230,000,000.00 |
Major Projects Questionnaire | View Questionnaire |
Project ID | 1309 |
Agency Name | Montgomery County |
Project Title | SH 99 Eastbound Frontage Road Improvements |
Facility/Street/Highway | SH 99 Eastbound Frontage Road |
Limits | Rayford to east of Birnam Woods |
Description | Add frontage road lanes (one-lane to two-lane) and add right turn lanes |
Timeframe | |
Estimated Cost | $3,000,000.00 |
High Growth Area Needs Questionnaire | View Questionnaire |
Project ID | 1310 |
Agency Name | Montgomery County |
Project Title | FM 2090 Expansion |
Facility/Street/Highway | FM 2090 |
Limits | FM 3083 to I 69 |
Description | Expand FM 2090 from 2-lanes to 4-lane divided. Re-alignment to meet current criteria |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $280,000,000.00 |
Major Projects Questionnaire | View Questionnaire |
Project ID | 1311 |
Agency Name | Montgomery County |
Project Title | FM 1097 Realignment |
Facility/Street/Highway | FM 1097 |
Limits | Bentwater to FM 149 |
Description | Expand from 2-lanes to 4-lane divided. Realign roadway to meet FM 1097 west of FM 149 |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $170,000,000.00 |
Major Projects Questionnaire | View Questionnaire |
Project ID | 1312 |
Agency Name | Montgomery County |
Project Title | FM 2854 Expansion |
Facility/Street/Highway | FM 2854 |
Limits | Loop 336 to SH 105 |
Description | Expand from 2-lanes to 4-lane divided. |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $390,000,000.00 |
Major Projects Questionnaire | View Questionnaire |
Project ID | 1313 |
Agency Name | Montgomery County |
Project Title | FM 2432 Expansion |
Facility/Street/Highway | FM 2432 |
Limits | SH 75 to FM 1484 |
Description | Expand from 2-lanes to 4-lane divided. Includes Railroad grade separation |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $150,000,000.00 |
Major Projects Questionnaire | View Questionnaire |
Project ID | 1314 |
Agency Name | Montgomery County |
Project Title | FM 1485 Expansion |
Facility/Street/Highway | FM 1485 |
Limits | Lp 494 to SH 99 |
Description | Expand from 2-lanes to 4-lane divided. |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $95,000,000.00 |
Major Projects Questionnaire | View Questionnaire |
Project ID | 1315 |
Agency Name | Montgomery County |
Project Title | SH 99 Ramp Improvements |
Facility/Street/Highway | SH 99 |
Limits | At Valley Ranch Pkwy |
Description | Add WB off ramp and an EB on ramp |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $12,000,000.00 |
High Growth Area Needs Questionnaire | View Questionnaire |
Project ID | 1316 |
Agency Name | TxDOT Houston District |
Project Title | FM 1485 AMS Phase 1 of 3 |
Facility/Street/Highway | FM 1485 |
Limits | From SL 494 to SH 242 |
Description | FM 1485 Access Management Study Short Term Recommendations Implementation (Phase 1) |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $5,688,003.00 |
Operational Improvements and Congestion Management Questionnaire | View Questionnaire |
Project ID | 1317 |
Agency Name | TxDOT Houston District |
Project Title | FM 1485 AMS Phase 2 of 3 |
Facility/Street/Highway | FM 1485 |
Limits | From SL 494 to SH 242 |
Description | FM 1485 Access Management Study Medium Term Recommendations Implementation (Phase 2) |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $6,129,385.00 |
Operational Improvements and Congestion Management Questionnaire | View Questionnaire |
Project ID | 1318 |
Agency Name | TxDOT Houston District |
Project Title | FM 1485 AMS Phase 3 of 3 |
Facility/Street/Highway | FM 1485 |
Limits | From SL 494 to SH 242 |
Description | FM 1485 Access Management Study Long Term Recommendations Implementation (Phase 3) |
Timeframe | Long Term (More than 10 Years) |
Estimated Cost | $24,789,388.00 |
High Growth Area Needs Questionnaire | View Questionnaire |
Operational Improvements and Congestion Management Questionnaire | View Questionnaire |
Project ID | 1319 |
Agency Name | TxDOT Houston District |
Project Title | FM 1314 AMS Phase 1 of 3 |
Facility/Street/Highway | FM 1314 |
Limits | From SL 494 to SH 242 |
Description | FM 1314 Access Management Study Short Term Recommendations Implementation (Phase 1) |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $3,340,000.00 |
High Growth Area Needs Questionnaire | View Questionnaire |
Operational Improvements and Congestion Management Questionnaire | View Questionnaire |
Project ID | 1320 |
Agency Name | TxDOT Houston District |
Project Title | FM 1314 AMS Phase 2 of 3 |
Facility/Street/Highway | FM 1314 |
Limits | From SL 494 to SH 242 |
Description | FM 1314 Access Management Study Medium Term Recommendations Implementation (Phase 2) |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $5,700,000.00 |
High Growth Area Needs Questionnaire | View Questionnaire |
Operational Improvements and Congestion Management Questionnaire | View Questionnaire |
Project ID | 1321 |
Agency Name | TxDOT Houston District |
Project Title | FM 1314 AMS Phase 3 of 3 |
Facility/Street/Highway | FM 1314 |
Limits | From SL 494 to SH 242 |
Description | FM 1314 Access Management Study Long Term Recommendations Implementation (Phase 3) |
Timeframe | Long Term (More than 10 Years) |
Estimated Cost | $87,560,000.00 |
High Growth Area Needs Questionnaire | View Questionnaire |
Operational Improvements and Congestion Management Questionnaire | View Questionnaire |
Project ID | 1322 |
Agency Name | Harris County Engineering |
Project Title | Sheldon Road (South) Reconstruction Project |
Facility/Street/Highway | Sheldon Road - Resilience |
Limits | Wallisville Rd to Jacintoport Blvd |
Description | Reconstruct and widen, reconstructing and widening the existing two-lane road with a concrete overlay and asphalt surface to create a four-lane roadway made of reinforced 12-inch concrete. The project encompasses a bridge section, two major thoroughfare intersections, multiple entrances for industrial and commercial businesses, drainage enhancements, sidewalk installation, and landscaping. These improvements will alleviate congestion, enhance safety in the area, improve pedestrian accessibility, address drainage issues, and optimize the transportation system's resilience during severe weather events. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $50,000,000.00 |
Resiliency and State of Good Repair Questionnaire | View Questionnaire |
Project ID | 1323 |
Agency Name | Harris County Engineering |
Project Title | Barker Cypress Road Capacity and Safety Improvements |
Facility/Street/Highway | Barker Cypress Road - HGAN |
Limits | From: Queenston BlvdTo: North of US 290 |
Description | The proposed project, which is primarily in existing right of way, widens Barker Cypress Road from four to six lanes, converting it from a four-lane asphalt section with open ditch drainage to a six-lane concrete urban section with curb-and-gutter including added sidewalks; the project includes reconstruction of the bridge over the railroad and intersection improvements along Barker Cypress Road at Queenston Boulevard, US 290 eastbound and westbound frontage roads. The improvements will reduce congestion, increase safety in the area, improve pedestrian accommodations, improve drainage due to modernizing the roadway to include curbs and gutters, reduce vehicular emissions attributable to severe traffic congestion, and decrease the travel delays for the Barker Cypress Corridor. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $60,000,000.00 |
High Growth Area Needs Questionnaire | View Questionnaire |
Operational Improvements and Congestion Management Questionnaire | View Questionnaire |
Resiliency and State of Good Repair Questionnaire | View Questionnaire |
Project ID | 1324 |
Agency Name | Harris County Engineering |
Project Title | Sweetwater Lane Reconstruction Project |
Facility/Street/Highway | Sweetwater Lane |
Limits | West Mount Houston to West Canino Road |
Description | Reconstruct Sweetwater Lane into a curb and gutter concrete roadway, including construction of new sidewalks, streetlights, in-line drainage, traffic signals, widen bridge over Halls Bayou, and other access management improvements to improve safety and connectivity. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $30,000,000.00 |
Resiliency and State of Good Repair Questionnaire | View Questionnaire |
Project ID | 1325 |
Agency Name | Harris County Engineering |
Project Title | Harris County Precinct 1 Traffic Signal Intersection Improvement Project |
Facility/Street/Highway | Various |
Limits | Nineteen (19) intersection locations (See "PCT1 Traffic Signal Intersectio" Tab) |
Description | The proposed project focuses on critical traffic signal and intersection improvements in Precinct 1 at 19 intersection locations. The project will improve signal operations, safety and connectivity, and will reduce traffic congestion and vehicular emissions. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $12,350,000.00 |
Operational Improvements and Congestion Management Questionnaire | View Questionnaire |
Project ID | 1326 |
Agency Name | City of Webster |
Project Title | Flyway Drive Extension |
Facility/Street/Highway | Flyway Drive |
Limits | Project limits extend from the eastern termination of Flyway Drive, eastward, across the CenterPoint corridor and ExxonMobil property, just north of Clear Creek, to terminate at SH3. |
Description | Approximately 3,400 LF of two-lane concrete pavement provides an alternate east-west route between SH3 and IH45, between FM518 and NASA Parkway. The Flyway Drive extension is instrumental to tourism support and economic competiveness, enhancing accessibility to a major hotel (Great Wolf Lodge), entertainment hub (Flyway), and adjacent commerce (Axiom Space, American Furniture Warehouse, Academy, Top Golf, and other retail and restaurant development). |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $2,500,000.00 |
Project ID | 1327 |
Agency Name | Houston Airport System |
Project Title | Ellington Road Extension |
Facility/Street/Highway | State Highway, Enterprise Shuttle Street and Space Center Blvd. |
Limits | State Highway 3 to Enterprise Shuttle Street and Space Center Blvd. |
Description | Improved roadway access and utility infrastructure connectivity to the Houston Spaceport |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $45,000,000.00 |
Project ID | 1328 |
Agency Name | Fort Bend County |
Project Title | E Dallas St Widening |
Facility/Street/Highway | E Dallas Street |
Limits | FM 521 to county line |
Description | Widening of existing 2-lane undivided asphalt roadway to 4-lane divided concrete Blvd. with roadside ditches and storm sewer. |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $14,200,000.00 |
High Growth Area Needs Questionnaire | View Questionnaire |
Operational Improvements and Congestion Management Questionnaire | View Questionnaire |
Project ID | 1329 |
Agency Name | Fort Bend County |
Project Title | SH 99 Frontage Rd (20301) |
Facility/Street/Highway | SH 99 |
Limits | SB Cinco Ranch Blvd to Bay Hill |
Description | Construction of a two lane concrete curb and gutter frontage road and SH 99 Ram reversal. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $8,600,000.00 |
High Growth Area Needs Questionnaire | View Questionnaire |
Operational Improvements and Congestion Management Questionnaire | View Questionnaire |
Project ID | 1330 |
Agency Name | Brazoria County |
Project Title | CR 59 widening |
Facility/Street/Highway | County Road 59 |
Limits | from the Fort Bend County Line to CR 48 |
Description | Widening existing 2-lane asphalt roadway to a 4-lane concrete Blvd. with roadside ditches, storm sewer and a detention pond. |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $20,000,000.00 |
High Growth Area Needs Questionnaire | View Questionnaire |
Operational Improvements and Congestion Management Questionnaire | View Questionnaire |
Resiliency and State of Good Repair Questionnaire | View Questionnaire |
Project ID | 1331 |
Agency Name | Harris County Transit Services |
Project Title | Sidewalk and Pedestrian Access |
Facility/Street/Highway | Unincorporated Harris County |
Limits | Unincorporated Harris County |
Description | Harris County Transit Services is will be installing sidewalks in unincorporated Harris County. Particularly, we will be focusing on areas where existing bus routes exist. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $4,000,000.00 |
Project ID | 1332 |
Agency Name | Galveston Wharves |
Project Title | 145 Direct Connect Engineering |
Facility/Street/Highway | I45 at Harborside to Harboside at Port |
Limits | |
Description | Engineering for I45 Direct Connect, project funded for preengineering already |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $13,000,000.00 |
High Growth Area Needs Questionnaire | View Questionnaire |
Major Projects Questionnaire | View Questionnaire |
Operational Improvements and Congestion Management Questionnaire | View Questionnaire |
Resiliency and State of Good Repair Questionnaire | View Questionnaire |
Project ID | 1333 |
Agency Name | Galveston Wharves |
Project Title | OPI 41st-51st Engineering |
Facility/Street/Highway | Old Port Industrial Road 41st- 51st |
Limits | |
Description | Enginerring for OPI 41st-51st, project funded for preengineering already |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $3,000,000.00 |
High Growth Area Needs Questionnaire | View Questionnaire |
Major Projects Questionnaire | View Questionnaire |
Operational Improvements and Congestion Management Questionnaire | View Questionnaire |
Resiliency and State of Good Repair Questionnaire | View Questionnaire |
Project ID | 1334 |
Agency Name | Galveston Wharves |
Project Title | Wayfinding |
Facility/Street/Highway | Port wide |
Limits | |
Description | Port wide design and construction signage consistent across port |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $1,600,000.00 |
High Growth Area Needs Questionnaire | View Questionnaire |
Operational Improvements and Congestion Management Questionnaire | View Questionnaire |
Project ID | 1335 |
Agency Name | Galveston Wharves |
Project Title | Parking to Terminal 25 Overhead walkway |
Facility/Street/Highway | |
Limits | |
Description | Construct pedestrian overhead walkway to go fro terminal 25 to parking lots A, B, C, D |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $4,000,000.00 |
High Growth Area Needs Questionnaire | View Questionnaire |
Operational Improvements and Congestion Management Questionnaire | View Questionnaire |
Project ID | 1336 |
Agency Name | Galveston Wharves |
Project Title | Intersection Harborside and 37th improvments |
Facility/Street/Highway | State High275 at 37th street |
Limits | |
Description | Intersection Harborside and 37th street traffic light and rail track improvments |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $2,500,000.00 |
High Growth Area Needs Questionnaire | View Questionnaire |
Operational Improvements and Congestion Management Questionnaire | View Questionnaire |
Resiliency and State of Good Repair Questionnaire | View Questionnaire |
Project ID | 1337 |
Agency Name | City of Bellaire |
Project Title | Reconstruction of Chimney Rock Rd |
Facility/Street/Highway | Chimney Rock Road |
Limits | Evergreen to Maple |
Description | The Chimney Rock Rd reconstruction project includes roadway and intersection improvements for enhanced mobility as well as storm drainage improvements to provide for increased access before, during, and after major events as well as improve regional flood resilience |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $9,300,000.00 |
Resiliency and State of Good Repair Questionnaire | View Questionnaire |
Project ID | 1338 |
Agency Name | City of Bellaire |
Project Title | Reconstruction of Newcastle Drive |
Facility/Street/Highway | Newcastle Drive |
Limits | Glenmont to Cypress Ditch Bridge |
Description | The Newcastle Dr reconstruction project includes roadway and intersection improvements for enhanced mobility as well as storm drainage improvements to provide for increased access before, during, and after major events as well as improve regional flood resilience |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $19,200,000.00 |
Resiliency and State of Good Repair Questionnaire | View Questionnaire |
Project ID | 1339 |
Agency Name | City of Bellaire |
Project Title | Reconstruction of S. Rice Ave |
Facility/Street/Highway | South Rice Avenue |
Limits | Elm to Cypress Ditch Bridge |
Description | The S Rice Ave reconstruction project includes roadway and intersection improvements for enhanced mobility as well as storm drainage improvements to provide for increased access before, during, and after major events as well as improve regional flood resilience |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $28,800,000.00 |
Resiliency and State of Good Repair Questionnaire | View Questionnaire |
Project ID | 1340 |
Agency Name | Test Agency |
Project Title | Pearland Parkway extension |
Facility/Street/Highway | Pearland Parkway |
Limits | from Dixie Farm to FM 2351 |
Description | Extend Pearland Parkway from Dixie Farm Road to FM 2351 (as a four-lane, median divided roadway) to improve mobility within Brazoria County and provide an additional north/south route parallel to SH 35 to reduce congestion. |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $35,000,000.00 |
Project ID | 1341 |
Agency Name | Test Agency |
Project Title | CR 100 extension |
Facility/Street/Highway | County Road 100 |
Limits | from CR 113 to SH 35 |
Description | Construct 2-lane roadway and 2-lane grade separation crossing at existing railroad. |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $16,600,000.00 |
Project ID | 1342 |
Agency Name | Test Agency |
Project Title | CR 64 widening (both east and west – but east is mostly City) - Medium Term |
Facility/Street/Highway | County Road 64 |
Limits | from SH 288 to CR 65 |
Description | Construct 10-foot shoulders along CR 64 from SH 288 to CR 65 to offset fixed objects from the travel way. |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $2,976,000.00 |
Project ID | 1343 |
Agency Name | H-GAC |
Project Title | Kirby Drive Extension |
Facility/Street/Highway | Street |
Limits | Holmes Rd. to Sam Houston Tollway South |
Description | Proposed Kirby Dr. is a multimodal thoroughfare consisiting of 3 segments: Segment 1 - construct a 4-lane from Holmes Rd. to Airport Blvd. with grade separation at Almeda Rd., Segment 2 - construct a bridge crossing Sims Bayou connecting to W. Orem Dr., Segment 3 - construct a 4-lane from Nichol Woods Dr. to Sam Houston Tollway South. Kirby Dr. is designated as a transit corridor from Fannin terminus at Feldman St. (west of Almeda Rd) to Airport Blvd. |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $110,000,000.00 |