Who is Completing the Application?

Please provide contact information for the person who will complete the online application for this project. The email address and password entered here will be used to complete and submit both Pre-Applications and Applications.

Maureen Crocker

Assistant Director

832-395-3222

[email protected]

Primary Agency Information

Please provide contact information for the agency official who is representing the project sponsor. This individual will be considered the official applicant and must be authorized by their agency to submit this request for funding and make necessary assertations and representations on the agency’s behalf.

City of Houston -Houston Public Works

Maureen Crocker

Assistant Director

832-395-3222

[email protected]

611 Walker

Houston

TX

77002

Additional Agency Information

Fort Bend County

Grady Prestage

County Commissioner Pct 2

281-342-3411

[email protected]

301 Jackson St., 4th Floor, Richmond, TX 77469

Richmond

TX

77469

Project Information

West Fuqua Street

Harris County

West Fuqua Street

City Limits to Chimney Rock Road

Summary of Problems: • Need for intersection improvements and turn lane storage • Need for safe pedestrian crossings and wider sidewalks • Need for signalized intersection The existing concrete pavement is in fair condition; however there are damaged curbs and failing panels throughout the corridor. The pedestrian facilities, including ramps, sidewalks, and bus shelters, are generally in poor condition. Sidewalks are cracked, broken, and uneven creating a safety issue. The need for safe pedestrian crossings and wider sidewalks for neighboring schools (Briargate Elementary, Southern Preparatory Academy, and Hunter Glen Elementary) and public library (Stimley Blue Ridge library) that feed into the corridor. Street and Traffic needs identification was evaluated based on the physical condition and capacity of the roadway. The pavement is over 40 years old and shows wide cracks, failure at joints, and numerous asphalt patches. Pedestrian mobility and safety are lacking with sidewalks in poor condition and lack of wheelchair ramps at cross streets and ADA compliance.

Proposed Improvements include: • New traffic signal at Ridgecreek and stop sign at Ridgerock. • Turning bays at median openings and turn lanes at new signalized intersections • Relocate and improve Metro Bus Stops along the corridor to optimize traffic operations. • Implement access management/driveway spacing to minimize conflicts and improve access to various developments along the corridor. • Reconstruction of roadway with new pavement and lane width standard

-Improve pedestrian safety with wider sidewalks and ADA compliant ramps/crosswalks. -Improve intersection safety and throughput with turn lanes, new signals and median turn lanes. -Improve pavement condition and ride quality Improve water and wastewater utilities. -Improve storm drainage to convey design and extreme event. Project will replace the street that is beyond repair and normal maintenance and also bring to current lane width standard. The project will also upgrade existing underground water, wastewater, and storm utilities.

No

No

Less than $100 million

(Maintain) Roadway/Freight Rehabilitation/Reconstruction

13806000

Support_letter.zip

Project Development/Readiness

30% PS&E

Categorical Exclusion (CE)

03/27/2020

No

No

No

Yes

No

No

No

City of Houston conducted a pre-engineering study on this corridor. The project is currently in design. See attached report.

W. Fuqua Final Reports.zip

Map/Location

Fuqua_map2.pdf

Project Budget

project-budget-fuqua.xlsx

No

Benefit/Cost Analysis

Roadway-Safety-Benefits- Fuqua.xlsx

1031201814833PM.xlsx

Roadway-Emissions-Benefits- Fuqua.xlsx

Regional Employment_Fuqua.JPG

TIP Resolution 2018-0035.pdf

Fuqua Road is being submitted under the Rehab/Reconstruction category. The project improvement will provide benefit by install pedestrian crosswalks, turn lanes at intersections and turn bays in medians, new traffic signal, and stop sign.

Planning Factors - Connectivity to Employment/Eliminates At-Grade Railroad Crossings

Yes

901 - 1000

No

Planning Factors - Environmental Justice

Yes

Yes

Planning Factors - Resiliency/Flood Mitigation Strategies

Yes

The reconstruction of W. Fuqua will included upgraded storm sewer system that will reduce street ponding during heavy storm events; maintaining mobility for transit, and area residents. Fuqua also is a direct connector to Beltway 8 and Fort Bend Toll Road which is an evacution connector, and major roadway on the freight system network.

Planning Factors - Improves Multimodal LOS

No

Yes

Yes

Project will improve pedestrian LOS with wider and safer sidewalks by replacing broken/uneven sidewalks and installing ADA compliant ramps and crosswalks. Transit LOS will be improved with new roadway surface and improved drainage system to reduce street ponding.

Planning Factors - Planning Coordination

Yes

City of Houston Major Thoroughfare and Freeway Plan

https://www.houstontx.gov/planning/transportation/MTFP.html

Planning Factors - Roadway Hierarchy/Freight System Priority/Evacuation Route

Collector

No

No

No

Yes