Who is Completing the Application?

Please provide contact information for the person who will complete the online application for this project. The email address and password entered here will be used to complete and submit both Pre-Applications and Applications.

Megan Campbell

Planner

713-802-5325

[email protected]

Primary Agency Information

Please provide contact information for the agency official who is representing the project sponsor. This individual will be considered the official applicant and must be authorized by their agency to submit this request for funding and make necessary assertations and representations on the agency’s behalf.

Texas Department of Transportation - Houston

Quincy Allen

District Engineer

713-802-5000

[email protected]

7600 Washington Avenue

Houston

TX

77007

Additional Agency Information

Project Information

FM 2920 Widening

Harris County

FM 2920

BS 290 to Rosehill Rd.

The proposed FM 2920 improvement project includes widening the existing two-lane undivided roadway to a proposed four-lane divided roadway from BU 290 to Cypress Rosehill, and widening from the existing four-lane divided roadway to a proposed six-lane divided roadway from Cypress Rosehill Road to SH 249. Current and projected growth in the area has caused traffic demand to increase within the corridor. As a result, the current roadway does not provide adequate mobility to accommodate population growth or alleviate congestion. In addition, there has been an increase in serious traffic crashes along the project corridor. The facility had 213 crashes and 10 serious injuries from 2015 to 2017. Congestion on the facility results in roughly 2,672 vehicle hours of delay per day. Improving congestion on this facility could save users in excess of 2,613,000 hours of travel time per lane-mile. Congestion is adversely affecting the travel time and reliability for freight movement. The truck volume on the facility is roughly 1,880 trucks per day and this represents 7.0% percent of the facility's AADT.

Widen roadway from 2 to 4 lanes

The purpose of the proposed project is to improve traffic flow, mobility, safety, and improve the reliability of peak-period travel times and travel time reliability for freight movement. The proposed design also identified intersections which could be realigned on new location to improve design deficiencies. In addition, the proposed design would accommodate bicycles and pedestrian facilities.

No

Yes

2941-01-026

Less than $100 million

(Expand) Roadway Added Capacity/New Construction/Complete Streets

77360000

TXDOT_HOU_HGAC2018CFP.PDF

Project Development/Readiness

30% PS&E

Environmental Assessment (EA)

06/01/2020

Yes

No

No

No

Yes

12/01/2020

06/01/2021

06/01/2023

50

0

No

No

Anticipated US Army Corps of Engineers Permits: Individual Permit (IP) 2941-01-028 and 2941-01-026 could be phased with 2941-01-028 first phase.

Map/Location

Map_HOU_45_HW_FM2920.pdf

Project Budget

HOU_45_HW_FM2920 Project Budget Worksheet.xlsx

No

Benefit/Cost Analysis

HOU_45_HW_FM2920 Roadway Safety Benefits Template - Editable.xlsx

10312018125811PM.xlsx

HOU_45_HW_FM2920 Roadway Emissions Benefits Template.xlsx

HOU_45_HW_FM2920_Support.PDF

Planning Factors - Connectivity to Employment/Eliminates At-Grade Railroad Crossings

Yes

901 - 1000

No

Planning Factors - Environmental Justice

Yes

Yes

Planning Factors - Improves Corridor Level of Travel Time Reliability (LOTTR)

0.01 – 0.10

HOU_45_HW_FM2920 Level of Time Travel Reliability LOTTR Estimation Template.xlsx

Planning Factors - Improves Multimodal LOS

Yes

No

Yes

This project adds one lane of capacity in each direction. This project will construct sidewalks, as well as a 15-foot-wide shared-use lane that can accommodate bicyclists.

Planning Factors - Planning Coordination

Yes

Harris County Support Letter

Harris County Support Letter

Planning Factors - Roadway Hierarchy/Freight System Priority/Evacuation Route

Principal Arterial

No

Yes

No

No

route_support.pdf