Please provide contact information for the agency official who is representing the project sponsor. This individual will be considered the official applicant and must be authorized by their agency to submit this request for funding and make necessary assertations and representations on the agency’s behalf.
2123 Market Street
Baytown
TX
77522
Additional Agency Information
Project Information
Cedar Bayou Crossing
Harris County
Unnamed
North Main Street to SH 146
The City of Baytown has only one east/west corridor that takes traffic to SH 146 from the west side of the City. There is a need to connect the residents in Chambers County and Harris County in order to provide congestion relief along SH 146. The lack of east/west connectivity was also immediately evident during the last two hurricanes where our residents had difficulty evacuating.
The proposed improvement is a four-lane boulevard that will extend the existing Hunt Road at North Main Street east to the intersection of Kilgore Parkway at SH 146. The improvement will also include two elevated railroad crossings and a bridge over Cedar Bayou.
The primary outcomes of this project will be: -increased east/west connectivity -additional, local, evacuation routes -congestion relief for the existing north/south corridors
I Don't Know
No
Less than $100 million
(Expand) Roadway Added Capacity/New Construction/Complete Streets
75000000
Project Development/Readiness
Not Started
Environmental Assessment (EA)
04/01/2022
Yes
No
Yes
No
Yes
11/01/2022
12/01/2022
06/01/2024
40
1
No
No
Map/Location
Benefit/Cost Analysis
Roadway-Safety-Benefits-Template (1).xlsx
Roadway-Emissions-Benefits-Template.xlsx
The proposed roadway does not appear in the existing TDM. The values used in the templates were taken from existing facilities in the TDM. The estimated future values were estimated using the base year value and growing the traffic volumes using the compound interest equation. It was assumed that the traffic growth rate between 2018 and 2025 was 3%. The assumed growth rate between 2018 and 2045 was reduced to 2%.
Planning Factors - Connectivity to Employment/Eliminates At-Grade Railroad Crossings
Yes
1 - 500 Jobs
Yes
Planning Factors - Environmental Justice
Yes
Yes
Planning Factors - Improves Corridor Level of Travel Time Reliability (LOTTR)
0.01 – 0.10
Planning Factors - Improves Multimodal LOS
Yes
No
Yes
This new roadway project will connect the east and west sides of Baytown over Cedar Bayou. This will be the first east/west corridor that will cross the bayou and will, therefore become a more desirable route for traffic that must either travel north to IH-10 or south to SH 146 in order to cross Cedar Bayou. The future traffic on the proposed roadway will be siphoned off from the existing north/south corridors which will relieve their congestion and increase the LOS for those roadways. This proposed roadway will also directly increase the LOS for the road users who choose to use the facility because their trips will take less time and distance to complete. The proposed facility will also increase the bike/ped LOS by providing an additional corridor for their travel and exercise.
Planning Factors - Planning Coordination
Yes
State Highway 146 Subregional Study
http://www.hgacmpo.com/sh146/documents/SH146_Report_051418.pdf
Planning Factors - Roadway Hierarchy/Freight System Priority/Evacuation Route
Principal Arterial
No
No
No
Yes