Operational Improvements and Congestion Management Questionnaire
Project Information
Agency Name | Galveston Wharves |
Project Title | 145 Direct Connect Engineering |
Facility/Street/Highway | I45 at Harborside to Harboside at Port |
Limits | |
Description | Engineering for I45 Direct Connect, project funded for preengineering already |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $13,000,000.00 |
Investment Category-Focused Criteria
No
1.5 – 1.75
Three mile stretch of road with multiple rail crossing and converging modes of traffic, speed 35, TTI 1.5-1.75
< 1.0
Travel Time Index: ratio of average peak travel time to an off-peak (free-flow) standard, in this case 60 mph for freeways. would reduce the TTI to < 1 traveling due to congestion.
Technology Waze. ... Revolutionize traffic light management. ... Restrict parking near busy intersections. ... Encourage the use of alternative routes. ... Promote carpooling and ride-sharing.
Yes
Other Investment Category Focused Criteria
No
n/a
n/a
n/a
n/a
n/a
n/a
Planning Factors Criteria
1/336
12/336
n/a
Resiliency
High
High
n/a
Access/Connectivity
19.2%
35.2%
Yes
Yes
No
Environmental Justice
19.2%
35.2%
19.2%
11.6%
19.1%
6.52%
42.292
n/a
n/a
Impacts on Natural and Cultural Resources
n/a
Innovation
Yes
signage
No