Transit Questionnaire
Project Information
Agency Name | City of Mont Belvieu |
Project Title | Public Works & Engineering Director |
Facility/Street/Highway | Eagle Dr. |
Limits | From Fm 565 to SH 146 |
Description | Reconstruction of 2-lane open ditch to 4-lane Blvd with curb and gutter with sidewalks and bikeway. |
Timeframe | Short Term (0-5 Years) |
Estimated Cost | $36,000,000.00 |
Investment Category-Focused Criteria
Yes
https://www.h-gac.com/livable-centers/planning-studies/mont-belvieu
No
No
No
0
The proposed widening project will improve connectivity between the residential areas of the community, and SH-146, a major hurricane evacuation route.
Other Investment Category Focused Criteria
Yes
The proposed improvements will increase the throughput capacity of the existing road, decreasing delays and improving safety. The existing road is expected to reach capacity within the next couple of years. The project will widen FM 3360/ Eagle Dr. from 2 lane undivided to 4 lanes divided with ability to adjust for additional capacity and turn lanes including wider sidewalk or trails with bikers. The intersections of FM 565 and SH 146 will have intersection improvements and upgraded signal technology including adding a fiber connection to the cities MBlink internet system for emergency services. Additional signals or pedestrian crossings will be analyzed and installed for the Riceland Development access to Town Center and City Hall.
The existing condition of the road will not be able to support the demand related to the upcoming growth. The proposed boulevard section will increase the capacity of the roadway, while improving the safety and resiliency of this important roadway segment.
There are currently few walking and biking options in the area. The project will expand the sidewalks and/ or trails network for pedestrians and bikers. The project will provide design for walkers and bikers to get to the new city hall on the westside of Eagle Dr. This will be critical since Riceland development is located mainly on the eastside of Eagle Dr. Project will provide a safer or improved bike/walker route to get to the Town Center area, Riceland area and park area approx. 0.5 mile south of FM 565. The project will also provide an improved connection between the north side of town and the south side of town, decreasing vehicular trips to major destinations on the south side of Mont Belvieu.
Eagle Drive in this area is a vital connection for Mont Belvieu and the adjacent area. Today Eagle Dr is a 2-lane highway undivided with 2' to no shoulders. Adding 4 lanes concrete pavement will help keep traffic moving and provide a relief lane or can provide a traffic pattern change to other side for emergency personnel to keep safe.
Project is currently planned to be concrete curb and gutter providing a long-life span. This will help with future maintenance. Underground storm system will not require cleaning out or scraping ditches every year to maintain a good flow. Additionally, the existing roadway section is reaching the end of its service life.
Planning Factors Criteria
0.1667 (1 in 2023)
0.3333 (2023)
The widening of FM 3360/Eagle Dr will provide a safer drive for future and current residents. The addition of additional through lanes, medians, left turn lanes, median openings/access management improvements, wider sidewalks and bike trails will reduce crash rates for rear end collision for turning vehicles and head on crashes. Having curb and gutters will provide residents and students with safer sidewalks and bike trails, including eliminating the ditches along sidewalks edges.
Resiliency
Low
Low
The project would eliminate the roadside ditches along FM 3360/Eagle Dr. Curb and gutter drainage system will provide a safer system for pedestrians and bikers near the current ditches. An underground drainage system would be added and connected to Mont Belvieu regional system.
Access/Connectivity
1252
931
Yes
Yes
No
Environmental Justice
1252
931
93 (10%)
500 ( 5.1%)
830
1320 (13.1%)
4
Project will provide access to city hall thru improved sidewalks and roadway crossings to pay bills including water, internet and others. It will also improve pedestrian and cyclist access to the livable center that is currently under construction around City Hall. Improvement will also better access to the Barbers Hill schools and Community Parks located south of FM 565 including biking and walking. This project is part of the transportation master plan for the City, which emphasizes pedestrian and cyclist connectivity throughout the entire town and between major destinations.
Project will be constructed and designed inside existing right of way. No additional right of way will be needed along Eagle Dr. The project will not hinder pedestrian or cycling connectivity in any way. Additionally, the proposed boulevard will not create a barrier between different areas of town as it will be walkable and will prioritize connectivity. No poverty areas will be affected but walkable, biking and traffic congestion will be improved.
Impacts on Natural and Cultural Resources
No wetlands or flood plains are located along the proposed project along Eagle Dr from FM 565 to SH 146. Moreover, the project will take place within existing right of way.
0.03 (both)
Innovation
Yes
The south end of the project is where the new Livable Center, updated City Hall, park area, retail, and other businesses will be. Innovative ideas will be implemented for the mobility of pedestrians and cyclists from all parts of town including crossing signals or median bulb-outs for refuge. Technologies will be needed for Riceland Development to connect to City Hall and Livable Center area. The implementation of this project would significantly improve connectivity and congestion while working cohesively with the livable center and the City's ultimate vision of a walkable town.
No
Additional Documents
Approved Riceland Master Plans - Mont Belvieu.pdf
Mont Belvieu Capital Improvements Plan 20182027 2019.03.20.pdf