Transit Questionnaire

Project Information

Agency Name METRO
Project Title Northline TC
Facility/Street/Highway Fulton St.
Limits @ Julia St.
Description Construct new multi-level TC on new location to replace existing Northline TC
Timeframe Short Term (0-5 Years)
Estimated Cost $42,000,000.00

Investment Category-Focused Criteria

Yes

a. The Northline Transit Center (NLTC) is in the 2045 Regional Transportation Plan (MPOID #15549) and 2023-25 Transportation Improvement Plan (TIP).

Yes

a. The proposed NLTC connects local bus, and automobile traffic with METRORail creating a multi-modal center enabling travelers to Downtown to avoid the congested IH 45, as well as allowing customers to connect to transit service serving destinations across the northern part of the service area.

Yes

a. Yes. The NLTC is location and the METRORail Red Line terminal station and will be a multi-modal hub for the community. The NLTC will connect up to four local bus routes and the METRORail Red Line, as well as area drivers via structured parking. b. METRO is also enhancing the 56 Antoine/Montrose route, which stops at the NLTC, into a Bus Operations Optimized Service Treatments (BOOST) route. BOOST routes will have higher frequency and upgraded amenities, such as next bus information, branded shelters and signage, and transit-friendly signal timing.

Yes

a. The new NLTC will be larger than the existing facility and will enhance the connectivity of the Northline community to the overall METRO network with more bus routes and parking capacity, expanding access to jobs and education.

a. Ridership counts taken in 2019 show that approximately 3,450 daily boardings between bus and METRORail.

a. The NLTC is located on Fulton Street and Crosstimbers Street, less than a half-mile from North Freeway (IH 45 N), a Hurricane Evacuation Route. In the event of an evacuation, the NTLC could serve as a collection point for the community and a location to stage bus service for evacuation.

Other Investment Category Focused Criteria

Yes

The Northline Transit Center (NLTC) is located adjacent to the METRORail Red Line Northline station, the terminal station. The NLTC will connect local bus routes and the METRORail Red Line, as well as area drivers via structured parking.

a. The Northline Transit Center (NLTC) is located adjacent to the METRORail Red Line Northline station, the terminal station. The NLTC will connect local bus routes and the METRORail Red Line, as well as area drivers via structured parking. b. No truck only lanes are proposed. c. Intersection improvements in the form of signal timing are proposed at Fulton Street and Deerfield Street. A new signal is proposed at Fulton Street and the HCC entrance.

a. The proposed NLTC will be served by the 56 Airline/Montrose BOOST route, which is designed to optimize service and transit treatment to provide a “Better Walk, Better Stop and Better Ride”. BOOST routes will have enhanced amenities with greater accessibility. b. METRO is making Universal Accessibility (UA) improvements throughout the METRO Service area to better connect bust stops and shelters to meet or exceed ADA standards. c. The City of Houston proposes bike lanes on the same block of Fulton Street as the proposed NLTC. d. Finally, the proposed NLTC will have a drop-off area with bicycle parking and pedestrian access to better serve active transportation.

a. The proposed NLTC is located at near Fulton Street and Crosstimbers Street. It is not on any truck routes nor adjacent to a bridge over the Houston Ship Channel. The project is located outside of the 100-year and 500-year floodplains. Drainage improvements will also be included in the project to mitigate any additional drainage needs from the project.

a. The NLTC will be a new facility designed and constructed to METRO’s high standards. The facility will not be in the floodplain and will be designed to accommodate additional drainage needs from the project. b. The new facility will be included in METRO’s Asset Management Plan.

Planning Factors Criteria

Traffic fatalities within a half-mile of the project site from 2019-2023 include: a. 9/30/2023 – Bauman Rd. @ Julia St. b. 9/24/2022 – IH 45 @ Crosstimbers St. c. 10/17/2021 – IH 45 @ Crosstimbers St. d. 11/29/2020 – IH 45 @ Crosstimbers St. e. 11/04/2020 – IH 45 Frontage Road @ Crosstimbers St. f. 11/29/2020 – IH 45 @ Airline Dr. g. 10/19/2019 – Berry Rd. @ Fulton St.

Traffic serious injuries within a half-mile of the project site from 2019-2023 include: a. Four in 2023 b. Two in 2022 c. Five in 2021 d. Four in 2020 e. Two in 2019

a. The proposed NLTC will offer improved connectivity for transit users and allow automobile drivers to access bus and rail facilities, reducing the need travel in congested freeways.

Resiliency

Low

High

a. The project is located outside of the 100-year and 500-year floodplains. Drainage improvements will also be included in the project to mitigate any additional drainage needs from the project.

Access/Connectivity

4153

6106

No

Yes

Yes

Environmental Justice

4153

6106

1392

462

237

1,589

62.4

a. The proposed NLTC connects local bus, and automobile traffic with METRORail enabling travelers to Downtown to avoid the congested IH 45, as well as allowing customers to connect to transit service serving destinations across the northern part of the service area. b. METRO is making Universal Accessibility (UA) improvements throughout the METRO Service area to better connect bust stops and shelters to meet or exceed ADA standards. c. Finally, the proposed NLTC will have a drop-off area with bicycle parking and pedestrian access to better serve active transportation.

a. The new NLTC will be larger than the existing facility and will enhance the connectivity of the Northline community to the overall METRO network with more bus routes and parking capacity, expanding access to jobs and education. b. A Categorical Exclusion (CE) was approved for the new NLTC that recognized the project’s benefits to the primarily low-income and minority community (attached). The findings of the Environmental Justice analysis for the project determined that there were no disparate or disproportionate impacts on low-income and minority populations.

Impacts on Natural and Cultural Resources

a. The project is located outside of the 100-year and 500-year floodplains. b. There are no cultural resources impacted by the project as documented in the project CE.

a. The NLTC will provide a safe and convenient connection for transit customers by expanding the facility to accommodate more existing bus routes and METRORail service: therefore, emissions reductions are negligible. b. As an approved bus transfer facility in a conforming RTP and approved in the TIP, the project is exempt from air quality analysis.

Innovation

Yes

a. The proposed NLTC connects local bus, and automobile traffic with METRORail creating a multi-modal center enabling travelers to Downtown to avoid the congested IH 45, as well as allowing customers to connect to transit service serving destinations across the northern part of the service area. b. METRO is also making Universal Accessibility (UA) improvements throughout the METRO Service area to better connect bust stops and shelters to meet or exceed ADA standards. c. Finally, the proposed NLTC will have a drop-off area with bicycle parking and pedestrian access to better serve active transportation.

No

Additional Documents