Major Projects Questionnaire
Project Information
Agency Name | TxDOT Houston District |
Project Title | US 290 Widening |
Facility/Street/Highway | US 290 |
Limits | From Washington County Line to SH 6 |
Description | Reconstruct and wide from 4 to 6 lanes. This project will widen the existing highway to the middle adding a third lane in each direction. |
Timeframe | Medium Term (6-10 Years) |
Estimated Cost | $188,640,000.00 |
Regional Transportation Plan Goals
According to the 2045 RTP, this project falls under H-GAC’s Manage, Maintain, and Expand strategies, which collectively directly support all five of H-GAC’s goals of improving safety, achieving/maintaining a state of good repair, moving people and goods efficiently, strengthening regional economic competitiveness, and protecting cultural and natural resources. [1] Improve Safety: This project will provide additional capacity to the roadway and reduce primary and secondary crashes caused by congestion. [2] Achieve & Maintain State of Good Repair: In a widening/reconstruction project, old pavement is removed and new pavement is constructed, thus increasing the state of good repair. [3] Move People and Goods Reliably and Efficiently: This project will reduce congestion and reduce resulting crashes, increasing the reliability of the facility. This project is supporting the nearby RCR Hempstead Rail Logistics Park that is under development. [4] Strengthen Regional Economic Competitiveness: This project will reduce congestion and resulting crashes, increasing the truck travel time reliability of the facility, boosting regional and economic competitiveness. This project is supporting the nearby RCR Hempstead Rail Logistics Park that is under development. [5] Conserve and Protect Natural and Cultural Resources: This project will include improved drainage that will meet or exceed ATLAS-14 standards, which will benefit the natural resources abutting the facility. This project will reduce emissions caused by idling and congestion.
Regional Significance
Roadway
Principal Arterial or Higher Functional Class
Potential Crash Reductions
1.33
5.763
Crash rates for this segment are per 100 million VMT. The fatality rate is 1.33, higher than the regional average (1.23), and the serious injury rate is 5.763, lower than the regional average (6.18). The reconstruction and widening of the roadway from an existing four-lane to a six-lane divided roadway will provide additional capacity to the roadway and reduce primary and secondary crashes caused by congestion. The addition of pedestrian and bicycle infrastructure will allow cyclists and pedestrians to safely use the facility and reduce points of conflict with vehicles, thus improving the overall safety of the segment. The widening of medians reduces the quantity and severity of crashes at intersections and provides refuge to crossing pedestrians. As an access management strategy in corridors, medians reduce mid-block left turn-related crashes. They enhance traffic flow and can be used as part of a traffic calming strategy to reduce speed. The consolidated crash reduction factor for this project is 93%, as a result of installing sidewalks (WC 407), and providing additional travel lanes (WC 517).
Potential Congestion Reductions
No
1.0 – 1.25
Travel Time Index (TTI) is a ratio that compares peak period travel times along a corridor to average travel times, thus estimating a relative level of rush hour congestion. Current TTI for the project area is 1.00, indicating that it takes 1.00 times as long to travel this corridor in the peak period than average, which is mildly congested.
This project will reconstruct and widen from 4 to 6 lanes divided with a 10 ft shared use path on the EB side of the project. This project will widen the existing highway to the middle adding a third lane in each direction. The segment will be brought up to TxDOT and FHWA safety design standards.
Connectivity to Jobs, Medical Facilities, and Activity Centers
Yes
256
No
Yes
This project will increase connectivity to a RCR Hempstead Rail Logistics Park under development near this project (goods movement and jobs). Downtown Hempstead (activity center) is right outside the 1/4 mile buffer on this corridor as well. This project will also improve connectivity to Brenham in Washington County and eventually north Austin.
State of Good Repair
52
Poor
The segment contains pavement in Poor condition, according to TxDOT and FHWA guidelines. This segment contains bridges in Fair condition, according to FHWA guidelines. The worst bridge on this project segment was built in 1972. It is rated as being in Fair condition overall, with a superstructure condition score of 6, substructure condition score of 6, and a deck condition score of 7. In a widening/reconstruction project like this project, pavement is removed and new pavement is constructed, thus increasing the state of good repair and extending the service life of the facility.
Biking and Walking Conditions
Widening will be done in the median and a 10 ft shared use path will be constructed on the south side of the right of way according to the current schematic. Shared use paths provide a low-stress experience for active transportation users, increasing user safety and health while improving regional connectivity.
Impacts to Vulnerable Populations
2,826
4,689
1,226
430
442
375
52.40
The area surrounding the project segment has a higher low-income population (18.24%) as compared to the regional average of 13.5%. The area surrounding the project segment has a higher minority population (69.75%) as compared to the regional average of 65% minority. Because of its central location in the regional network, the project will produce improvements in mobility and connectivity for vulnerable populations as well as connectivity to schools (nearby Hempstead ISD or Texas A&M University up SH 6), medical facilities, and social services (nearby Texas Health and Human Services Commission office) for the regional population. The facility is designated as a hurricane evacuation route. As a result of the improvement, vulnerable populations will have increased resilience and evacuation capacity in the event of hazards. The project will improve drainage to ATLAS-14 standards, which reduce flooding events and their impact on vulnerable populations. As a result of the improvement, vulnerable populations will have increased resilience and evacuation capacity in the event of hazards.
The area surrounding the project segment has a higher low-income population (18.24%) as compared to the regional average of 13.5%. The area surrounding the project segment has a higher minority population (69.75%) as compared to the regional average of 65% minority. TxDOT’s Environmental Process is designed to ensure compliance with Title VI of the Civil Rights Act of 1964, and the Executive Order on Environmental Justice. Standard practice is to implement projects that provide user safety and operational efficiency while taking into account environmental quality and impacts to surrounding communities. In practice this means identifying and assessing potential project impacts, then proposing measures to avoid, minimize and/or mitigate disproportionately high and adverse effects to Environmental Justice Populations. For example, the project will improve drainage to ATLAS-14 standards, which will mitigate impacts from added capacity to vulnerable populations. A noise analysis will be conducted as part of the NEPA process to determine if sound walls will be needed or not for a widening project like this.
Hurricane Evacuation Route
Yes
Additional Documents
2023HGAC-CFP-CR-LOS-City of Pattison - Mayor (All Waller Co Projects).pdf
2023HGAC-CFP-CR-LOS-Waller County - County Judge (All Waller Co Projects).pdf
2023HGAC-CFP-RGM-LOS-City of Pattison - Mayor (ALL RGM TxDOT Projects).pdf
2023HGAC-CFP-RGM-LOS-Port Freeport-Chairman (ALL RGM TxDOT Projects).pdf
2023HGAC-CFP-RGM-LOS-Waller County-County Judge (ALL RGM TxDOT Projects).pdf