Who is Completing the Application?

Please provide contact information for the person who will complete the online application for this project. The email address and password entered here will be used to complete and submit both Pre-Applications and Applications.

Megan Campbell

Planner

713-802-5325

[email protected]

Primary Agency Information

Please provide contact information for the agency official who is representing the project sponsor. This individual will be considered the official applicant and must be authorized by their agency to submit this request for funding and make necessary assertations and representations on the agency’s behalf.

Texas Department of Transportation - Houston

Quincy Allen

District Engineer

713-802-5000

[email protected]

7600 Washington Avenue

Houston

TX

77007

Additional Agency Information

Project Information

FM 1960/ Cypress Creek Pkwy Sidewalks

Harris County

FM 1960/ Cypress Creek Pkwy

SH 249 to I 45

The existing sidewalks along FM 1960/ Cypress Creek Pkwy 6 between 249 and I-45 are not well connected considering the high demand of accessing nearby bus service, commercial services, and medical care. There’re high density residential apartments both sides along the FM 1960/ Cypress Creek Pkwy. Very few intersections and segments in front of the commercials have existing sidewalks. The proposed segments are along METRO bus route. Safe access to bus stops is needed. A few medical facilities currently locate along the FM 1960/ Cypress Creek Pkwy near I 45 while sidewalk coverage is not continuous. All of these make it difficult for local residents to access commercials, restaurants, hospitals, and transit service.

Construction of ADA accessible sidewalks from SH 249 to I 45.

The project is provided to address the lack of continuous and safe pedestrian access along FM 1960/ Cypress Creek Pkwy. New sidewalk will be installed to fill the gaps. Greater access to surrounding shops, restaurants, and services will be provided, while pedestrian travel safety will also be improved.

No

No

Less than $100 million

Active Transportation

5680924

HOU_87_AT_SH6 - Letters of Support.pdf

Project Development/Readiness

Not Started

Categorical Exclusion (CE)

02/01/2021

(c)(3) Construction of bicycle and pedestrian lanes, paths, and facilities

No

No

No

Yes

No

No

No

HOU_87_FM1960_SH6 - Timeline.pdf

FM 1960/Cypress Creek Parkway Project Readiness No Advanced Funding Agreement (AFA) will be needed for this project since TxDOT will provide the 20% match, which reduces the project timeline by 6-12 months for the AFA process. No permits from the Army Corps of Engineers, US Coast Guard, and railroad are expected to be required before the project can be constructed. No documentation is needed from the State Historic Preservation Office (SHPO). TxDOT’s Houston District Environmental Section has reviewed the project and indicated that the criteria for FHWA Categorical Exclusion Action (c)(3) Construction of bicycle and pedestrian lanes, paths, and facilities would be appropriate for this project. This project does not require additional acquisition of right-of-way (ROW), no ROW acquisition and/or easements is needed. TxDOT proposed sidewalk improvements on S FM 1960/Cypress Creek Parkway leverages the construction of 7,555 SY in ADA-compliant ramps and 5,839 SY miles of sidewalk gap-fillers built as part of CSJ 0912-00-101. As a result, no ADA ramps are included in the proposed project.

HOU_87_FM1960_SH6 - Project Readiness.zip

Map/Location

HOU_87_FM1960_SH6 - Location Map.pdf

Project Budget

HOU_87_HGAC_Template.xlsx

No

Benefit/Cost Analysis

TxDOT - Ped Roadway Safety Benefit - SH 6 Sidewalk.zip

10302018104320PM.xlsx

TxDOT - Ped Emission Benefits - SH 6 Sidewalks.xlsx

HOU_87_SH 6_Additional Information.zip

SH 6 Daily User Methodology Generation Methodology A Bicycle and Pedestrian Demand Sketch methodology (Greg Griffin) was utilized to generate daily bicycle and pedestrian volumes for the SH 6 Facility. This methodology utilizes American Community Survey commuting mode share data (Subject Table “S0801 Commuting Characteristics by Sex”) to estimate mode shares along the facility for both bicycle and pedestrians. To develop the most accurate estimate of mode share for each project, buffers were utilized to account for surrounding land uses and area types. A 1.5-mile buffer was utilized for pedestrian projects and a 5-mile buffer for bike projects. ACS data within these buffers was averaged to generate a likely mode share for both bike and pedestrian modes. This data was then applied to traffic volumes generated from the regional travel demand model to estimate daily user bike and pedestrian trips. For the SH 6 Facility, only an estimate for daily pedestrian users was generated. The specific process utilized to develop daily user estimates is outlined below: Assemble mode share and roadway network data • ACS data collection for city/county/MPO bike and pedestrian commute share • Pull ADT information from regional model for appropriate network links parallel or nearby project facilities • Load data into GIS • Identify ACS Block Groups within buffer range to generate ACS mode share estimates Apply pedestrian rates to roadway segments • The direct ACS pedestrian mode share was applied to the SH 6 project as a proportion of current and/or projected vehicular volumes along specific roadway segment to develop estimated daily users. Transit ridership estimates were utilized to determine that this method was more feasible than applying the sketch planning multiplier. Interpolate to Estimate Build Year Daily Users • The HGAC Model Years are 2018, 2025, and 2045. To estimate the “build year” daily users, an interpolation was applied to develop estimates for 2021, 2022, 2023, and 2024. Reasonableness Check • A reasonable check was conducted by reviewing local information and transit ridership information to assess the reasonableness of user estimates generated in the previous steps. This methodology resulted in reasonable estimates of pedestrian users in the year op

Planning Factors - Barrier Elimination (Active Transportation)

Yes

No

Planning Factors - Emissions Reductions

0.99 tons/year NOX

0.28 tons/year VOCs

Planning Factors - Environmental Justice

Yes

Yes

Planning Factors - Expands or Improves Bicycle & Pedestrian Connectivity to Employment/Schools/Medical Facilities/Transit Stops/Other Points of Interest

Yes

901 - 1000

Yes

Yes

Yes

Yes

Planning Factors - Planning Coordination

Yes

H-GAC’s Cypress Creek Pkwy Livable Centers Study and the FM 1960 Access Management Study (2004)

http://www.h-gac.com/community/livablecenters/planning-studies/cypress-creek-parkway.aspx http://www.h-gac.com/taq/access-management-studies/documents/fm1960-Final-Report.pdf