Amendment Number Date of Approval Type Description

May-20

5/22/2020 TPC Funding Modification - 2 projects

May-20

5/29/2020 Administrative Scope Modification - 4 projects

Apr-20

N/A TPC No amendments.

Apr-20

N/A Administrative No amendments.

Mar-20

3/27/2020 TPC Funding Modification - 20 projects
Scope Modification - 2 projects
Schedule Modification - 2 projects

Mar-20

3/30/2020 Administrative Funding Modification - 9 projects
Scope Modification - 4 projects

Feb-20

2/28/2020 TPC Funding Modification - 19 projects
Scope Modification - 16 projects
Schedule Modification - 17 projects

Feb-20

2/28/2020 Administrative Schedule Modification - 1 project

Jan-20

1/24/2020 TPC Funding Modification - 19 projects
Scope Modification - 16 projects
Schedule Modification - 17 projects

Jan-20

1/24/2020 Administrative Scope Modification - 6 project
Schedule Modification - 4 projects

Nov-19

11/22/2019 TPC Funding Modification - 3 projects
Scope Modification - 3 projects
Schedule Modification - 2 projects

Nov-19

11/22/2019 Administrative Scope Modification - 1 project
Schedule Modification - 3 projects

Oct-19

10/25/2019 TPC Funding Modification - 7 projects
Scope Modification - 9 projects
Schedule Modification - 3 projects

Oct-19

10/25/2019 Administrative Scope Modification - 8 projects - CSJ numbers and phase only

Sept-19

9/27/2019 TPC Funding Modification - 7 projects
Scope Modification - 7 projects
Schedule Modification - 7 projects

Sept-19

9/27/2019 Administrative Funding Modification - 2 projects
Scope Modification - 12 project
Schedule Modification - 118 projects

Aug-19

8/23/2019 TPC Funding Modification - 25 projects
Scope Modification - 25 projects
Schedule Modification - 25 projects

Aug-19

8/23/2019 Administrative Funding Modification - 5 projects
Scope Modification - 1 project
Schedule Modification - 7 projects

Jul-19

7/26/2019 TPC Funding Modification - 3 projects
Scope Modification - 3 project
Schedule Modification - 3 projects

Jul-19

7/26/2019 Administrative Funding Modification - 7 projects

Jun-19

6/28/2019 TPC Funding Modification - 28 projects
Scope Modification - 26 projects
Schedule Modification - 25 projects

Jun-19

6/28/2019 Administrative Funding Modification - 2 projects

May-19

5/24/2019 Administrative Funding Modification - 3 projects
Scope Modification - 5 projects
Schedule Modification - 3 projects

Apr-19

4/5/2019 TPC Funding Modification - 30 projects
Scope Modification - 19 projects
Schedule Modification - 19 projects

Apr-19

4/5/2019 Administrative Funding Modification - 1 projects
Scope Modification - 1 project
Schedule Modification - 8 projects

Mar-19

3/22/2019 TPC Funding Modification - 3 projects
Scope Modification - 2 projects
Schedule Modification - 3 projects

Mar-19

3/22/2019 Administrative Scope Modification - 1 project

Feb-19

2/22/2019 TPC Funding Modification - 2 projects
Scope Modification - 1 project
Schedule Modification - 2 projects
Feb-19 2/22/2019 Administrative Scope Modification - 1 project

Jan-19

1/25/2019 TPC

Funding Modification - Appendix D only
Funding Modification - Appendix D only
Schedule Modification - Appendix D only

Jan-19 1/25/2019 Administrative

Funding Modification - 1 project
Funding Modification - 1 project
Schedule Modification - 1 project

Dec-18 12/21/2018 TPC

Funding Modification - 6 projects
Funding Modification - 3 projects
Schedule Modification - 2 projects

Dec-18 12/21/2018 Administrative Funding Modification - 2 projects
Funding Modification - 6 projects - Descriptions & CSJ only
Schedule Modification - 2 projects

Oct-18

10/26/2018 TPC

Funding Modification - 2 projects
Funding Modification - 2 projects
Schedule Modification - 2 project

Oct-18

10/26/2018 Administrative

Funding Modification - 2 projects - Combine
Funding Modification - 9 projects - Various
Schedule Modification - 7 projects - Various

Sept-18

9/28/2018 TPC Funding Modification: 8 projects
Funding Modification: 6 projects
Schedule Modification: 7 projects

Sept-18

9/28/2018 Administrative Funding Modification: 3 projects - Split 14573
Scope Modification: 3 projects - Split 14573